1 scope
This technology is applicable to general
industry and civil architecture wall dry stick stone construction.
2 construction preparation
2.1 materials and equipment:
2.1.1 cement: No. 325 and more cement or
Portland cement, color uniformity, should adopt the same products, the same
number of cement. Product certification.
2.1.2 sand: sand 5mm before using the sieve
of aperture, or if necessary yarn tension and the screen, screen good
alternate.
2.1.3 gravel: hard particles, not
containing clay, film, alkalis and other organic substances and other harmful
substances. Selection of its specifications, the design requirements, eight per
cent in size of 6mm, small eight percentage point size is 4mm, sift before use,
make it with uniform particle size, meet the above requirements. Sieve with
water after wash to dry, color-coded stacking, with canvas cover above.
2.1.4 lime cream: one month before using
lime braised, 3mm sieve of aperture, shower of lime paste, when gypsum mortar
must not contain particles and impurities that are not cured.
2.1.5 pulverized quicklime: using water to
stew through the week before, unripened granules should not.
2.1.6-fly, 107 glue, adhesives or certified
and factory certificate, and instructions for use.
2.1.7 main equipment: mortar mixers, iron
trowel, wood float, plastic trowel, big bar, mini bar, MI Li, small wooden
racket, small sieves 30cmx50cm several, small plastic rollers, small child,
foot boards, gravel screening 30cmx80cm.
2.2 operating conditions:
2.2.1 shelf pitched well in advance, the
best selection of scaffolding or bridge shelf double exclusion, the use of
double exclusion shelf, it should at least guarantee the operation there are
two frames of scaffold, the horizontal rod and tie rod, Rod spat 200~250mm
should leave doors and Windows, step should be to meet the construction needs
of the shelf.
2.2.2 reserved hole dimensions in the
drawings should be of good equipment, embedded parts should be installed and fixed
in advance, door and window box installed and fixed with the wall, the cracks
filled dense aluminum alloy door and window frame corrosion and surface
protection film in advance.
2.2.3 wall surface grass-roots cleanup
clean, feet hand-eye blocking good, concrete had beam, and circle beam, and
combination column,, will its surface cleanup clean, highlight wall surface of
concrete tick flat, recessed to part should watering Yin through Hou, with
water heavy 10%107 rubber of 1:3 cement mortar layered fill flat, each layer
fill wipe thickness not should is greater than 7mm, and each again wipe Hou not
should with have too tight. Aerated concrete panel grooves at the patch
application with water 10%107 rubber 1:1:6 of the mortar mix layer fill, joints
must also Gou Ping, Yan. Precast concrete wall panels have dealt with
waterproof seams, after tricking water test, leakage-free.
2.2.4 construction technology, technology
to give the low-down to the operator.
2.2.5 model before construction of large
area walls, by the person concerned after acceptance, construction model can
request.
3 operational processes
3.1 process:
Checks → base → shelf
hanging vertical, looking for plaster cakes, gluten-filled → rules → base →
Line → cells → viscosity
stick stone mortar from the Pat down, finishing stone → → → viscosity, dinging →
conservation
3.2 grass-roots operation method of
concrete wall panels:
3.2.1 grass-roots processing: on with steel
die construction of concrete plate should for tick hair processing, board
surface Shang has crisp skin of should will crisp skin tick to, or with
concentration for 10% of caustic soda water will board surface of oil brush
off, with of with water will its lye flush clean, dry Hou with 1:l cement fine
mortar (therein of sand should had yarn stretched screen) with water heavy 20%
of 107 glue mixing uniform, with empty pressure machine and the spray bucket
will mortar spray to wall Shang, or with broom will mortar dumped to wall
Shang, requirements spray, and dumped uniform, end gel Hou watering
conservation, 3~5d at room temperature, until all lumps of cement mortar cured
on a concrete plate, break with one fixed it.
3.2.2 hanging vertically, set square,
looking for rules: If the building is the top, in the corners and door window
on both sides, using theodolite find vertical. For multi-storey buildings can
be hoisted vertically from the top with a big line, stretched wire to find the
rules and layered plaster cake. Line the floor elevation datum for coil
control, at the end of each layer to gray pie base screed strip so that its
bottom ash horizontal even vertical.
3.2.3 wipe bottom mortar: wipe Qian brush a
mixed water 10% of 107 rubber cement pigment pulp, follow with layered points
again wipe bottom mortar, at room temperature Shi can used 1:0.5:4 (cement:
lime cream: sand), winter Shi shi application 1:3 cement mortar playing end of,
wipe to and rushed of reinforced a usually, with big bar scraping flat, wood
wipe child rub hair, end gel Hou watering conservation.
3.2.4 spring line, cells, cell adhesion,
drip line: the line drawing size, grid, and set the grid width as required,
should be horizontal even vertical grid surface, smooth and consistent, and
stick according to site requirements for drop tanks, their width, depth, the
design requirements.
3.2.5 Visco-stone mortar, adhesive stones:
Visco-stone mortar, glue there are two stone mortar, one is within the pigment
slurry cement 20%-107 adhesive compounded with the polymer cement slurry; the
other is polymer cement mortar and mix cement: Lime plaster: sand: 107 gum
=1:1.2~2.5:0.2. The plastering layer thickness, selected according to gravel
size, generally sticking stone mortar should be less than 1~2mm. Stick stone
mortar surface should wipe flat, then stick stone, used dumped stone stick
stone, its method is hand took end of nail screens of small sieve, screen
within loaded gravel, another hand took small wood took, shovel Shang gravel
Hou in small wood took Shang Hoang about, makes gravel uniform to sub cloth in
small wood took Shang, again to stick stone mortar Shang dumped, requirements a
took received a took to dumped, to will gravel dumped strict, and dumped
uniform, dumped Shi application small sieve then off down of gravel, stick
stone Hou timely with clean of wipe child gently to will gravel pressure into
gray layer among, requirements will gravel grain diameter of 2/3 pressure into
gray in the, Exposure of 1/3, and to the principle of not gel paste and
bonding. After treating the water slightly steaming ash, with the trowel vertically
from bottom to top to slip again, to eliminate traces of the stone.
For large area sticky stone walls, use
mechanical shotcreting construction, shotcreting should promptly after rubber
roller rolling, gravel onto the ash layer 2/3, their bond.
3.2.6 construction procedures: arch face
doors and Windows, balconies, rain cover should be set according to the
requirements, such as throat, its width and depth, the design requirements.
Stick stone should stick after a small stick surface, surface, small intersection
angle put sticky lime should be used when the character on foot, feet when
screening small grain of rice by the end of stone repair black to make it bond
dense stone tablets.
3.2.7 dressing, and processing black side:
stick finished stone Hou should timely check has no didn't stick Shang or stone
grain stick of not dense of place, as found Hou water brush dipped water dumped
in its Shang, and timely fill stick stone grain, makes its gravel bond dense,
and uniform, found gray layer has pendant crack phenomenon, also should in gray
layer end gel yiqian dumped water will crack pressure real. Corner a black side
should be feet time after sticky rice stone and shoot it.
3.2.8, bars, caulking: after you stick the
stone gravel with a trowel onto the ash layer in time 2/3, iron trowel and
gently slipped up again to reduce scars. Then out grid, drop tank, using trowel
after ash layer after gently press to prevent adhesion of lime bottom ash to be
pulled while, formed after the empty drum. Plain cement paste can be used to
sew after Gou Ping, hook. Ash again after all the dry joint.
3.2.9 water conservation: stone
construction viscosity at room temperature after 24h, you can use the watering
can water conservation.
3.3 base for brick wall method of
operation:
3.3.1 base treatment: clean walls,
highlight the concrete wall tiqu, water wet walls.
3.3.2 hanging vertically, set of square,
looking for rules: wall and four-line rules, must start at the top with a
special large pendant hanging full height vertical lines, and in the yin and
Yang of wall corner and window sides, Duo and other parts under the gray
vertical line, column, pie, plays the upper and lower horizontal lines in the
window, anyway perpendicular injection gas cake circle.
3.3.3 the underlying mortar: normal
construction mixture ratio of 1:0.5:4, mixing mortar or 1:0.2:0.3:4 of fly ash
mortar mix, winter construction mixture ratio of 1:3 for cement mortar and
mixed with a certain proportion of antifreeze. Base must be forced to squeeze
into the mortar joint of mortar, and erase twice and ribs, tie bar anyway,
scrape, rub wood trowel, water conservation the next day.
3.3.4 cell adhesion: according to the
drawings of the width and depth of cell adhesion, with plain cement paste on
both sides of eight fixed, line, should be responsible, so that the grid size
to fit drawing. This should be done before in cell adhesion.
3.3.5 Visco-stone mortar, adhesive stones:
stone quality to ensure viscosity, Visco-stone mortar mix is slightly
different, the current general use 6mm 1:3 cement mortar, followed by 2mm
polymerization of cement plaster (cement: 107 gum =1:0.3). Then stick stone
stone into the ash layer 2/3 and viscosity, to shoot, shoot. Sticky when stone
mortar should be part of the grid after both sides in order to prevent the
wooden lattices of absorbing water, gray morning on both sides, stone impact
viscosity effects. Stick stone should be cell adhesion on both sides first and
then stick the middle section, when sticking a plate after plate continuous operation,
require stone tablets-adhesive evenly close-grained, prison, after no water,
with the trowel and gently slip away again.
3.3.6 construction program: top-down
construction, doors and Windows, balconies, soft face the rain cover to
indwelling throat, its width, depth, the design requirements. Stick stone
should first stick small, sticky surface after.
3.3.7 trim, black-edged; sticky lime is not
before the final set, should check the glued stone surface, identify problems
and repair; yin and Yang Kok should check the flat and vertical, check the Horn
parts have no black edges, processed in a timely manner after it was
discovered.
3.3.8, bars, caulking: to be repaired,
grid, drop tank and, later with the trowel and gently press to prevent adhesive
layer when you pull up, after the formation of hollow. The next day, watering
moist plaster with cement jointing.
3.3.9 water conservation: 24h at room
temperature, with watering can water conservation stick stone surface.
3.4 grassroots for aerated concrete method
of operation:
3.4.1 grass-roots processing: will added
gas concrete Board spell sewing at of mortar wipe flat, with broom will surface
dust, added gas fine not sweep NET, watering Yin through, hook Board sewing,
with 10% (water heavy) of 107 glue mud brush a again, follow with with 1:1:6
mixed mortar layered hook sewing, and on deficiency ribs off angle of Board,
layered fill flat, each layer thickness 7~9mm.
3.4.2 the underlying mortar: one of the
following two methods can be used.
3.4.2.1 on aerated concrete panels in the
wet brush 20% 107 adhesive mud mixed with water, followed by a thin shaving a
1:1:6 mortar mix, with a broom to sweep out the vertical lines, water
conservation after the final set, bonding with mortar and concrete, hand break
does not move. Can be hung vertically, set rules, Chong tendons, the underlying
mortar.
3.4.2.2 in wetting of aerated concrete
panels, spray or dump a 20% 107 glue mixed with water mixed mortar mix
synthetic 1:1:6, requires the pimple to spray, left even after the final
setting of water conservation. Spray, after mortar and concrete bond flick, to
be hung vertically, sets, rules, the underlying mortar.
Bottom mix 1:1:6 mix mortar, layered
application, each ply should be controlled 7~9mm, bottom ash and Chong Jin smooth,
big bumper anyway, scrape, rub wood trowel, after the final setting of water
conservation.
3.4.3 sticky cells, throat: according to
the drawing requirements section line grid, sticking, requiring surface
horizontal even vertical grid.
3.4.4 Visco-stone mortar, throwing gravel
adhesive stones: the method is the same.
3.4.5 operation program: top-down
construction, Arch face doors and Windows, balconies, rain cover should be
sticky after small sticky surface, cell adhesion on both sides and then stick the
Center. Stick large and small personal corner stone character should be used on
foot. Throat width and depth should comply with the design requirements for
retention.
3.4.6 trim, Black Sticky lime is not final
setting should be checked before the sticky walls with and without defect,
found that the problem should be trimmed in a timely manner, as a black, Shan
rice stone water viscosity.
3.4.7, bars, caulking: Visco-stone built,
grid and drip out in a timely manner, with a trowel and gently press the next
day with plain cement plaster joint.
3.4.8 water conservation: 24h at room
temperature, with a watering can water conservation.
Winter construction of 3.5:
3.5.1 plastering mortar insulation measures
should be taken, the mortar on the wall temperature should not fall below + 5 °
c.
3.5.2 plastering mortar layer hardening
beginning not from the cold. When the air temperature is below + 5 c, outdoor
plastering can lower the freezing temperature of the additive should be mixed
into, its content determined by experiment.
3.5.3 freezing masonry walls, outdoor
plastering construction should be completely thawed, shall not be washed with
hot water freeze wall or eliminate frost on the wall.
3.5.4 plaster should not be mixed with lime
plaster, to ensure that operations can be used with volume fly ash instead of
to increase workability.
4 quality criteria
4.1 project: the variety and quality of the
material must meet the design requirements. The plaster layer and must bond
between plaster layer and the substrate, no delamination, hollowing and cracks
and other defects.
4.2 Basic project:
4.2.1 stick stone stone surface particle
bonding, distribution, surface roughness, color, don't Cha, no exposed pulp,
leak-free sticky corner without black edges.
4.2.2 uniform grid width and depth, (seam)
is smooth, Leng corners neatly, horizontal even vertical, smooth.
4.2.3 drop line (Groove) flow direction is
correct, drip line straight, throat width and depth is not less than 10MM. Neat
and consistent.
4.3 allowable deviation, as shown in table
9-6.
Dry stone wall surface tolerance table 9-6
Project tolerance (mm) method
1 façade vertical 5 2m supporting plate
check
2 surface flat 5 2m on foot and wedged
feeler Gage check
3 angle vertical 4 2m m on foot and wedged
between yin and Yang feeler Gage check
Founder 3 2cm 4 corner feet and wedged
feeler Gage check
5 sew straight 3 5M line, less than 5M
Latrun Ray
6 full-height vertical single-layer,
multi-layer h ≤ 20 ‰ and transit checks
Senior h ≤ 30 ‰ and transit
checks
Note: h is the total height of building
facades.
5 finished product protection
5.1 mortar on the door and window frames and
shelves should be cleaned in time, scattered in the gravel on the shelf should
be recovered in time. Aluminum alloy doors and Windows shall be protected,
protective film on it intact.
5.2 the Board, remove the shelf do not
impact dry stick stone walls, sticky corners after the stone should be
protected to prevent collisions.
5.3 Oiler oil brush is strictly prohibited
when stepping on the pedal sticking stone surface and edges, do not stick the
tank off the pollution stone walls.
5.4 do brush the stone should be protected
before sticking stone walls, preventing brush stick stone stone cement
pollution.
6 quality problems to be noticed
6.1 stick stone surface roughness, color:
sticky lime uneven, stick stone hard and uneven; when you press the glued stone
plasters thick places after a slurry, plastering thin ash layers occur at the
pit, sticky stones, followed by nothing. Gravel floating in the surface color
is heavy, and pulp white, owing to stone surface layer of flowers, different
colors.
6.2 grid appears on both sides of the
corner and black side: Ash dry faster on both sides, gravel on a stick; angle
without the use of eight feet, feet and not repaired. Price should stick then
stick at large, Yang Kok stick stone character should be used by foot, feet
time after using the stone rice patches and black border.
6.3 a gravel float, flat touch: Ash layer
dry too fast, stick stone cannot move, or clap hard enough; end of stick and
stone dust should be watered on moist, sticky after stone to tap, will shoot
into the gravel layers of ash 2/3.
6.4 crack: bottom ash water saturation.
Sticky lime too thin ash layers too thick, sticky stones due to gravel dumped
ash layer when shattering crack drop pendant. Watering should be appropriate,
and to ensure the consistency of sticky lime.
6.5 empty drum cracked: there are two, one
is the bottom cracks with grass-roots; another is a layer of adhesive layer and
bottom ash between the cracks. Bottom ash and matrix cracks causes of substrate
to clean up dirty; water impermeable; ash layers too thick, plaster, no
layering effects. Bottom ash and adhesive layer cracks are mainly caused due to
cracking. To prevent cracks grey, a note to clean up, the other is the attention
to moderate watering, third, we must pay attention to the thickness of the ash
layer and the consistency of mortar. Strengthening the construction inspection
checks.
Section 6.6, drip grooves are not smooth,
faint: after the main article is uneven seams, according to construction
require careful caulking.
7 quality records
This standard shall meet the following
quality records:
7.1 raw materials factory certificate and
test report (sand, gravel).
7.2 cement reinterview report and factory
certified.
7.3 using adhesive material proof and
factory certificate.
7.4 quality inspection and assessment of
records.