1 scope
This technology is applicable to industrial and civil construction steel door and window installation.
2 construction preparation
2.1 materials and equipment:
2.1.1 steel doors and Windows: type, model, the design requirements, the manufacturer should have the quality certification of products, and products of the factory certificate, to enter the construction site quality acceptance.
2.1.2 steel yarn fans: type, model with steel doors and Windows support, and comprehensive accessories.
2.1.3 cement No. 325 and more sand in the sand or coarse sand.
2.1.4 all kinds of machine screws, flat iron layering, reserved hole with the reserved steel doors and Windows when installing Aperture, consistent spacing, installing steel doors and Windows and fixing method should comply with the design requirements.
2.1.5 the paint brush and the use of wire fabric shall be as per drawing requirements.
2.1.6 electrode grades should be commensurate with their welding requirements, and should have a factory certificate.
2.1.7 main equipment: welding machines, masks, welding wire, spade, a shovel or trowel, supporting Board and small wire, iron, wire, small buckets, wooden wedges, hammers, screwdrivers, etc.
2.2 operating conditions:
2.2.1 structure works have been finished, and acceptance of quality, work had been done between the transfer procedures.
2.2.2 have pressed the middle line of the drawing size to play the doors and Windows, and better indoor 50cm horizontal lines.
2.2.3 Windows Embedded iron parts stay good location according to its elevation, and meet the requirements upon examination. Reserved hole clean.
2.2.4 between doors and lintels concrete iron location, number of connections, meet the requirements upon examination, connect iron or location is not set, steel doors and Windows installation requirements completed.
2.2.5 installing steel doors and Windows should be checked before type, size. , Welding and deformation and warping defects such as processing meets the requirements before installation.
2.2.6 combination steel doors and Windows to make assembling the model, after acceptance until a large number of Assembly.
2.2.7 after correction or repair after processing the number of brush paint, and ensures uniform coat.
3 operational processes
3.1 process:
Doors and Windows installation location and elevation games fan vertical steel doors and Windows of the window wedge temporarily fix

Horizontal installation elevation of review, according to the review in the middle position welding

Plugging the hole accessories glass brushes paint fan yarn brushes paint

3.2 marking rules: according to the design drawings of the doors and Windows installation location, dimensions, elevations, to prevail on both sides of the window in the middle of the window edges to top level Windows and doors installation location, to find the doors and Windows on each floor installation location and elevation, respectively.
3.3 number requirement according to the drawing doors and Windows, steel doors and Windows, respectively to the installation location and cushion firmly to prevent collision injury.
3.4 Windows and doors in place, iron fixed foot inserts for reserved holes was hanging straight and ensure accurate location with a wooden wedge temporary fix, Windows box from the beam 2cm joints, it's about Aperture, width, from the outer wall meets the design requirements.
3.5 the balcony door Windows, can be assembled and then install or install Windows and doors, now spelled is installed, Word should be correctly positioned, alignment, hanging straight.
3.6 after Windows and doors made of steel, to check for location and elevation, meets those requirements, on box iron feet and beam welding of iron, and iron foot inserts for reserved holes on either side of the window, water wet, dense 1:3 stiff mortar to plug, and water conservation.
3.7 after the blinding mortar solidified, 1:3 door window frame into the cement mortar joints really, ensure the door window fixed.
3.8 Conference frayed yarn, yarn: yarn than the actual size of each side of the CD 50mm, Eli yarn. Tension and paving the way for the yarn at the yarn, layering on the pressure, compaction, machine screws tighten yarn even tighten the Batten is installed, loosen the screw, then put bead on both sides and tighten machine screws will cut excess yarn with a flat shovel off, to cut a clean without leaving any yarn.
3.9 yarn fans paint: stretch yarn should be brushed before you paint, mixed paint. Stretch yarns before installation and then paint, the other two mixed paint brush again after installation.
3.10 steel door and window paint prior to installing good anti-rust and breaker-mixed paint, brush with the Interior wood doors and Windows after the installation of two mixed paint.
3.11 hardware should wait for the paint to dry for installation if needed when first installed, care should be taken to prevent pollution and lost, damaged.
3.12 yarn installation of doors and Windows, such as brush well let's give the oil in the storerooms, and then installed again, to paint color should be consistent, and not hit touch the paint when you install to avoid secondary tonic and aesthetic impact, so let's give the oil the best brush again after installation.
3.13 winter rain during construction:
3.13.1 in winter, filling holes with pea stone concrete and mortar chinking should be high and low outdoor temperatures, mixed with a certain percentage of admixtures, concrete and mortar from the cold.
3.13.2 rain during construction, heavy rains suspend construction, installation of steel doors and Windows when rain, should be looking for is hanging straight fixed. Plugging the hole, pouring completed work should stay on sunny days.
4 quality criteria
4.1 project:
4.1.1 quality of steel doors and Windows and their accessories must comply with the design requirements and the provisions of the relevant standard.
4.1.2 installation of steel doors and Windows the location, direction of opening, you must comply with the design requirements.
4.1.3 steel doors and Windows installation must be firm; the number of embedded iron parts, positions, laying the connection methods must comply with the design requirements.
4.2 Basic project:
4.2.1 installation of steel doors sash should be closed tight, flexible, non-blocking, rebounding and Alice.
4.2.2 steel doors and Windows Accessories complete, correct position, securely, upright, opening and close flexibly applied.
4.2.3 steel door and window frames and wall cracks filled full of dense, smooth surface, materials and workmanship meet the design requirements.
4.3 allowable deviation: steel door and window installation box in side perpendicularity, door and window frame, door and window boxes two diagonal length difference, window fan clearance limit, window frame sector overlap limits shall conform to the values set out in table 8-2.

Steel doors and Windows installation tolerances and gap width table 8-2
Project tolerance (mm) test method

Door and window frame two diagonal difference 2000mm
>2000mm 5
6
Steel measuring tape to check angle
2 hinge 2 2x50 plug check the hinge surface
Window fan clearance limit hold 1.5x50 plug for hand 1.5 check box
3 frames overlap limits the fasting window concentration of 4 used steel dash and check
Solid Web window concentration of 2 steel dash and check
4 door and window frames (spell-containing Tang) are examined on a 3 1M supporting plate vertical side
5 door and window frame (including spelling Tang) level-3 1M level, and wedge-shaped feeler Gage check
6 when the doors without threshold, joints between the door leaf and the ground within limits 4~8 wedge feeler Gage check
7 outside the window frame, jamb (spell-containing Tang) Center from the 5 with a steel ruler to check

5 finished product protection
5.1 steel Windows and doors after entering, according to specifications, models, classified and piled up and tags indicating their specification, type and quantity of sheet cover, to prevent heap lying to prevent deformation and rusty steel Windows.
5.2 steel Windows and doors when transported with care and take protective measures, to avoid crushing, bump, to prevent damage.
5.3 when the plaster, mortar residues on the steel door window frame which should be cleaned up in a timely manner.
5.4 no Tang as a scaffold of steel doors and Windows point and fixed point, the Tang material compression; it is strictly forbidden to wooden rod fixed or tied to the scaffold on steel door and window frames to prevent displacement and deformation of steel doors and Windows.
When the 5.5 split rack, note that will open up the doors and Windows closed and falling shelves again to prevent the damaged steel Windows and doors.
6 quality problems to be noticed
6.1 warping and channeling angle: steel Windows and doors processing individual fans are there standards of quality: carefully in case of transport stack, not seriously kept; vertical flat installed enough, should be carefully checked before installation, find warping and angles should be corrected in a timely manner to repair, fix after installation.
6.2 iron fixed foot does not meet the requirements: original foot position for reserved holes and iron, and has no checking and handling before installation, during installation any gas welding burning iron feet, some iron foot bending cram into holes in the severely affected steel Windows installation firm.
6.3 steel doors and Windows are not straight up and down, steel doors and Windows around the elevation is not consistent: no process construction points, before the construction could not find the rules, no thread during installation.
6.4 steel door and window switches are not flexible: eat affect their flexibility when plastering; install vertical founder did not find a good, door and window splitting, channeling angle angled or after repair. Request check switch test was carried out after the installation of steel doors and Windows, is flexible, the effect switches the plaster layer should tick up again, door and window fans split ribs and shot angle should be adjusted.
6.5 opening direction is not in place: plastering quarrel not founder, or arch face drooping, convex lines are not straight, will directly influence the opening of doors and Windows. When plaster is required strictly according to the evaluation standards inspection, after the failed to fix, then woodworking installing doors and Windows.
6.6 the adjustment of steel doors and Windows, or processing such as welding, gas cutting and uncertain to solder coating does not hit, welding without steel fell file, don't brush paint.
6.7 steel Windows with water; when installing Windows, use errors, steel Windows keep. Should carefully check the window number, meets the requirements before installation, and pay attention to the protection of the pishui when stacked.
6.8 metal parts wood is complete and comprehensive, construction lost, second supplement and does not match the original brands. Request entry of steel and metal fittings at the same time supporting the processing and consider reasonable failure rate, processing orders at a time enough.
6.8 fans stretch yarn made of rough, hard waste exposed: gauze window sash and door does not fit on the CD, the aperture is too large, yarn tightly, or yarn head exposed.
6.9 press yarn using the self-tapping screws too long, sharp exposed easily hurt.
6.10 steel screen doors and Windows painted rough, or paint the exposed grass-roots dirt cleaned is not clean.
7 quality records
This standard shall meet the following quality records;
7.1 steel door and window factory certification, product acceptance certificate.
7.2 steel doors and Windows which are connected with the main structure of anchorages of laying hidden inspection records.
7.3 hardware accessories factory certificate.

7.4 quality inspection and assessment of records.