1 scope
This technology is applicable to
prefabricated cavity structure construction technology of waterproof wall
panel.
2 construction preparation
2.1 materials and equipment:
2.1.1 General spontaneous styrofoam
(polystyrene Board for short), thick 15~20mm.
2.1.2 PVC soft plastic sheet, the thickness
of 1.5~2mm.
2.1.3-PVC soft plastic pipe, 20mm.
2.1.4 building asphalt, or 30th, 30th, five
oils or use an ordinary pitch, or 65th, 75th.
2.1.5 cooling oil, or 3%-methyl-sodium
(silicone).
2.1.6 polyethylene acid formaldehyde (107
glue).
2.1.7 No. 350, asphalt paper linoleum.
2.1.8 PVAc (emulsion).
2.1.9 cement: No. 325 of ordinary Portland
cement and slag Portland cement.
2.1.10 sand: clay is less than 3%.
2.1.11 waterproof grease. (Clay): building
gel, PVC cement, two-component polyurethane sealing cement, chlorosulfonated
polyethylene sealant, etc. According to the design requirements.
2.1.12 waterproof coating: Chloroprene
LaTeX asphalt coating, PVC coating, polyurethane coating, according to the
design.
2.1.13 fish oil or light oil.
Note: the above material must comply with
the design requirements for quality and performance.
2.1.14 main tools: hand saws, cutters,
scissors, rulers, scrapers, wire cutters, caught in the electric stove, boiling
tar buckets, water tube, rubber tube.
2.2 operating conditions:
2.2.1 cutting insulation: polystyrene with
a resistance wire cutters cut into strips, wide depending on the design
drawings of the exterior wall construction, width, and length longer than the
cavity waterproof wall panel slots 50mm. Polystyrene Board long enough, kraft
paper, coated polystyrene LaTeX long available.
2.2.2 cutting linoleum: linoleum cut with a
saw, long width the same as polystyrene.
2.2.3 asphalt felt waterproof thermal
insulation: the asphalt with a furnace or water boil (boiling temperature
should not be too high in order not burn polystyrene), linoleum and polystyrene
with hot asphalt cement pressure.
2.2.4 cut plastic: PVC panels cut into
strips. Length and width must be adapted to and crack width, its width set
width and 25mm, height of high layer 100~150mm, for closing the cavity and
catchy, cut a circular-arc notch at the lower end, to arrange for water holes.
2.2.5 plastic pipes: polyethylene plastic
pipe cut into 60mm pieces, one end cut point reserve, as shown in Figure 4-43.
Figure 4-43
2.2.6 checking sizes and shapes of
waterproof wall panel construction is complete, if there is damage, congestion,
voids and defects, should be carefully repaired.
2.2.7 vertical slot and cavity wall panel
brushed waterproof coating. With cold methyl-sodium silicate solution in oil or
3% the end of paint coats.
2.2.8 when above the first floor for the
reinforced concrete in the basement when the prefabricated wall panels, first
floor drawings should be now-long monolithic concrete water outside weathering.
Should be reserved in the Foundation or basement beams reinforcing, with
vertical bars, water the beans after the formwork concrete, concrete strength
up to 5MPa, installed the first layer of wall panels, as shown in Figure 4-44.
Figure 4-44
3 operational processes
3.1 process:
Vertical seam sewing waterproof waterproof → do → do
cross-seam waterproof waterproof →
→ other parts tricking water test
3.2 State joint waterproofing:
3.2.1 insert asphalt felt waterproof
insulation: once when the siding is installed in place, steel welding keyway
immediately, exterior-wall nodes (column) before the reinforcement, asphalt
felt waterproof thermal insulation block inserted in the end, around tight, no
bulge cracking or segmented plug. Width of a asphalt felt waterproof insulation
should be appropriate to prevent when poured wall concrete. Plug the cavities.
Vertical wall panel as shown in Figure 4-45.
Figure 4-45
(A) longitudinal walls; (b) gable
3.2.2 inserting plastic: according to the
actual width used for inserting the proper size waterproof to prevent too
broad, too narrow, tank stripping, crimping slippage, if such phenomena should
be replaced immediately. Water transfer to waterproof upper with document
closely and lower into the water on the slopes to an enclosed cavity
waterproofing to prevent debris falling into the cavity. Construction
waterproofing must be synchronized with layers from the top down when inserted
into the cavity, no plug from behind the outer wall face. Before inserting
waterproof, to check the State after seam cavity of asphalt felt waterproof
insulation for damage should be repaired; will be spilled mortar pouring
columns clean stones and other debris, such as vertical seam is too narrow when
unable to clean, this gap can no longer do construction waterproofing, should
be treated with waterproof grease embedded solid fill into the waterproof
material. Plastic article itself is flexible, easy to bend inserting and as
bottom of the jointing mortar, so when the mortar joint, force should not be
too large, to prevent the water off trough caused the cavity plug.
3.3 do sewing waterproof:
3.3.1 sewing effect depends mainly on
siding installation. Therefore, wall panels in place to reach the upper and
lower vertical flat pad height is appropriate. Is water, water protection,
ensure flat cavity full, straight and smooth. Cavity into linoleum volume,
cement mortar on the outside. Linoleum rolls as bottom of the jointing mortar,
when the joint force should be uniform, and should not be too large, to prevent
the linoleum go into plug cavity. Sewing waterproofing as shown in Figure 4-46.
3.3.2 when pishui with water to touch or
with leakage when the plug cannot be picked off, all such joints should be
filled with waterproof ointment or plaster, cement mortar outside. When sewing
too wide or water damage, was wrong in the water to large, first in the joints
"6" or "8"-shaped linoleum rolls, outside the cement
mortar. As shown in Figure 4-47.
3.4 cross-seam waterproof: Gou Li joints,
horizontal joints before the mortar insert the semi-circular plastic drainage
pipe cross stitch, to stick wall 15mm, and tilted down. Construction should be
checked before the upper end of the vertical seam of plastics come into contact
with water tight, height and volume is appropriate, as there are gaps must be
sealed with grease. Should be at the top of the lower plastic plug on the back
side of the retaining wall, sealing upper, upper plastic bottom insert to lower
on the weathering of exterior wall panels. Cross joints waterproofing as in
Figure 4-48.
3.5 other waterproof material:
3.5.1 balcony (including anti-slot balcony,
and flat balcony) waterproof: balcony of Shang, and Xia side state sewing must
with ointment embedded sewing, outside hook mortar protection, Xia sewing
embedded ointment of length ends the many Yu 30cm, Shang sewing as met blind
sewing Shi, to out 20mmx20mm gap, cleanup clean, brushing cold Foundation oil
Hou, again embedded ointment, side state sewing and upper wall Board empty
cavity State sewing handover at should pass long embedded ointment, do drainage
slope, left drain. Seam between two adjacent balcony plates are pointing up and
down, separated by gel workmanship in compact. Balcony waterproofing is shown
in Figure 4-49.
Figure 4-46
3.5.2 waterproof rain cover, awning
waterproofing references balcony.
3.5.3 wall waterproofing: used when
constructing a waterproof, and sewing and the sewing practices the same wall
panel, vertical joints should be embedded in a waterproof grease on the inside.
When waterproof material is used, you must enable sewing, outside seam, sew,
Neili seam seal, vertical seam embedded grease and tar the roof lap. Bean stone
parapet at the top do concrete top and flashing (flashing).
3.5.4 wall tube hole must grease
workmanship according to design requirements. In the flat, vertical joints in
case of through-wall pipe hole, must the entire block filled grease. At the
time of construction, hang shelves on the wall outside the cave, waterproof
mortar should be used plug, located 2cm impaction waterproof mortar, mortar
screed outside.
3.6 after the exterior caulking, paint two
waterproof coating, thickness should be not less than 1.5mm to prevent water
seepage because of shrinkage crack of mortar.
3.7 grease joint construction should pay
attention to the following points:
3.7.1 joint parts of the base surface must
be smooth, solid and dry and clean up the joint contact surfaces of dust,
debris, then brush the cold oil, ointment: petrol =3:7 prepared with cold oil,
dried caulking processing.
3.7.2 when filleting ready-made rub
ointment into strips into joints within the diameter of 20mm, then the valve
compact, or within the crowded block in the gap with caulking gun; as low
temperature grease hard, softened ointments can be properly heated (baking
temperature: 60 ℃ below), fill in the seam with a scraper in the compaction.
Paragraph 3.7.3 joint grease must be
considered compact, which bond without breaking. Phenomena such as peeling,
open, pendulous; ointment after the block, surface brushing cold oil, grease
seam painted on both sides, then the valve flat and compact. To prevent
sticking, when in the hands, wipe a small amount of fish oil on the valve or
light oil, no oil to avoid bonding fragile joints caused seepage.
3.8 tricking water test: tricking water
test is a waterproof wall panel the last operation, cavity proof after all, did
not engage in external decoration must be carefully tricking water test,
testing the waters and make records.
4 quality criteria
4.1 project:
4.1.1 for waterproof quality and technical
properties of various materials, you must meet the requirements of
specification for design and construction; must have manual and quality
certification. And a "certificate", prior to the second interview.
4.1.2 wall plates, wall plate waterproof
structure must be complete, type, size and shape must comply with the design
requirements and the relevant provisions, members should also have the factory
certificate.
4.1.3 walls, balconies, rain cover, wall
boards after installation, its elevation, Board width, pulp thickness should
comply with the design requirements and provisions of the code.
4.1.4 ointment caulking must be tight,
bond, no cracks, seams on both sides of cover width exceeds the not less than
20mm.
4.1.5 waterproofing coating must be flat
and evenly, without falling off, peeling, cracking, blistering and other
defects.
4.2 Basic project:
4.2.1, balcony plates, wall plate cover
plate, wall Board Joint waterproofing construction completed, vertical sewing,
sewing, cross stitch tricking water test to check.
4.2.2 issues tricking water test, to
identify the cause of leakage and repaired in a timely manner, and continued to
do after tricking water test until no more when a leakage occurs, may be
carried out outside finish construction.
Location and repair the leakage point 4.2.3
should be carefully recorded, indicating the location, as the technical
information included in the technical file for future reference.
4.2.4 joint grease surface density, cold
oil should be uniform, protective layer of caulking bond, cover tightly.
5 finished product protection
5.1 when padded waterproof caulk and paint
coatings, no pollution, such as walls, Windows and doors.
5.2 when repairing leaks, should pay
attention to protection of walls, balconies, rain cover place the decorative
surface layer.
6 quality problems to be noticed
6.1 outside wall Board installation
deviation big: Board end of pad gray too much, will makes was water super high,
caused flat cavity exposure; Board end of pad gray too less, caused Xia sewing
Yu touch, no empty cavity drainage: Board end of pad gray uneven, produced flat
cavity end water drainage not Chang, and will caused State sewing Shang BU
width ranging, insulation article, and waterproof article construction
difficult; lifting outside wall Board Shi, upper and lower two block is not a
level surface Shang, pishui and the block water Taiwan dry touch, caused
capillary sucking water into indoor; Board itself geometry size not
specifications, has errors, also will produced above phenomenon. Therefore, the
installation quality of waterproofing and exterior wall cavity are closely
related.
6.2 water leakage:
6.2.1 plastic tube off, curled, skew, too
soft, back seam to form vertical seam cavity, resulting in leakage of water.
6.2.2 top and water without the plastic
seal, not on the plate at the lower end of the drainage slopes made sewing,
sewing the leakage of ash and other debris does not clean wall plate defects
did not fix or repair improperly, resulting in leakage.
6.2.3 standing seam, flat seam jointing
force too much would set a joint plastic deformation or extrusion with
waterproof and thermal insulation paste, so retaining wall drainage; or cavity
fill linoleum rolls squeezing leaned back against the label of water plugging
cavities, resulting in leakage.
6.2.4 balcony, rain cover, parts of the
wall materials such as waterproof, does not meet the requirements of
construction quality, resulting in water leakage.
7 quality records
This standard should share the following
records:
7.1 component factory certificate.
7.2 waterproof material factory certificate,
instruction manual, sample inspection report, the permit card and without
security.
7.3 wall panels tricking water test
records.
7.4 covert inspection records.
Because of the war, many people become homeless. I can't do it well. Please help me.my PayPal is xhhnet@163.com.