Tuesday, October 18, 2016

Rigid flame retardant plastic pipes (PVC) laying technology for tomorrow

1 scope
This technology is applicable to indoor or acid and alkali corrosive lighting wiring installation installation (not above 40 c in places vulnerable to mechanical impact, friction collision and other places laying).
2 construction preparation
2.1 materials requirements:
2.1.1 where the use of flame-retarded (PVC) plastic pipe, the material should have a flame retardant, impact resistance, flame retardant indicator of its oxygen should not be less than 27%, and verification reports, and product certification.
2.1.2 fire retardant plastic, continuous flame retardant outer wall should be spaced not more than 1M marks and factory mark. Pipe miles away should be smooth, no ridges, dents, pinhole, bubble; inner and outer diameter should be in line with national standards, tube wall thickness should be uniform.
2.1.3 use flame retardant plastic attachments and flame retarded plastics products, such as lamp box, switch boxes, junction boxes and socket boxes, pipe straps, you must use the fire retardant plastic products.
2.1.4 adhesive must be used with flame retardant plastic pipe accessory products, adhesive must be used within a specified period is used.
2.2 the main tools:
2.2.1 ruler, tape measure, pencil, tape measure, level gauge rod, square, wire pendant, small line, pink bags.
2.2.2 hammer, chisel, and hacksaw, saw blade, knives, cabinet file, live spanner, ash bucket, bucket, etc.
2.2.3 pipe spring (bending springs for short), pipe-cutting, hand drill, bench drill, drills and pressure case.
2.2.4 electric hammer, air heater, electric stoves, Hole saws, insulating gloves, tool bags, toolboxes, pipe-simmer, high stools.
2.3 operating conditions:
2.3.1 when mixing concrete structure construction, according to the design drawings in beam and plate, under the column tube and pipe.
When construction of the brick structure 2.3.2, embed a large pipe, angle steel bracket and tube.
2.3.3 in the renovation before the construction level and thickness of the plastering and piping, line casting according to design embedded parts and stability with angle brackets.
2.3.4 spraying is complete, installation for piping and all kinds of cartridges, boxes, and prevention of pollution from pipelines.
3 operational processes
3.1 process:
Prefabricated, and hangers iron determination of box and pipe and tube bending fixed point position of fixed line

Pipeline laying pipe into the box deformation joint practice
3.2 in accordance with design machined bracket, hanger, anchor, iron castings and pipe bends.
Preformed pipe bending cold simmer method and heating method can be used.
3.2.1 environmental temperature of the flame retardant plastic pipe laying and simmering bending requirements are as follows: the laying of fire-retardant Plastics pipes and fittings, installation and simmering bending production, should be carried out on raw materials for the permissible ambient temperature, temperature is not lower than-15 degrees centigrade.
3.2.2 cold simmer method:
Diameter in the 25mm and the following cold simmer method can be used.
3.2.2.1 use lever bent tube simmering bending, tube insert supporting pipe Bender, needed for the lever a simmering curves shown in Figure 3-l.
3.2.2.2 insert the bending spring (PVC) tubes need to simmer bend, his hands gripping bend both ends of the spring head, knee bend, camber lever gradually simmer required, and bending springs (when bending a long tube, bending springs with wire or nylon line can be tied on one end, simmering bending when you are finished taking).
3.2.2.3 heating method: electric stove, hot, heats evenly, bake simmer bend of the pipe until the pipe is heated to optionally bending, pipe placed on the Board immediately, fixing pipes, gradually simmer the pipe bend required, wipe with a damp cloth to cool curve shape, and bending springs. Not due to roast simmer bend the pipe damage, discoloration, cracking phenomenon.
3.3 determination of boxes, cartons and fixed line point location:
3.3.1 measured in accordance with design drawings, such as boxes, cartons, and outlet position. When measuring, use homemade gauge rod, line positioning.
3.3.2 under boxes, boxes for the determination of position, vertical lines horizontal lines pop up, mark the bracket according to the request, hangers fixing points size.
3.4 fixed line method:
3.4.1 tube method: first punch holes in the wall, the tube into the hole, again with screws (bolts) fixing.
3.4.2 method of wooden bricks: using wood screws directly to the embedded on the wooden block.
3.4.3 embedded iron welding method: with the civil construction, according to the determination of position of embedded iron parts. After stripping, brackets, hangers welded on the embedded iron parts.
3.4.4 stability methods: with construction brick masonry, the bracket is secured.
3.4.5 the stability methods: built with masonry walls, the bracket is secured.
3.4.6 tick methods: according to the determination of position, remove wall (port should be picking bigger inside the cave), wet hole with water, then up high-grade mortar to fill the hole, after the brackets, and hanger or bolt into the hole in the correction of buried deep and straight, is correct, erase the hole.
3.4.7 clamp method: according to the determination of position, when it encounters a beam, full collar, hanging the bracket is secured.
3.4.8 regardless of the method, should be both fixed bracket, hanger, bracket, then pull the line fixed the Middle hanger.
3.5 tube:
3.5.1 broken pipe: small-diameter pipe-cut can be used, large diameter using a hacksaw cut flush nozzle file after the fracture.
3.5.2 application tube, first pipe clamp at one end of the screws (bolts) tightening by half and conduit inside a pipe clamp, tighten one by one.
3.5.3 brackets, and hanger is correctly positioned, evenly spaced, solid tube kayingping; buried bracket dovetail, embedding depth shall be not less than 120mm bolted through the wall is fixed, add washers and springs behind pad nut is tight and firm.
3.5.4 pipe laying, height shall be not less than 2000mm; vertical installation, not less than 1500mm (1500mm protection pipe should be added).
3.5.5 when a longer pipe laying, when they exceed the following, should be added to the junction box;
3.5.5.1 line when there is no bending, 30m;
3.5.5.2 pipes have a turn, 20m;
3.5.5.3 pipeline when there are two curved, 15m;
3.5.5.4 pipeline has three corners, 8M;
3.5.5.5 cannot be installed at the junction box, tube diameter should be increased first.
3.5.6 brackets, hangers and laying pipe clamp fixed on the wall dots and boxes, boxes from the edge of 150~300mm, pipe middle distance shown in table 3-1.
3.5.7 wiring and piping between the minimum distances shown in table 3-2.
3.5.8 piping connections:
3.5.8.1 pipe should be smooth; pipes with pipes, tubes and boxes (boxes) and other devices should be connected by the Insert method, surface should be coated with special rubber mixture at the connection, the interface should be firmly sealed.
3.5.8.2 when used between tube and tube cuff, sleeve length straight to 1.5~3 times the tube diameter; pipes and tubes
Counterparts should be located in the casing on the flat.
3.5.8.3 tube and device connections, depth appropriate to 1.1~1.8 times the pipe diameter.
3.5.9 tube:
3.5.9.1 pipes and brackets, hangers should be mounted straight, strong, neat, pipe bends, no significant creasing, concave flat.
3.5.9.2 bend RADIUS and bend the flat shall conform to the specifications.
3.5.10 straight tube should be installed every 30m compensator, compensator joint head with straight sets in and glued at one end (PVC) section head and glued on the tube, and then the small end into the clamping ring, small end can slide inside the ring. Compensator installation diagram. As shown in Figure 3-2.
3.5.11 (PVC) pipe leads to the ground, you can use a section of pipe leads, but the need to make the appropriate transition-specific coupling, coupling embedded in the concrete and steel pipe, steel pipe casing grounding or the zero connection protection. (PVC) pipe and pipe connection as shown in Figure 3-3.
And brackets, and hanger should be straight, strong, neat; pipe bends, no significant creasing, concave flat.
4.2.2 box, box is set up correctly, reliable, it tube box, the box, apply adhesive, adhesive tight and firm when end connector with lock, tighten the cartridge wall is not loose.
Inspection method: observation and standard checks.
4.2.3 pipeline should satisfy the following requirements:
Through the deformation joints compensator, compensator can move freely through buildings and equipment, should protect pipe compensator smooth, pipe smooth, lock and reliable connection of the pipe; and protection pipe correctly marked in a hidden project records.
Inspection method: observation on concealed works of checking and inspection records.
4.3 allowable deviation:
Hard (PVC) plastic pipe bending radius installation tolerances and testing methods should be consistent with table 3-3.
5 finished product protection
5.1 laying pipe, keeping the walls, ceiling, floors clean complete. Repair iron paint, not contaminated buildings.
5.1.1 construction when the stool is used, not the collision wall, corner, door, window but not state high stools against the wall; high stool foot Binder, scratch-resistant flooring, anti slip.
5.1.2 handling objects and equipment without crushing lines and boxes, cartons.
6 quality problems to be noticed
6.1 set of hoops, looseness, plug in place, adhesive which could have uneven, small brush evenly supporting the supply of adhesive inserts turn the insert in place.
6.2 when simmered with large diameter bend, with a concave flat and roast injury, discoloration, cracks. Baked baking area is small, uneven heating should be sand furnace indirectly grilled or baked with water. Larger area, heat should be uniform, and there is a simmering.
6.3 pipeline laying there are vertical and horizontal overload and unbalanced, it tube cards uneven spacing. Fixed pipe clamp without cable, resulting in horizontal error; error measurements using a tape measure, use a spirit level to review, always point level, then line fixed pipe clamps, fixed up the final two points, the Middle pipe clamp, select products, and measured with a gauge Rod pipe clamp fixed height.
7 quality records
7.1 flame retardant type (PVC) plastic pipe and accessories test reports and product certification.
7.2 rigid flame retardant plastic tubes laid out pre-inspection, self-inspection, mutual inspection records.
7.3 change record of negotiation and completion.

7.4 project for quality inspection and assessment records.