1 scope
This technology is applicable to industrial
and civil construction of plastic door and window installation.
2 construction preparation
2.1 materials and equipment:
2.1.1 of rigid PVC plastic door and window
specification, model, dimensions shall meet the design requirements. Applied
load does not exceed 800N/m2.
2.1.2 door and window frame fittings (iron
foot) connected with the cave wall, generally by mechanical piercing tube bolt;
screws or embedded wood brick; should be prepared as necessary.
2.1.3 Windows hardware specifications,
models should be doors and Windows support.
2.1.4 doors and Windows should be installed
to prepare wood wedge, steel nail.
2.1.5 sealants should be prepared according
to design requirements. And there should be proof of delivery and product
certification.
2.1.6 varieties should be selected
according to the design requirements of caulking materials.
2.1.7 head tapping screws, wood screws as
needed to prepare.
2.1.8 cement: No. 325 more than ordinary
Portland cement or slag cement.
Sand: 5mm sieve, sieve well and set aside.
Bean stone: prepare a little.
2.1.9 main tools: wire pendant, pink bag, a
spirit level and supporting plate, hammer, flat spatula, steel tape measure,
screwdriver, impact drills, nail guns, saws, planes, small shovel, a small
bucket, drill, etc.
2.2 operating conditions:
2.2.1 structure works have been finished,
meet the qualifying standard of acceptance, transfer procedures between the
good jobs.
2.2.2 dimensions as shown better door and
window line of position, and based on the play the good +50cm level, determine
the installation height.
2.2.3 checking doors and Windows that have
been retained to wall size and elevation meets the design requirements,
problems should be corrected in a timely manner.
2.2.4 checking whether the connector
placement of plastic door and window installation meets the requirements.
2.2.5 check plastic door color is uniform.
Is free of cracks and pitting. Stomata and visible bruises.
2.2.6 is ready to install scaffolding and
safety protection measures.
3 operational processes
3.1 process:
Line the rules → jambs
processing → check → plastic doors and Windows of the installed connector appearance
check →
Request delivered to the installation site
as shown: →
→ → caulking
around the Windows and doors installed plastic doors and Windows installed
metal accessories → cleaning
3.2 the procedure should be introduced into
port construction, shall not be made after the first construction. Plastic door
and window frame to connector as shown in Figure 8-4.
3.3 check the door hole size is larger than
the size of door and window frames 3cm, you should first pick your cut.
3.4 Summary of installation position the
drawing size on the doors and Windows box line and the vertical elevation
control line.
Iron foot 3.5 is installed on a Windows
box.
3.6 install door and window boxes, and by
looking for a vertical line in place and elevation with a wooden wedge
temporarily fixed, check the side vertical and diagonal lines, after passing
the bolted iron foot and firm structure is secured.
3.7 caulking: window box with a crack in
the wall should be constructed according to the design requirements of caulking
materials such as asphalt used in requests or foam filled. Sealant closed
surfaces with thickness of 5~8mm.
3.8 Windows attachments installation:
installation be sure to drill boreholes, using self-tapping screws screwed
into, do not beat with a hammer or a hard object and prevent damage to the box.
3.9 after installation finished product
protection, pollution prevention, and welding sparks burn and damage the
surface.
4 quality criteria
4.1 project:
4.1.1 quality of plastic doors and Windows
and their attachment and glass must comply with the design requirements and the
provisions of the relevant standard.
4.l.2 plastic doors and Windows must be
installed firmly, numbers, locations of embedded iron parts, laying and
connection method should comply with the design requirements and the relevant
provisions of the standards.
4.1.3 plastic door and window installation
position and opening direction must comply with the design requirements.
4.2 Basic project:
4.2.1 plastic doors and Windows closed
tight, flexible, non-blocking rebounding, no distortion and warping.
4.2.2 annex plastic doors and Windows
installation is complete, install strong, correct position, upright, opening
and close flexibly applicable appearance.
4.2.3 the plastic door filled the gap
between the window frame and the wall full of dense, smooth surface, impaction
material meets the design requirements.
4.2.4 plastic door surface is clean and
smooth, the same color, no scratches scratches, no pollution, seam is tight.
4.3 allowable deviation, as shown in table
8-5.
5 finished product protection
5.1 when embedded waterproof sealant around
the window frame, the operation should be carefully, ointment not contaminated
door and window frames.
5.2 coat of exterior wall, interior wall
spraying, the plastic blocking the doors and Windows to prevent pollution.
5.3 indoor cement mortar must be blocked
well before the plastic Windows and doors, to waterproof mud pollution Windows
and doors.
5.4 sewage, garbage, filth, and not through
the window to the ground.
5.5 lift, removal, transport of scaffold
and scaffold, not in the door frame which dragged on.
5.6 installation of equipment and piping
should be protected from material damaged doors and Windows.
5.7 no stand at the window sash.
5.8 sash installed in time after installing
hardware, turn off the window lock to prevent wind damage to doors and Windows.
5.9 no nail hammering, or carved on the
doors and Windows, no scraping or scrubbing with a hard object and other
resources to clean up the Windows and doors.
6 quality problems to be noticed
6.1 transport storage damage: when
transported with care, when stored in the warehouse with sleeper pad flat on
the ground and direct deposit, and should be kept away from heat sources.
6.2 door window frames loose: installation
Shi should first in door window box Shang by design provides of location drill,
with since attack screws will plating zinc connection pieces tight solid;
electricity hammer in doors and Windows hole playing hole, loaded into nylon
expansion tube, doors and Windows installation Hou, with wood screws will
connection pieces fixed in expansion tube; single brick and the light wall,
should masonry concrete block wood brick, to increased and connection pieces of
pulled knot firm degree, makes frames installation Hou not loose.
Plastic doors and Windows installation
tolerances in table 8-5
Project tolerance (mm) test method
1 door and window frame two diagonal
difference ≤ 2000mm
>2000mm 3
5 steel measuring tape to check
2 sash and casement window box poor lap
width 1 depth gauge or a steel ruler to check
3 casement window Tang door adjacent to
door cross corner width difference of 2 plates, cable and check
4 door opening force limit fan size ≤ ≤ 40N 1.5m2 100N
spring scale hook
Push-pull fan door opening force limit fan
area >1.5m2 60N hand hoist 5 average
5 door sash and frame or adjacent State
edge parallel 2 1M steel ruler check
6 door lip sewing or fan and box joints
limit State transverse joints between 2~4
7 spring door door leaf and ground
clearance joints limit 2~7
8 door counterpart sewn shut down level 2
with depth gauge check
Door and window frames (spell-containing
Tang), a ≤ 2000mm 2 1M side vertical supporting plate check
9 door and window frames (spell-containing
Tang), side vertical >2000mm 3 1M supporting plate check
10 door and window frames (spell-containing
Tang) level 2 1M level of scale and wedge feeler Gage check
11 steel plate for door and window frames
at 5 feet checked, compared with baseline
12 double doors and Windows inside and
outside the frame, jamb (spell-containing Tang) Center from the 4 with a steel
ruler to check
6.3 the window frame and the wall gaps are
not filled soft material: fill in soft materials such as styrofoam or mineral
wool, with walls formed of elastic connections.
6.4 after Windows installation variants:
filling too hard and big, made of extrusion deformation shall not spread take a
scaffold on the doors and Windows.
6.5 sash does not block sealant: should
operate according to the drawings.
6.6 connection screws hammer directly
within the getting started window frames: no first use a hand drill drill by
the rules, then turning the screw.
6.7 pollution protection measures, cleaning
is not serious.
6.8 hardware damage: due to improper after
installation, do not pay attention to when using.
7 quality records
This standard shall meet the following
quality records:
7.1 Windows product certificates and test
reports.
7.2 hardware certification.
7.3 heat preservation material proof of
caulking materials and factory certificate.
7.4 seal plastic factory certificate, and
instructions for use.
7.5 quality inspection and assessment of
records.