Tuesday, November 22, 2016

Installation technology of air handling unit

1 scope
This technology is applicable to industrial and civil building air handling equipment, sectional air conditioner and air conditioning box installation works.
2 construction preparation
Requirements 2.1 materials and equipment:
2.1.1 installation process uses a variety of profiles, bedding, hardware supplies the factory certificates or related documents.
2.1.2 in addition to the above documents should also be carried out Visual inspection, no serious damage and corrosion and other defects.
2.1.3 flange connections using the litter should be selected in accordance with the design requirements and meet the requirements of fire-proof, moisture-proof, corrosion-resistant performance.
2.1.4 other installation materials used by cannot be installed because of a quality problem affecting the quality and effect of use.
2.1.5 windlass, carts, chains, pulleys, rope, steel ruler, set square, adjustable wrench, pliers, screwdrivers, wire, steel tape measure, level, wooden hammers, hammers and other tools.
2.2 operating conditions:
2.2.1 installation check before the scene, should have plenty of space.
2.2.2 before installation clean the installation site, and no other piping or equipment to prevent.
2.2.3 device model, device based on size and location, the design requirements.
2.2.4 building devices out of the box the unit tests complete with spare parts, equipment shall be valid. The data with the device and product certificate should be completed. Imported equipment must have a commodity inspection departments inspected the file.
2.2.5 opening inspection records.
3 operational processes
3.1 process

Sectional set in place
Equipment acceptance check transport air handling unit out of the box
Monolithic installation

Leveling find quality control

3.2 device out of the box to check:
3.2.1 with the construction and equipment supply departments, has checked out of the box.
3.2.2 check boxes before opening the box, box number matches the documents provided. Then check on the packaging, there is no damage and moisture.
3.2.3 upon opening the box carefully check the device name, specification, type conformance to design drawings. Product specifications, certificates are included.
3.2.4 packing list and technical documents, check host attachments, special tools are complete, surface with or without defects, damage, corrosion, moisture, and so on.
3.2.5 open device activity panels, with their hands moving fan there is no impeller and casing touch metal, fan shock absorber specification parts.
3.2.6 the inspection results recorded, involved in opening inspection responsibilities have been signed and sealed, as evidence of the transfer of information and Of plant.
3.3 equipment transport:
3.3.1 equipment should be used when handling the small trailer.
3.3.2 devices when lifting, equipment lifting points, lifting when there was no lift, lifting points shall be located in the metal base of the air on the main beam.
3.4 air conditioning unit installed on the segment group:
Modular air conditioning unit is not cooling, heat, water and steam for the media to feature styling products for the combo unit, when installed according to the following steps:
The paragraphs 3.4.1 installation first check the metal air line with the drawings, the equipment installed in the body paragraphs, if the part is a complete non-destructive and accessories must be complete.
3.4.2 used in the ready to install bolts, gaskets and other materials and the necessary tools.
3.4.3 installation site must be formed, processed steel air tank base in place (or pouring concrete piers) and leveling.
3.4.4 when several AHU installation site, be careful not to field is wrong, tell the difference between left-and right-(sight downstream direction observation or according to the manufacturers instructions). Order content-ID must match the drawings. Before installing on the numbering of paragraphs.
3.4.5 from end of air conditioning devices, each body carried to the base after the correction location, plus liner, adjoining segments bolted tight and firm. Before each connection segment, internal cleaning.
3.4.6 and section connected to the heating section should be used in heat-resistant gaskets, surfaces or gaps between the application of the heat exchanger heat blocking material.
3.4.7 surface heat exchanger for cooling the air in the lower drainage should be established.
3.4.8 air handling units are installed, connections between its various functions should be tight, the whole flat. Check door opening flexible waterways.
3.4.9 site Assembly of the air conditioning unit, air leakage testing should be done. Air leakage requirements shown in table 4-28.
Table 4-28
Unit properties static pressure air leakage rate
General air conditioning units keep 700Pa not more than 3%
Below the class 1000 clean keep 1000 Pa is less than 2%
Than, equal to, class 1000 clean keep 1000 Pa is less than 1%

3.5 air conditioning unit installed:
Cold source of air-conditioning unit (split and air-cooled units as a whole):
3.5.1 split outdoor unit and air cooled whole unit installation, surrounding space to meet the requirements of cooling air circulation and environmental regulations.
3.5.2 installation of indoor unit is correctly positioned, eye level, condensation water discharge flow.
3.5.3 overall unit installed in the following order:
3.5.3.1 earnestly familiarity with drawing paper, equipment instructions before installation, as well as relevant technical information.
3.5.3.2 where air conditioning unit installed must be flat, should generally be higher ground from 100 to 150mm.
3.5.3.3 air conditioning units if required install shock absorbers should be strictly according to the design requirements of the shock absorber type, quantity and location to install, level alignment.
3.5.3.4 the cooling water system of air conditioning units, steam, hot water pipes and electrical power and control circuits, installed by plumbers and electricians.
3.5.3.5 refrigerator without charge freon for air conditioning unit should be under the guidance of senior workers or manufacturers, charging according to product specification.
3.6 other types of equipment installed
3.6.1 effect or HEPA filter must be installed in a clean room completed cleaning and test 12h to check out of the box, qualifying immediately after installation.
3.6.1.1 must seal between the filter and frame padding thickness for 6~8mm. After installing padded compression ratio should be greater than 50%.
3.6.1.2 liquid seal, truss installed horizontally grooved sealing liquid at least 2/3 deep within.
3.6.1.3 installations, should be consistent with the direction of flow the arrow on the outside box, corrugated plate corrugated vertical installation of the filter must be perpendicular to the ground may not be reversed.
3.6. more than 1.4 when more than one filter Assembly, according to the initial resistance of the filter size allocation, each rated resistance and the difference of average resistance should be less than 5%.
4 quality criteria
4.1 project:
4.1.1 air handling unit construction connections must be tight and spray water is strictly prohibited.
Inspection method: Visual check.
4.1.2 HEPA filter must have the correct mounting direction; composite corrugated filter in vertical installations, corrugated sheet must be perpendicular to the ground. The connection between filter and frame no leakage, plastic deformation, damage and leakage, and so on.
Inspection method: observation of air leakage test check and check records.
4.1.3 cleaning system of air, filters in rooms after installation must ensure that the wall clean, free from dust, grease, rust and other debris.
Inspection method: observation or white silk cloth to check.
4.2 Basic project:
Subparagraph 4.2.1 air handling unit installation or installation, installed smooth, smooth. Solid, no significant gap in four weeks. Primary, secondary air Regulation valve and air control valve flexible regulation.
Inspection method: standard and Visual check.
4.2.2 enclosed viewing window should be consistent with doors and frames, smooth, strong, leak-free, flexible switching requirements, water condensation drainage tube (Groove) are clear.
Inspection method: splash and close inspection.
4.2.3 surface heat exchanger installation framework for smooth, firm, smooth installation. Between the heat exchanger and heat exchangers and envelope around the gap seal.
Inspection method: lever and observe the examination.
4.2.4 installation of the air filter should be installed smooth, firm; filters and framework, the gap between frame and envelope seals; filter for easy removal.
Inspection method: lever and observe the examination.
4.2.5 window air conditioner installation should conform to the fixation, shade, rain-proof measures, condenser exhaust air is not stopped, condensed water tray should be around the slope and the gap closed. Around the positive horizontal even vertical and gap seals to coordinate with the Interior appearance.
Inspection method: Visual check.
4.3 allowable deviation:
Air handling equipment installation tolerances and testing methods should be consistent with table 4-29.
Equipment installation tolerances and inspection methods table 4-29
Project tolerance (mm) test method
Horizontal error 1M Michael Jackson-3 cable, fluid connectors and check
1M Michael Jackson-2 hanging vertical metal air conditioning equipment and standard inspections
5M Michael Jackson-10

5 finished product protection
5.1 air processing unit after installation, external protection measures prior to Unicom systems, should not be damaged. To prevent debris falling into the unit.
5.2 air conditioning unit installed after the formal transfer of the use cases, air conditioning facilities should have a special guard to protect. Prevent damage to the missing parts.
5.3 If the accident should immediately report the relevant department heads, to take measures to deal with.
5.4 press factory mark, high efficiency filters should be in vertical transport and storage in a clean room, and moisture-proof measures.
6 quality problems to be noticed
6.1 installation of air conditioning equipment should pay attention to quality issues as shown in table 4-30.
Installation of air conditioning equipment should pay attention to the quality of table 4-30
Ordinals often quality control measures
1 no coordinates, elevation, stereo enhanced sense, strictly according to the design and operational requirements

Connection between paragraphs, padding specifications are not made as required,
Gasket leakage phenomenon
Cooling coil water line out
4 HEPA filter frame or efficient air leakage in strict accordance with the design and operation process

7 quality records
7.1 inspection projects and inspection record form.
7.2 entry equipment inspection records.
7.3 device engineering acceptance record.
7.4 assembling air conditioners air leakage inspection records.
7.5 General ventilation system operation records.
7.6 air quality inspection and assessment of manufacturing and installation project tables.
7.7 unit project impression quality assessment form.
7.8 acceptance record.

7.9 out of checking and cross-checking records.

No comments:

Post a Comment