1 scope
This chapter applies to industrial and
civil building fire automatic alarm system installation work. Does not apply to
the production and storage of gunpowder, explosives, ammunition, pyrotechnics
and other explosive place settings of automatic fire alarm system installation
work.
2 construction preparation
2.1 after receiving the construction should
first drawings for triage, is familiar with charts, building plans, improvement
plans and other drawings, finding design issues affecting the construction organization
design intentions, solve problems in design and construction, deal with
technology changes communication construction methods and is equipped with the
corresponding labor, equipment, materials, machinery, etc. Equipped with a
complete set of life, temporary facilities.
2.2 the main equipment and materials:
2.2.1 General material selection for main
equipment of automatic fire alarm systems shall conform to 6-1, "General
requirements for the installation of fire engineering" of the relevant
content.
2.2.2 major equipment (see Figure 6-l)
Zone fire alarm control unit;
Central alarm control device;
Fire control equipment;
Image display and printing devices;
Fire emergency power supply;
Fire detectors (smoke, heat, gas, etc);
Manual fire alarm button;
Sound and light shows alarm;
Various modules (relay);
Linkage control and signal feedback
devices;
Fire communications equipment (such as the
fire service phones);
Fire radio equipment.
2.2.3 common materials:
Pipe, and steel, and line slot, and wire,
and cable, and metal hose, and fire Xu material, and shaped plastic pipe, and
flame retardant plastic pipe, and wiring box, and tube Hoop, and root mother,
and nursing mouth, and Guan Kazi, and electrode, and oxygen, and acetylene, and
wire, and wire, and rust paint, and expansion bolt, and expansion plug, and
sets screws, and welding oil, and solder, and battery, and oil, and saw, and
mark pen, and bandages,.
2.3 main equipment:
Sets Silk machine, and sets Silk Board, and
hydraulic simmering bent device, and manual simmering bent device, and welding
machine, and gas welding tool, and bench drill, and hand drill, and wheel saw,
and electric hammer, and open hole device, and line pliers, and shot nail gun,
and hacksaw, and hammer, and live wrench, and level feet, and ruler, and
square, and steel tape, and line pendant, and iron, and electric stove, and Tin
pot, and flat file, and round file, and pressure case, and pressure pliers, and
electrical tool, and high stool, and tool bags, and Toolbox, and universal table,
and trillion Ou Biao, and try Bell, and on told phone, and step phone, and try
smoke device, and mobile hair dryer machine, machines.
2.4 labour is equipped with:
According to the construction requirements,
arranging the construction schedule and workforce planning, duration, quality,
safety, equipment construction, electricians, welders, etc should be certified.
2.5 preparation of construction schemes and
technical disclosure, disclosure according to the characteristics and training
of construction personnel so that each operator should be familiar with the
technology, quality, safety and fire requirements.
2.6 should be according to the design
requirements, at the construction site well using a range of specifications,
books, technical requirements, quality records, forms and other related
documents.
3 construction technology
3.1 process:
Steel pipes and metal slot installed → steel pipe
laying wire trunking wiring installation of automatic fire alarm equipment → →
Inspection and acceptance for debug → delivery
3.2 steel pipe and metal slot to install
the main requirements:
3.2.1 enter the tubing, steel, metal
trunking and accessories have material proof or certificate and shall check the
quality, quantity, specifications and requirements consistent, complete
inspection records. Steel pipe requires a uniform wall thickness, weld evenly
split and sand holes angled thorn-free, no-female flat, evenly inside and
outside galvanized layer intact. Metal raceways and its annexes should be used
after a galvanized product. Slots should be smooth, without thorns should not
distort the wing angled edge deformation.
3.2.2 piping should be designed, to provide
manufacturers a variety of detectors, Manual alarm, loudspeaker equipment
models, specifications, select the junction box, the box with the installed
equipment.
3.2.3 cable protection tube when you
encounter one of the following conditions should be convenient place to thread
an additional junction boxes:
Pipe is longer than 30m, no bending;
Pipe is longer than 20m, there is a bend;
Pipe is longer than 15m, there are two
bending;
Pipe lengths over 8M, has three bent.
3.2.4 wire and bend protection tube there
should be no creases, dents, cracks, and bend flat should not be greater than
the pipe diameter of 10%.
3.2.5 out pipe bend radius should not be
less than 6 times the pipe diameter, dark pipe bend radius should not be less
than 6 times the pipe diameter, when buried in the ground or in concrete, and
the bending radius should not be less than 10 times the pipe diameter.
3.2.6 pipeline dark time, cable protection
pipe should be laid along the lines of recent and should reduce bending.
Embedding non-burning buildings and structures within the cable protection tube
with buildings and structures should be less than the distance from the wall
30mm. Metal wiring duct and pipe out the timing, according to the design
requirements of fire protection measures.
3.2.7 wiring protective tubes should not be
through the basis for equipment or buildings or structures, must be through
protection measures need to be taken, such as the use of protective tube.
3.2.8 horizontal or vertical laying out the
distribution line protection tube allowable deviation 1.5, length deviation
should not be greater than diameter of 1/2.
3.2.9 cable laid in dusty or humid places
tube, pipe and all connections should be sealed.
3.2.10 pipe laying building deformation
joints (settlement joints, expansion joints, anti-seismic joints including)
compensation measures need to be taken. Like 6-2A, 6-2B, 62-c.
3.2.11 out distribution tube should be
neat, fixed spacing should be uniform, maximum distance between pipe as shown
in table 6-l, pipes, elbows point card and Terminal, electrical appliances or
box (box) the distance from the edge, should be 0.15~0.5M.
3.2.12 laying pipeline should use a
separate fixture in the ceiling installation or support fixed, renovated units
permitted, 20mm and the following pipe fixed to the boom or the main keel.
3.2.13 dark pipes in the case of no
ceiling, position of the detector box is where to install the probe cannot be
adjusted, so to determine cartridge position detector installation requirements
should be positioned.
3.2.14 out piping using the junction box
and install fire equipment boxes mounted boxes should be used.
3.2.15 laying pipe installation into
cartons, boxes, both inside and outside of the root parent lock fixed,
installed with the mouth on the inside. Steel pipes into the length of the box
is subject to take full guard post into root.
3.2.16 boxes, wiring duct and pipe supports
should be used embedded bolts, expansion bolts, expansion screw fixed, embedded
iron parts and welding methods, prohibited the use of Cork. When using
expanding screws, expansion bolts, drill specifications should support with the
tube.
3.2.17 all kinds of metal structures,
junction boxes, box mounting holes electrical and gas welding and cutting holes
cannot be used.
3.2.18 steel pipe threaded pipe end thread
length shall be not less than 1/2 of the length of the fitting, connection thread
suitable for exposed 2~3 clasp, thread surfaces should be smooth and free from
defects.
3.2.19 galvanized pipe threaded connections
or casing fastening screw connections, welding connections should not be used,
so as not to undermine the zinc coating.
3.2.20 piping and wiring duct installation
should take into account the different systems, different voltage and current
type of line should not be worn in the same tube or slots with slot hole.
3.2.21 pipes and lines should be considered
when installing the horizontal laying transmission lines such as the use of the
alarm system conduit wiring, different fire lines should not be put into the
same tube, detector alarm circuit using the bus system is not affected by this
limit.
3.2.22 weak lines of cable shaft shaft set
and strong lines, when conditions share the same shaft, to be arranged on the
sides of the shaft.
3.2.23 in ceilings of buildings must use
metal tubes, metal slot wiring.
3.2.24 laying pipe and hot water pipes,
laying steam pipes should be laid on the same side in the hot water pipe, steam
pipe below. Difficulties can be laid on top, between the net distance shall be
not less than the following values:
3.2.24.1 when the tube below the water line
at 0.20m, above 0.3M, 0.5M when the tube beneath the steam pipe, above at 1M.
3.2.24.2 insulation should be used when you
cannot meet these requirements. On the steam pipe with insulation measures
upper and lower clearance can be reduced to 0.2m.
3.2.25 steel pipe and other pipe mains
parallel distance should not be less than 0.10m. When the side with the pipe
laying up laying on top of pipe (not including combustible gases and flammable
liquid pipeline). When the line jump when it crosses a distance of not less
than the corresponding parallel spacing above.
3.2.26 line tank should be installed in a
dry place and susceptible to mechanical damage.
3.2.27 trunking installation should use a
separate fixture installation or support for a fixed, the diameter of the
hangers should be not less than 6mm, the fixed support spacing should not
exceed 1~1.5M, in and out of the junction box, boxes, cabinets, corner, corner
and curved seam ends and t-joints of three-Terminal 0.5M, should set a fixed
support points.
3.2.28 slot interfaces should be straight,
tight lid should be complete, smooth and without corners.
3.2.29 fixed or connector, slot screws or
other fasteners after fastening the ends should be connected with the Groove
smooth inner surface, online slot nuts outside the wall, fastening complete
flat mats and trampoline.
3.2.30 line tank outlet and angle, corner
is correctly positioned, smooth, Burr-free.
3.2.31 trunking installation should be
straight and tidy, horizontal and vertical tolerances length of 2 ‰, and length
tolerances for 20mm, side by side installation slot cover should be easy to
open.
3.2.32 metal slot connections should not go
through floors or walls.
3.2.33 metal tubes or metal raceways and
fire-fighting equipment made of metal hoses and flexible metal pipe when the
bridge was made, its length should not be more than 2m, and should be fixed by
clamp, fixed spacing should not be greater than 0.5M, and ends with a lock or
clamp fixing and grounding as required.
3.2.34 concealed fire hydrants when pipes,
junction box should not be placed in the back of the fire box and side entry.
3.2.35 fire-fighting equipment and pipeline
grounding, protection and construction should be according to the
specification, design and documentation requirements.
3.3 pipe insulated wires laying and wiring
duct wiring requirements:
3.3.1 enter insulated wires and control
cables model specifications, quantity, certificate shall conform to the design
requirements, and fill materials inspection records.
3.3.2 automatic fire alarm system for
transmission line, using insulated copper wire or copper cable, the voltage
should not fall below AC 250V, 500V best to improve insulation and anti-jamming
capability.
3.3.3 in order to meet the mechanical
strength requirements for wires and cables, insulated wire for pipe laying,
minimum core cross section shall be not less than 1mm2; laying the wires the
minimum cross section within the Groove shall be not less than 0.75mm2;
multi-core cable core minimum cross-section should not be less than 0.5mm2.
3.3.4 pipe insulated conductor or cable's
total area should not exceed 40% of the sectional area of the tube, laying on
the closed line of insulated wire or cable should not be greater than the total
area of slot NET section area of 50%.
3.3.5 wires in the pipe or wire Groove,
there should be no joints or kinked. Joints should be welded in the junction
box of the wires or crimping.
3.3.6 different systems, different
voltages, different categories of current lines should not be put in the same
root canals or worse the same slot.
3.3.7 horizontal laying transmission lines
if the pipe runs to the alarm system, different fire lines should not be put
into the same tube. Used bus system is not affected by this limit.
3.3.8 smoke alarm transmission lines should
choose a different color of insulated wire, detector "+" line to red
"-" line is blue, the other line should be distinguished according to
different uses other colors. But uses the same wiring colors should be
consistent in the same project, Terminal markings.
3.3.9 wires or cables in the junction box,
expansion joints, fire-fighting equipment should leave enough margin.
3.3.10 tubes or slots in the thread on the
building plaster and ground end of the project. In front of the thread should
be pipe or a trough of water and debris removal clean, tube take care.
3.3.11 wire laid in vertical lines, section
50mm2 below, each longer than 30m should be fixed at the junction box.
3.3.12 is currently China's rapid
development of the cause of the fire, using the bus line control many, track
laying length of line resistance is required, construction should be strictly
according to manufacturer technical information required for laying out and
wiring.
3.3.13 joints shall not increase the
resistance of the wire connections, wire should not reduce the mechanical
strength, they cannot reduce the dielectric strength, in order to meet the
above requirements, wire connections should do the following:
3.3.13.1 plastic wires 4mm2 the following
should generally be used when clamp exploitation off the wire insulation, such
as woven wire application electrician's knife and stripped the outer braid and
leave 12mm insulation, core length of wiring methods and the desired mechanical
strength may be.
3.3.13.2 wire insulation and snap together,
at a distance of insulation 12mm with one of the cores in the other thread core
wound after 5~7 laps to cut, and Qi Yu TOU turn on the cord, and rinsing Tin
treatment.
3.3.13.3 LC safety press line cap: press
line cap is copper wire is divided into yellow, white and Red tricolor, applied
respectively to 1.0 mm2 and 1.5 mm2 and 2.5 mm2, 4 mm2 2~4 wire connection.
Their method of operation is: wire insulation stripped 10~ 13mm (decided by CAP
model), removing oxides, prescribed proper press line cap, will take over core
insert the pressure CAP, if it is not filled with real, cores can be retraced
(Peel long double), full. After the wire inserted in the end, Guan Kouping
align the wire insulation should be pressed to take over, and packages within
the CAP, and then with a special crimping pliers compaction. Table 6-2, 6-3.
3.3. 13.4 stranded copper conductor wire
screws when crimping, wire core twist should be eye-shaped, copper nose or
small press, net to flatten and then after rinsing Tin coated pad with screw
tight and firm.
3.3.13.5 copper single wire and
PIN-terminal connection (crimp), insert wiring connection wire line core header
pinholes, wires exposed pinhole l~2mm, pinhole larger than core diameter of 1
time when the need to insert crimp fold back. If multiple soft copper wire
should be tightening rinsing Tin, clean crimp. As in Figure 6-4.
Dressing for 3.3.13.6 wire connection:
Selection of rubber (or plastic) insulation
from wire connector at the beginning of the sound insulation layer, winding l~2
insulating tape width, half overlap winding. Dressing should as far as possible
in the process of tightening up insulation tape. Finally wound after l~2 laps
on the insulating layer, and back around again. And then covered with a black
cloth, to cohesion when dressing well, half-width winding overvoltage edges and
tighten the tape during the dressing process, both ends of the wire connectors
with a black cloth tightly.
3.3.14 wires connected to complete, should
check, correct to 500V, quantum 0~500M ω-megohmmeter, between conductors,
Line, line to ground the shield of the
shake test, their low insulation resistance values should not be
20MΩ。 Note You cannot
shake test with fire-fighting equipment. Shaking speed should be around
120r/min, readings should be applied after 1 minute readings.
3.4 installation of automatic fire alarm
equipment requirement:
3.4.1 automatic fire alarm equipment should
be according to the requirements of the design drawings, model, variety,
quantity, specifications, appearance and other checks, and made available to
State Fire electronic product quality supervision and inspection Center for
effective inspection reports and other information about installation
requirements, provision of equipment and units for processing of incoming
equipment procedures.
3.4.2 point type fire detectors, gas
detectors, infrared beam fire detector installation requirements:
3.4.2.1 smoke temperature detector area and
protect RADIUS shall conform to the requirements, shown in table 6-3.
Smoke, temperature detectors protected areas
and protection of the RADIUS table 6-3
Detector protection area and radius r
Fire detection area the room height top of
slope θ
Type s h for θ ≤ 15 ° 15 ° < θ ≤ 30 ° θ >30 °
(m2) (m) A
(m2) R
(m) A
(m2) R
(m) A
(m2) R
(m)
S≤80 h≤12 80 6.7 80
7.2 80 8.0
Smoke detector
6<h≤12 80 6.7 100 8.0
120 9.9
h≤6 60 5.8 80 7.2 100
9.0
S≤30 h≤8 30 4.4 30
4.9 30 5.5
Thermal detectors S>30 h ≤ 8 20 3.6 30
4.9 40 6.3
3.4.2.2 smoke temperature detector
installation spacing should not exceed the limit curve in Figure 6-5 D1-D11 (D9
')
Under scope, and protected by the detector
area and protect the limit curve of RADIUS r determine the detector's
installation space.
3.4.2.3 a set number of detectors of
detector area domestic demand should be calculated according to the following
formula:
N=
Type N--
S——
A——
K--a number of detectors required within
the detection area set (only), and an integer.
A detection zone area (m2);
A probe of the protected area (m2);
Correction factor to protect buildings take
0.7~0.9, and the rest is 1.0
3.4.2.4 ceiling bi when setting up a smoke,
temperature detectors, beam height influence detector installations.
On the roof of a beam to highlight the
ceiling height is less than 200mm set smoke, temperature detectors, don't
consider the detector area impact.
B when the highlight 200mm~600 m m, the
height of the ceiling, according to 6-6 and 6-4 to determine the beam effect
between beam and a detector can protect areas of those numbers.
C when the highlight ceiling heights of
more than 600mm, beam dividers between each beam area should be set up at least
one detector.
D cut off when the beam area over a probe
of the protected area shall be regarded as a detection area, count the number
of detector setting.
3.4.2.5 housing top heat barriers, the
smoke detector distance between lower surface and roof shall conform to table
6-5 requirement. Zigzag-shaped roof of the roof and slopes of more than 15 °,
in each set the roof of a row of detectors, detector distance of the lower
surface of roof top should meet the requirements of table 6-5.
3.4.2.6 detectors should be installed
horizontally if it is necessary to tilt when installing angles should not
exceed 45 °.
3.4.2.7 the room is separated by
bookshelves, device or partition, which is less than the distance from the
ceiling or beam at the top Stud
Surface under the smoke detector from the
ceiling (or roof) table of distances 6-5
Lower surface detectors smoke detectors
from the ceiling (roof) the distance d (mm)
Installation height of ceiling (roof) slope
θ
h θ≤15° 15°<θ≤30° θ>30°
(M) minimum maximum minimum maximum minimum
maximum
h≤6 30 200 200 300 300
500
6< h≤8 70 250 250 400 400
600
8< h≤10 100 300 300 500
500 700
10< h≤12 150 350 350 600 600
800
5%, each separate part of the detector
should be set.
3.4.2.8 detectors around 0.5M, there should
be no curtain, the probe horizontal distance to the side walls, beams, should
not be less than 0.5M. As shown in Figure 6-7.
3.4.2.9 detectors to the air outlet side of
the horizontal distance should not be less than 1.5M, as shown in Figure 6-8,
air levels of roof openings up to hole distance should not be less than 0.5M.
(Refers to the distance from the detector within a 0.5M radius of the centre hole
using non-burning material filling, or similar of the windshield).
3.4.2.10 width is less than 3M when setting
the detector on the ceiling of the aisle should be arranged. The installation
spacing should not exceed 10m temperature sensor detector, smoke detector
installation spacing should not exceed 15m, distance between detector and end
walls should not be greater than the spacing between detectors installed half.
3.4.2.11 in the elevator shaft, lift shafts
set the detector, the location should be at the top of the shaft on the roof of
the engine room.
3.4.2.12 the following places do not set
fire detectors:
A toilet, bathroom and other wet places
B cannot detect fire place
C do not place where ease of use and
maintenance
(Except for the key parts)
3.4.2.13 flammable gas detectors should be
installed in the gas easily leak out and gas easily flows through the site, and
easily to places of detention, installation location according to the measured
the density of the gas, installation site direction of flow, temperature and
other conditions have been determined. As shown in Figure 6-9.
A denser, heavier-than-air gases, liquefied
petroleum gases should be installed in the lower part, from 0.3M. And the
appropriate location from the gas stove is less than 4mm.
B artificial coal gas density is smaller
and lighter than air, combustible gas detectors should be mounted at the top,
away from the outlet side of the gas stove is less than 8M on the roof. If
there is no outlet should be installed near the gas side of the beam, elevated
relations with detector see 3.4. Article 2.4.
C other types of combustible gases can be
provided by the manufacturer and by the national qualified product
specification to determine the installation location of the detector.
3.4.2.14 infrared beam detector
installation location, should guarantee an adequate field of view, send beams
should be parallel to the roof, away from strong magnetic fields, avoiding
direct sunlight, the base should be securely mounted on the wall, the installation
height shown in Figure 6-10.
3.4.2.15 installation requirements for
other types of detectors should be installed according to designs and
manufacturers provide technical information.
3.4.2.16 detector base should be reliable,
when installed in the ceiling should be fixed on the main box keel or rooting
on the ceiling bracket, and its connecting wires must be reliable crimping or
welding when welding may not use corrosive flux, external wires 0.15m and
cushion into the ends shall be clearly marked.
3.4.2.17 detector to confirm the lamp
should be oriented to their view of the direction of the main entrance.
3.4.2.18 detector base threaded holes
should be sealed, installation of protective measures should be taken (such as
install shield).
3.4.2.19 detector wiring wiring according
to the designs and manufacturers, but "+" line should be red
"-" lines should be blue and the remaining lines according to
different uses other color, but the same project in the same wire color should
be consistent.
3.4.2.20 detector head is checked when
installing, installation should be properly kept and should take measures such
as dust, moisture and corrosion.
3.4.3 manual fire alarm installation.
3.4.3.1 each fire alarm in the region
should be set at least a manual alarm button from one fire compartment until
recently at any location within walking distance of a manual fire alarm button
should not be greater than 30m.
3.4.3.2 manual fire alarm should be
installed in a clear and easy on the wall, height above ground 1.5M securely
should not tilt.
3.4.3.3 manual fire alarm call external
wires should be left 0.10m allowance, and the ends of shall be clearly marked.
3.4.4 module and terminal box-box
installation.
3.4.4.1 boxes generally set in the terminal
box and module dedicated to the shaft, should be designed according to the
required height with metal expansion bolts mounted on the wall, and the
installation should be correct when a firm shall not be tilted.
3.4.4.2 in line for line numbers, then
wires have a certain cushion against the control center to route and fire alarm
and control lines are banding into a bundle, and are located at both sides of
the Terminal Board, to control the center line on the left, right for fire
alarm detectors and other equipment to the control circuit.
3.4.4.3 line before the shake test the
insulation of the wire, after passing the line according to designs and
manufacturers requirements.
Designed 3.4.4.4 modules box modules are
manufacturer and request an assembly line, reasonable layout, and the installation
should be solid and straight, and uses symbols and line number.
3.4.5 fire alarm control unit installation.
3.4.5.1 fire alarm control unit
(hereinafter referred to as controller) received fire detector and fire alarm
signals and other fire alarm signals, sound and visual alarm indicating the
parts of the fire, according to pre-programmed logic, send control signals,
various fire-fighting linkage control equipment, fire quickly and effectively.
To ensure the function must do careful construction, ensure a quality
installation. Generally should be set on fire, fire fire alarm Office, manned
guardhouse and other provisions of the room or place. Display the actions panel
of the controller should avoid direct sunlight, room without high temperatures,
high humidity, dust, corrosive gases not subject to vibration, shock and so on.
As shown in Figure 6-11.
3.4.5.2 civil work before installation the
device should meet the following requirements:
Construction has been completed of a roof,
floor, there shall be no leakage.
B end Interior floors, doors and Windows,
ceiling installation.
C bad installation of decorations all over.
3.4.5.3 area alarm controller when
installing on the wall, the bottom margin should be not less than 1.5M, buried
metal expansion bolts or bolts that are available for installation, fixed to a
solid, upright, mounted on the light wall reinforcement measures need to be
taken. Close to the door side of the axis distance should not be less than
0.5M, positive operating distance should not be less than 1.2m.
3.4.5.4 central police control room or fire
control center equipment installation should meet the following requirements:
A floor installation, it should be above
the ground at the end of 0.05~0.2m, channels or water is commonly used as a
basis, such as when there is a raised floor with steel base should be rooting
firmly fixed cement ground. Channel straightening first rust, paint and brush,
the installation level and small looking for a straight line, then fixed with
bolts firmly.
B Panel arranged according to design
requirements, according to the Cabinet's fixing holes drilled in basic steel,
installation starts from the end of one by one in place, screw, with a small
wire leveling will bolt straight after each.
C control equipment before operating
distance, single row arrangement should not be less than 1.5M, double row
layout should not be less than 2m, someone on duty often working side control
panel to wall distance should not be less than 3M, after-hours maintenance
distance should not be less than 1M, control panel array length is greater than
4m, the control panel should be set up at both ends of channel width not less
than 1M.
When installing the floor control panel d
regional control rooms, reference to the relevant requirements of the above
installation and construction.
3.4.5.5 fire alarm controller cable, wire
grounding should comply with the following requirements:
A on the introduction of the cable or wire,
first line for line. By drawings requirements number, then shake
measuring-and-, and on to, insulation resistance, not should is less than 20M
ω, all qualified Hou by different voltage grade, and uses, and current category
respectively lashing into beam introduction to Terminal Board, by wiring figure
for line, note each wiring Terminal wiring not should over two root, disc
circle should by clockwise direction, more unit line Ying Shuanxi, wire due
appropriate allowance, logo number should right and and drawings consistent,
handwriting clear, easily faded, distribution line should neatly, avoid cross,
fixed firm.
B wire inlet is completed, at the inlet
pipe should be blocked, main power inlet shall be directly connected with the
fire power, prohibited the use of connectors, mains shall be clearly marked.
C where the introduction of AC power supply
of fire-control equipment, shell and should be based on reliable earthing, PE
line should be connected to the power line.
D fire control room should in General be
special grounding device is designed according to the needs as a working ground
(geographical logic refers to the fire control equipment signal ground). When
the separate grounding resistance should be less than 4 ω when using combined
grounding, grounding resistance should be less than 1 ω, control room to
grounding grounding line should use a piece of not less than 16mm2 insulated
copper wire or single-core cables, put into the protective tube, respectively
pressure control equipment grounding plates and outdoor ground body. Fire
control work ground to fire control equipment and fire alarm control unit Earth
wire should be not less than 4mm2 insulated copper wires into the protective
tube forms a zero electric potential of grounding network, fire alarm devices
to ensure stable and reliable. During the construction of earthing devices,
different stages should be hidden check for electrical grounding, grounding
resistance shake test, sketch of the quality inspection records.
3.4.6 other fire alarm equipment and
linkage equipment installation, in accordance with the relevant specifications
and design manufacturers required to install wiring.
3.5 debug requirements (Figure 6-12):
3.5.1 commissioning of automatic fire alarm
system, in interior decoration of buildings and construction after the end of
the system.
3.5.2 shall submit to the commissioning
before commissioning the construction personnel completed drawing, design
changes, construction records (including acceptance of concealed work record),
inspection records (including the insulation resistance and Earth resistance
test record) and completion of the report.
3.5.3 served as head of commissioning must
be performed by a qualified professional and technical personnel. General plant
engineer or production plant commissioned by trained personnel. Its eligibility
is determined by public security fire control institutions.
3.5.4 debugging should be checked according
to the following requirements:
3.5.4.1 identification according to design
requirements, equipment, specifications, models, spare parts, spare parts, etc.
3.5.4.2 in automatic fire alarm system
construction and construction quality acceptance of requirements to check the
system. Are part of our problem in the construction, shall be settled through
consultations in conjunction with the relevant authorities, and documented.
3.5.4.3 check inspection system wiring wiring,
wiring, wiring resistance, insulation resistance, earthing resistance,
termination resistor, wire, grounding and whether line color with the design
and specifications, found the wrong line, open circuit, short circuit, such as
inadequate should be processed in a timely manner, and troubleshooting.
3.5.5 fire alarm system should be
respectively the detectors, fire control equipment, such as stand-alone power
inspection and test them one by one. Single check test, conduct system testing,
powered access systems fire alarm alarm controller self-test function,
silencing, reset, fault alarm, fire priority functions, alarm memory function,
automatic switching and standby power supply auto power charger, standby power
supply undervoltage and overvoltage alarm function. Above in a powered up check
all functions must conform to the regulations of the GB4717 requirements of the
General technical conditions for fire alarm control unit.
3.5.6 by design require main power supply
and standby power supply, check one by one testing fire alarm linkage control
function and features of the system, its control function and the linkage
function should be normal.
3.5.7 check mains: automatic fire alarm
system mains power and standby power, its capacity should be consistent with
the relevant national standards, standby power supply for charging and
discharging three times normal, primary power supplies, standby power switch
should function normally.
3.5.8 Add smoke to control the debugging
application-specific heating tests, should be the test for various types of
detectors individually, action right can be put into operation.
3.5.9 other alarm devices to test error
after put into operation one by one.
3.5.10 according to the system debugger
system functional self test. After the system fully functional, continuous
trouble-free operation of 120h, opened to write debug report acceptance.
3.6 system acceptance procedures
3.6.1 fire alarm system installation is
completed, by the construction unit, debug, unit project quality pre-test,
debug, quality, construction materials, and quality assessment, and found
quality problems should be resolved in a timely manner, up to comply with the
design requirements and norms.
3.6.2 pre-screening all qualified,
construction unit, debug, unit construction, design and supervision units,
project completion acceptance check, correct upon completion and acceptance.
3.6.3 construction or construction
technology of building fire protection facilities testing unit for testing,
submitted by the unit test report.
3.6.4 above after the completion of all
works, the construction unit acceptance application report to the public
security fire control institutions, and provide the following documents and
information:
3.6.4.1 Fire Department's fire in the
building of audit files, memos and their implementation.
3.6.4.2 construction units and equipment
manufacturer qualification certificate and certificate of product testing.
3.6.4.3 construction records (acceptance of
concealed work, design changes, negotiation, insulated shake test records,
records, material certificate, certificate of major of grounding resistance.
3.6.4.4 debug reports.
3.6.4.5 employer organization construction,
design and supervision units for processing completed acceptance form.
3.6.4.6 testing unit test report.
3.6.4.7 system drawings, completed systems
tables.
3.6.4.8 management, maintenance personnel
registration form.
3.6.5 fire engineering construction quality
by public security fire control institutions to reinspect the fire equipment
and function testing, after all, to the construction unit of the acceptance
certificate of building fire protection facilities, the construction unit can
be put into use, access to the system is running.
4 quality criteria
Automatic fire alarm system works at
present state there is no uniform standard of quality assessment, in order to
improve project quality, strengthening quality management and project quality
examination standards, apply GBJ-300-88, GBJ303 188 part of quality assessment
standards and quality requirements for new project.
4.1 pipe and pipe threading, use 2-3-l
table GBJ303-88 "pipes and pipe thread for quality inspection and assessment
form" content, but some of the content should be changed as follows:
4.1.1 project lead and lead on the value of
the insulation resistance between words must be greater than 20M.
4.1.2 Basic project pipeline laying in the
dark layer of piping should be changed to 30mm.
4.1.3 in the allowable deviation, pipes
minimum bending radius pipe bending radius light and shade change greater than
or equal to 6 times (6D), or underground concrete piping into dark ≥ 10D.
4.1.4 pipe and threading should be separate
inspection and evaluation (evaluation of records using a table twice).
4.2 fire alarm and linkage of the enclosure
to be installed in GBJ303 188 4-3-1 "power distribution cabinet (plate)
and power switchgear installation engineering quality inspection and assessment
of form" part of the building.
4.3 Terminal Board box and module
installation quality assessment can be applied GBJ303 188 4-7-1
"electrical lighting and power distribution box (disc) quality inspection
and assessment of installation project tables" part of the building.
4.4 earthing installation quality
assessment form GBJ 1,303,188 5-0-1 "lightning rod (net) and grounding
engineering quality inspection and evaluation form" part of the building.
4.5 alarm detector construction quality
assessment form, there is no standard, this is just a project, Basic projects,
allowable deviation in some requirements, such as, to set the table for quality
assessment.
4.5.1 project: detector type, model,
location, quantity and function, the design and specification requirements.
4.5.2 Basic project shall meet the
following requirements
4.5.2.1 probe is mounted firmly, confirm
the lights right and complete accessories, no damage and breakage, and so on.
4.5.2.2 detector wiring connections must be
reliable crimping or welding, and there should be a flag, an external wire
room.
4.5.2.3 detector installation location, the
protection of RADIUS, area requirements.
4.5.3 allowable deviation:
4.5.3.1 detector away from walls, Liang
Bian 0.5M and around the curtain from air conditioning air outlet distance ≥ l.5M,
porous fence ≥ 0.5M.
4.5.3.2 width less than 3M set the detector
to the occasion on the top center of the aisle layout, temperature detector
installation distance 10m, 15m smoke detector installed, should be greater than
the distance from the detector from the end wall of the detector installed half
the distance.
4.5.3.3 detectors should be installed
horizontally if it is necessary to tilt when installing its tilt angle not
greater than 45 °.
4.6 the section contents of quality
assessment, if it is a subcontractor, contractors quality assessment quality
assessment for these items should be added to the common assessment in the
building Division of electrical installation engineering. If works, quality
assessment for these items as a unit of electrical installation (Division)
project, according to the relevant requirements of GBJ300-88 assessed quality
rating.
5 finished product protection
5.1 when steel pipes laid in concrete or a
wall, sealing tube and box in a timely manner, so as not to enter the debris
under the influence of process threads, causing tick chisel; civil engineering
concrete or masonry to a hand tie, avoid laying pipe displacement resulting in
rework.
5.2 pipe thread: Groove when wiring within
the remainder of the wire should be placed in a box or boxes, covers and slot
cover in a timely manner to avoid wire damage or loss.
5.3 automatic fire alarm system equipment
store, to dust, moisture, anti collision, smashing prevention, prevention
measures such as safekeeping and handling procedures for incoming inspection
and permit.
5.4 automatic alarm device installation,
civil works should meet the floors, walls, Windows and doors, spray finished in
dedicated under the condition of the installation.
5.5 after the completion of fire control
room and a room equipped with a controller should be locked in time, close the
doors and Windows, the equipment should be covered with dust and moisture
Department.
5.6 alarm detector should be mounted on the
base, and wear a dust cover reloaded when you debug probe.
5.7 after the completion of terminal box
and module boxes to door locks, box cover to protect the body from being
polluted.
5.8 loss of damaged equipment such as
manual alarm, Horn, phones and phone jacks should be installed last, protection
measures are required.
5.9 installing alarm systems and equipment,
civil works and decorative work have come to an end, installation steps should
be taken to ensure that the walls, floors, ceiling from damage and pollution.
5.10 when pick slot, picking holes in the
construction, not breaking structural reinforcement in, must be broken, and
shall be subject to approval of the construction and design can be broken,
especially its main steel structure must be in strict compliance with the
provisions of this article, otherwise it will cause irreparable accidents.
6 quality problems to be noticed
6.1 construction workers should strictly
abide by the 6-l "General requirements for the installation of fire
engineering and related provisions", which is an important condition to
ensure project quality and service.
6.2 strengthened into the factory
inspection of equipment and materials, its quality must conform to the
requirements of the relevant specification and the process, cannot use the
nonconforming product.
6.3 quality problems should be paid
attention to in construction:
6.3.1 simmer bend found concave flat too
large or sufficient bend RADIUS multiple phenomena, the solution is the use of
hand and simmering bending moves to moderate, not too hard, until you meet the
requirements.
6.3.2 embedded box, boxes, brackets,
hangers, skew, or box with too many people coming in and going out is too
serious, according to resize or re-planted.
6.3.3 out piping or piping in the ceiling,
unstable fixed point, iron clamp loose and fixed point are too large and
uneven, should be the supporting pipe clamp fixation, span should get even.
6.3.4 dark match pipe plug, piping should
be added in a timely manner after jammed tight shutoff nozzle, and you should
always check, found leakage blocking or dropped in time blocked, such tubes
have been blocked to handle repairs.
6.3.5 prohibited the use of electric weld
and cut the pipe. Bracket and the holes in the box set, and saws and reamers
should be used for the construction, flush cut requirements, with a file to
remove burrs and then piping.
6.3.6 cartons, boxes, destruction of
galvanized steel pipe, galvanized layer should be promptly treated.
6.3.7 using metal hose should not be longer
than the 2m, fixed spacing should not exceed 0.5M, fixed at both ends should be
solid.
6.3.8 conductors shall be conducted
according to technical specifications and color selection and installation,
detector "+" line to red "-" blue line and the remaining
lines according to different uses other color, but use the same wire colors
should be consistent in the same project.
6.3.9 must wear protection when threading
pipe to protect the insulation of the wire.
6.3.10 wire crimping the connector, rinsed
Tin, bandaging, shall be consistent with this process and related regulatory
requirements.
6.3.11, relative to the insulation
resistance of the wires should be not less than 20M. Shaking when measuring the
insulation resistance not shake test with automatic fire alarm equipment.
6.3.12 detector installation location and
type shall conform to the design and technical specifications, installation
location the principles established at the outset to ensure the function,
followed by the appearance, such as interference with other types of equipment
installed, should inform the design and consultation unit address.
6.3.13 crimping of wires on the device,
according to requirement of design and manufacturer number and crimp firmly
knot, anti-ring phenomenon are not allowed, the same terminals cannot be more
than two wires.
6.3.14 debugging when the first stand-alone
adjustment,-by-item-by-item function debug absolutely, cannot be missed, to
ensure the effective operation of the automatic fire alarm system as a whole.
6.3.15 construction process, construction
technology for data collection, complete, custody shall be synchronized with
project progress.
7 quality records
7.1 the main steel material proof and
certification, certification of insulated wire and cable, fire alarm equipment
and fire prevention materials to Beijing license testing report and quality
supervision departments, equipment and material incoming inspection record.
7.2 change record of negotiation.
7.3 inspection records.
7.4 cover engineering inspection records,
electrical grounding devices hidden inspection record and sketch.
7.5 commissioning record, which mainly
include: insulation resistance test record, grounding resistance test record
debug report of fire control system, fire alarm system, such as inspection
reports.
7.6 the construction programme, technical
and construction logs.
7.7 engineering quality inspection and
evaluation form.
7.8 acceptance form.
7.9 the fire sector check memo.
7.10 building fire facility inspection
certificates and use licenses.
7.11 as-built drawings.
7.12 alternative technologies and quality
of information, mutual inspection records, acceptance records, equipment,
product specifications, technical and quality minutes, drawing record, accident
reporting, supervision of the use of a variety of forms.
No comments:
Post a Comment