1 scope
This technology is applicable for
industrial and civil construction ground concrete liner construction
operations.
2 construction preparation
2.1 materials and equipment:
2.1.1 cement: Yi No. 325, Portland cement
and ordinary Portland cement and slag Portland cement.
2.1.2 sand: sand or coarse sand, clay is
less than 5%.
2.1.3 the gravel: gravel or crushed rock,
size 0.5~3.2mm, clay is less than 2%.
2.1.4 concrete mixers, scales, trolleys or
dump truck, a sharp spade, shovel, plate vibrator, barrels or chute, scratch
poles, wood trowel, rubber pipes, iron chisel and wire brush.
2.2 operating conditions:
2.2.1 quality of structure engineering has
completed the acceptance procedure, door frame is installed, has been playing
around the wall good +50cm level elevations.
2.2.2 the warm, guard pipelines across the
floor was installed, it tube hole has fine stone concrete pouring and packing
density.
2.2.3 laying horizontal tube has been done
in the cushion and finished the hidden procedures.
2.2.4 in the pouring of the first floors
before concrete pad, heating Groove and Groove through the Interior heater has
done, finished and through the acceptance procedure of drainage pipe, indoor
backfill for quality inspection and assessment.
3 operational processes
3.1 process:
Base treatment → find levels
of elevation, elastic control vibrating line laying concrete concrete mixer → → → →
Leveling → conservation
3.1.1 base treatment: bonded on concrete
laitance, loose concrete, mortar, scrape with a cold chisel, use wire brush
away the cement slurry, and then use a broom to sweep.
3.1.2 bomb find elevation level control
line: according to the level of +50cm on the wall elevations, measure down
cushion height, there are conditions to play around on the wall.
3.1.3 concrete mixer
3.1.3.1 mix (its strength not less than
C10), check the background materials, check the accuracy of the scales, made
mixing all the preparations before. Back-office operators carefully according
to the concrete mix feed, each release order are stones → → → cement sand water.
Should strictly control the water, stirring to evenly, mixing time in the 90s.
3.1.3.2 of the surface engineering of
building construction and acceptance specification for requirements of the
production block. Block group number, in terms of surface engineering of
architecture on each floor should not be less than one group. When each layer
of surface engineering of building area of more than 1000m2, for each
additional 1000m2 each of a set of blocks, less than 1000m2 on a 1000m2 basis.
3.1.4 the laying of concrete: concrete pad
thickness should not be less than 60mm. In order to control the smoothness of
the cushion, the first floors in the filling into small stakes
(30mmx30mmx200mm), the horizontal elevation line flat on the mat at the stake
marks (about 2m). In the floor on the concrete base 100mmx100mm, leveling Pier
(with fine stone concrete), DUN glazing for elevation on the cushion.
Large cushion sections should be poured on
the ground. Partition in relation to slot location of ground connection,
different materials and device based location, divided.
Prior to the laying of concrete spraying
water on the grass-roots moist, brushing a layer of pigment slurry (water than
for 0.4~0.5), and then start laying from end, from the Interior to the outside
back operation.
3.1.5 vibration: paving concrete with a
spade, the thickness of slightly higher than the level, then plate vibrator
vibrating. Thickness of more than 20cm, the vibrating needle should be used,
and its radius of action of moving distance of not more than 1.5 times, do not
leak, and ensuring concrete density.
3.1.6 leveling: after vibration compacting
of concrete, horizontal level line on the wall and leveled to check for
smoothness, high off a, hollow fill. Horizontal wood bars scraper scrape, rub
wooden trowel flat on the surface. There are slope requirements of the ground
should slope according to design requirements.
3.1.7 conservation: has finished pouring
concrete pad, should be covered by 12h and water conservation should not be
less than 7d.
3.1.8 winter operation, the ambient
temperature should not be below + 5 c. Under negative temperature, such as
construction, with antifreeze must be qualified through laboratory tests before
use. Chloride content shall not be greater than the weight of cement 3%. Is
less than, equal to, C10 concrete, in front of the cold concrete of compressive
strength shall not be less than 5.0N/mm2.
4 quality criteria
4.1 project
4.1.1 cement used in concrete, water,
aggregate and additives must comply with the provisions relating to the
construction and.
4.1.2 concrete mix proportion, measurement
of raw materials, mixing, conservation and construction joint treatment must
comply with the provisions of the code.
4.1.3 evaluation of concrete strength of
blocks must be in accordance with the standards of inspection and evaluation of
concrete strength (GBJ107-87), sampling, production, maintenance and testing,
which must comply with the provisions of the code.
4.2 allowable deviation, as shown in table
7-2.
Bedding concrete ground tolerance table 7-2
Serial number item tolerance (mm) test
method
10 2m m on foot and 1 surface flatness
wedge feeler Gage check
2 elevation ± 10 use level to check
3 incline less than 2/1000 of the relative
size of the room, and not more than 30 adjustable triangle check
4 thickness in some places no more than
1/10 feet in thickness check
5 finished product protection
5.1 in the pad of poured layer of concrete
intensity after 12MPa can only be allowed in their walk and carry on other
operations.
5.2 in the construction process, the attention
to transport concrete car don't touch moving door frame (should be protected in
advance), and in the laying of concrete to protect electrical devices such as
pipe.
5.3 concrete pad poured out to meet the
conservation time, continued construction of surface layer, such as continued
construction, the cushion should be covered to protect and avoid mixing mortar
on the cushion. Store the bucket so as to avoid contamination, such as bedding,
affect the bond strength of surface layer and layer and causes surface layer
hollowing.
6 quality problems to be noticed
6.1 not compacting: mainly due to leakage
vibration and vibration is not compact, or mix allowed and caused by the
improper operation. Basement sprinkler at the end is too dry and the cushion is
too thin, can also cause imperfect.
6.2 surface irregularities, levels are not
allowed to: operation is not serious when leveling. Paving concrete must be
based on the horizontal line while mastering the laying of concrete thickness,
vibration level again after checking smoothness, high after filling, with a
wooden scraper bar horizontal (or small stakes) for the standard shave.
6.3 irregular cracks: cushion size is too
large, not fragmented warehouse construction, first warming layer of ditch
cover plate is not concrete, backfill the first floors uneven sinking too much
cushion thickness less than 60mm or pipelines and other factors, can lead to
cracks.
7 quality records
This standard shall meet the following
quality records:
7.1 cement factory certificate.
7.2 quality assessment for concrete blocks
and concrete strength test record form.
7.3 ground waterproofing requirements,
waterproof material factory certification and testing records, hidden
inspection records.
7.4 cushion section for quality inspection
and assessment of concrete form.
No comments:
Post a Comment