1 scope
This technology is applicable to industrial
and civil construction in the clay, and silty clays containing small amounts of
sand, stone and clay layers, and underground water level low manual holing
pouring piles.
2 construction preparation
2.1 materials and equipment:
2.1.1 cement: No. 325, ~425 should be used,
ordinary Portland cement and slag Portland cement.
2.1.2 sand: sand or coarse sand, clay is
less than 5%.
2.1.3 stones: diameter of 0.5~3.2cm of
pebbles or gravel; the pile the stones in the concrete can also be used
particle size is not greater than 5cm, and clay content of not more than 2%.
2.1.4 water: tap water or clean water that
contains no harmful substances.
2.1.5 external accelerator experiments use
fly ash admixture shall be determined according to the laboratory.
2.1.6 steel: steel grade, diameter must
conform to the design requirements, certificate and retest report of the
factory.
2.1.7 General should has three wood take, and
hoist group or electric gourd, and trolleys or dump truck, and picks, and
spade, and hand shovel, and soldering, and line pendant, and set pulley group,
and oriented pulley group, and concrete mixer, and bucket, and chute, and
catheter, and vibration pound rod, and plug soldering, and rough rope, and wire
rope, and security activities cover Board, and waterproof lighting lamp (low
voltage 36V, and 100W), welding machine, and ventilation and the for oxygen
equipment, and head pump, and wood windlass, and activities ladder, and helmet,
and belt,.
2.1.8 template: combined steel formwork,
Arc tool steel mold four (or eight) assembled. Clamps, hooks and spare parts.
Wood, wood, 8th or 12th channel steel and so on.
2.2 operating conditions:
2.2.1 Manual excavating pile hole wall
support should be based on the characteristics of soil and groundwater in the
area of distribution of the preparation of the practical construction
programme, supporting calculation and design of shaft lining.
2.2.2 three connections and one leveling
the excavation site before. Aboveground and underground cables, pipelines, old
buildings, equipment and other obstacles have been excluded have been disposed.
The temporary facilities such as lighting, power, ventilation and safety
facilities in place.
2.2.3 familiar with construction drawings
and the site of the underground soil and hydrogeological data, be aware.
2.2.4 on the basic floor plan, set axis and
anchor pile; pile around the gray lines. Determination of elevation bench
marks. Line after the operation is finished, go through the preflight
procedures.
2.2.5 good design fabricated steel cage.
2.2.6 prior to full excavation and
selective test pile to dig two holes, analyzing soil, hydrologic and other
relevant circumstances, to modify the original knitted construction program.
2.2.7 in the area of the underground water
level is relatively high, lowering the underground water level below low 0.5M.
2.2.8 artificial digging hole is critical
to the security of the operation, excavation prior to construction personnel
conduct comprehensive safety technology gives the low-down; operation to secure
the spreader inspection and testing to ensure safety.
3 operational processes
3.1 process:
Line position and elevation → excavation
pile Earth → the first section against templates for additional steel →
Casting section retaining concrete → check
position (Center) → set up the axis vertical transport →
Installation of electric hoist (hoist or
wooden winches) → install bucket, lighting, event cover, water pump, fan →
Lifting section excavation pile of Earth
(trimming) → split the first savings section Dado template (attached steel) →
Section II of the water retaining concrete → check
position (Center) axis → cycle down layer by layer →
Excavation expanding bottom part hanging → check → on
reinforcing cage → concrete slip tube (catheter) →
Pouring concrete pile (with the cast with
vibration) → Insert pile head reinforcing bar →
3.2 line position and elevation: in sites
based on the three connections and one leveling according to building surveying
control network information and basic floor plans, determination of pile axial
and Gao Chengji permitted point of square control network. Decide on a Center,
the midpoint circle, with the radius of the pile and wall thickness as the
RADIUS to draw the upper (the first step) circumference. Lime Wire as
excavation of pile holes size line. Hole after the line set, must be reviewed
by the relevant departments, run the pre-screening procedures of excavation.
Section 3.3 excavation pile earth moving:
excavation pile layers from top to bottom, dig the middle part of the Earth,
and then spread in and around, effectively control the excavation hole size.
The height of each section should be based on soil quality is good or bad,
depending on the operating conditions, generally to 0.9~1.2m is appropriate.
3.4 Dado template bar: to prevent the pile
hole collapse to ensure safe construction, a hole should be well set, the two
kinds of plain concrete and reinforced concrete. With in-situ reinforced
concrete ring as well, and soil-wall seamless integration, stability and
overall performance are good, and even stress can be preferred. When the hole
diameter is small, relatively shallow soil and groundwater under low conditions
or Jet concrete wall. Wall thickness according to material, performance,
rigidity and stability, convenient operation, simple construction requirements,
and force, inherit the Earth section in the bottom of the side pressure and
lateral pressure of groundwater, determined by calculation.
Dado template removal section, under the
support section on turnover for the same purpose. Fixed template using clamps,
fasteners or at each node template to set the upper and lower ends of the arc,
made of steel or steel internal rims as a medial support, prevent tension and
deformation of memes. No level of support to facilitate the operation.
Higher wall to floor 150~200mm the first
section is appropriate, for retaining, watertight. Axis and elevation shall be
calibrated in the first quarter caused by the catchy, wall thickness and
generally the 100~150mm.
3.5 section retaining concrete pouring:
pile wall excavation of concrete each completed section immediately after
pouring the concrete. Artificial casting artificial tamp, concrete strength is
typically C20, slump-control in 100mm, ensure the stability of hole wall.
3.6 check the position (Center) and
elevation axes: pile wall after making each section, you must cross the axis
and elevation surveying in retaining the catchy, and then use the crosshairs,
wait for fall to bottom cast is set, with vertical RADIUS gauge Rod hole wall
smoothness. Followed by trimming depth must be according to the datum point,
measured one by one. Ensure pile hole axis position, elevation, section meets
the design requirements.
3.7 build vertical transportation: section
after Kong Chengkong, which began at pile head erect vertical transportation support.
Brackets: wooden, pipe hangers, wooden hangers, or I-beam rail bracket forms
called building stable, solid.
3.8 installation of electric hoist or
hoist: install in vertical transportation pulley and electric or worn hoist
wire rope, choose the appropriate location for installing the hoist. If piles
and small pile, you can also use wooden hangers, wooden wheel or human use
thick hemp rope as a promotion tool. Ground earth-moving trolleys or dump
truck.
3.9 installing buckets, lighting, event
cover, water pump and fan.
3.9.1 pulley and bucket when it is
installed, take care that the bucket coincides with the hole Center location,
intuitive control as a digging pile and the centerline of the wall formwork.
3.9.2 bottom lighting must use low voltage
power supply (36V, 100W), waterproof cover safety lamps. Arranged on the
surrounding fence.
3.9.3 when the depth is greater than 20m,
to the underground ventilation, air convection. Oxygen, if necessary, to
prevent harm of poisonous gases. When rotation operations, personnel closely
observe the pile on pile under the situation, respond to each other and prevent
the occurrence of safety accidents.
3.9.4 underground water when digging mud
with buckets out. Underground water is larger, bucket which could not meet the
drainage, dig in pile bottom sump, sink with elevation pump into the pump,
while precipitation excavation, determined according to the pumping of water
pump specifications. Class three day and night pumping water level remains
stable. Underground water level is high, should adopt measures to consolidate
the precipitation, further excavation.
3.9.5 pile installation horizontal
activities over safety cover, when the hole was dug, cover the safety cover
plate to prevent debris dropped one. Staff shall not be closer to the hole.
When lifting the soil, then open the safety cover.
Lifting section 3.10 excavation pile of
Earth (trimming), from the beginning of the second section, lifting equipment,
personnel should wear a helmet in the pile, ground crews tie belt. Bucket above
the left hole 1.5M, promoting event safety cover, mask hole to prevent
unloading of clods of soil, stones and other debris falling hole internal
damage people. Bucket in a small cart after removing the soil, and then open
the cover plate, lower buckets with soil.
After excavation of pile holes to the
required depth, using poles to check the diameter of the hole and shaft arc,
vertical up and down smoothly, finishing hole.
3.11 dismantled the first savings caused by
the template in section II, additional reinforcement, retaining savings in turn
used in the following section on the template removed. Aperture narrowed down,
should be equipped with a small block template to adjust. Template is 100mm
room at the upper concrete pouring and tamping compaction at the interface.
After stripping with concrete or masonry block, cement mortar trowel, stripping
strength 1MPa.
Section 3.12 pouring retaining concrete:
concrete barrels come pouring of artificial, artificial plug pound density.
Experimental determination by adding early-strength admixture for concrete, to
speed up the hardening of the concrete.
3.13 check the central axis and elevation:
to pile hole of the anchor line on the basis of the calibration section by
section.
3.14 down layer by layer cyclic operation
would pile hole dug to design depth, clear tilled soil, check the soil, pile
bottom force-bearing the design requirements for the bearing layer.
3.15 excavation expanding bottom: end of
piles can be divided into bottom-enlarged and does not spread at the end of
both. Dig pile expanding bottom pile in first cylinders dug, spread bottom of
sizes and shapes cut from top to bottom soil expansion into design drawings
requirements; no clear requirements such as design, bottom-enlarged diameter
for 1.5~3.0d. Spread bottom diameter is 1:4.
3.16 inspection and acceptance: the hole
must pile diameter, head size, expansion of hole-bottom elevation, pile the
Middle, perpendicular to the wall, Virtual Earth determine the full thickness.
Well construction record, for the covert acceptance procedures.
3.17 hanging steel cage: steel cage should
tie before in mortar for blocks, according to the design requirements for the
70mm (steel cage around every 3~4m or so in the main bar of a φ 20 earrings, as
the positioning pad); dipping steel cage, must aim at the hole, hanging
straight steady, slow down, avoid collision wall. Steel cage to design
position, should be fixed immediately. In case of two-stage connection of steel
cage should be used in welding (lap-welded or welded), both sides, joint by 50%
staggered to ensure that the bar is correctly positioned, the thickness meets
the requirements.
3.18 pouring concrete pile: pile the stones
in the concrete using particle size is not greater than 50mm, 80~100mm slump,
mechanical mixing. Chute plus barrel of pouring concrete into the pile.
Concrete difference is greater than 2m, pile hole depth exceeds 12m, the
pouring of concrete ducts should be used. Concrete should be continuous,
layered vibration compacting. Generally the first step should be poured to the
top of pedestal parts and upper concrete pouring. Lamination height to tamping
tool, but should not be larger than 1.5M.
3.19 when pouring concrete pile, due over
the pile design elevation, after the removal of laitance by guarantee, top
level meets the design requirements. On top of the pile of steel and iron must
be inserted to keep the design sizes, vertical insert, and there is sufficient
cover.
3.20 in winter and rain during
construction:
3.20.1 in winter when the temperature is
lower than 0 ℃ when pouring concrete, heating and insulation measures should be
taken. Pour into mould temperature should be determined by the winter
programme. Top of the pile is not to design strength 50% must not be frozen.
When summer temperatures above 30 degrees centigrade, retarding measures should
be taken according to the specific circumstances of concrete.
3.20.2 cannot do the work of manual hole
digging pile in the rain. Site must have drainage measures, to prevent ground
water into the pile, pile hole collapse.
4 quality criteria
4.1 project:
4.1.1 piles of raw material and concrete
provisions must comply with the design requirements and specifications.
4.1.2 the actual pouring of concrete, no
less than the calculated size.
4.1.3 top elevation of pouring concrete
pile and treatment of laitance must meet the requirements of specification for
design and construction.
4.2 Basic project:
4.2.1 the pile diameter should be strictly
controlled. Generally should not exceed a length of 3, and a maximum of 50mm.
4.2.2 virtual depth should not exceed the
end of hole. Belled shape and size to fit the design requirements, should be
vested in the bearing at pile bottom soil layer, bearing stratum of soil should
not be destroyed.
4.3 allowable deviation, as shown in table
2-9.
Poured pile by artificial hole tolerance
table 2-9
Project tolerance (mm) test method
1 steel cage reinforcement spacing ± 10 '
check
2 Stirrup spacing of reinforcement cage ±
20 foot check
3 steel cage diameter ± 10 ' check
4 length of steel cage ± 50 foot check
5 position the central axis ± 10 cable and
check
6 3 ‰ l vertical pile, and no more than 50
hanging and foot check
7 pile diameter ± 10 ' check
8 bottom elevation ± 10 ' check
9 wall thickness ± 20 feet of concrete
check
Note: • for length.
5 finished product protection
5.1 has been digging pile holes must be
boarded or scaffold, steel mesh cover to prevent the clods of soil, debris, people
fall. No grass bag, plastic sheeting behind.
5.2 has dug pile in time to put the steel
cage, pouring concrete in a timely manner, time interval shall not exceed 4H in
case of collapse. Groundwater pile hole should be dug, with check, with the
reinforcement cage, to keep the concrete-filled well, avoid water immersion.
5.3 pile outside the circle should be
retaining, prevention of water and soil.
5.4 protecting steel cage, not twisted,
loose shape. Into the hole, do not hit the hole wall. Barrel should be
vertically positioned to prevent the concrete wall thickness of oblique shock,
damage caused by the soil, resulting in clips.
5.5 reinforcing cage not contaminated by
slurry; when pouring concrete, at the top of the steel cage fixation and
limited reinforcement cage floating.
5.6 finished pouring concrete pile should
review pile and the pile height. Pile reinforcement or to insert iron fuzheng,
enclosed with plastic sheeting or straw, and prevention of concrete shrinkage
and cracking.
5.7 the axes properly protect the site
construction process, standard point. Not compacted head, bending steel bars.
6 quality problems to be noticed
6.1 vertical deviation is too large: as the
excavation procedure does not check the verticality of each section as
required, after finishing digging vertical overload and unbalanced. Each dug up
a section had to be lifted according to axis of the hole on the straight, edge
trimming, keeping the hole arc straight up and down.
6.2 hole wall collapse: poor quality of the
soil or groundwater seepage and the hole wall collapse. Field soil should be
mastered before excavation, stagger excavation of pile, shortened each section
height, observe the loosening of soil conditions at any time and, if necessary,
can collapse with bricks, steel sheet pile, wood pile plugging operation
process to compact, not space gaps and avoid collapse.
6.3-well tilled soil residues at the end of
too many after drilling, trimming more Virtual Earth, brick, is not hard to
clear. Steel cage should be carefully checked before and after the hole bottom,
clear tilled soil debris. When necessary, with cement mortar or concrete.
6.4-well water at the end of: when fast
seeping groundwater or rainwater, drainage, and water will appear. During
excavation of holes dug at the end of sump, pump pumping water in a timely
manner. If you have a small amount of water, pouring concrete in the first set
and a half dry and hard, a lot of water sometimes exclude difficult
circumstances, using catheter method of placing concrete under water to ensure
construction quality.
6.5 bad quality of pile concrete: neck,
empty, folder and so on. In front of the concrete must be ready to operate
technology gives the low-down, insisted on stratified pouring and vibrating,
continuous operation. Necessary auxiliary plug for iron pipes, bamboo poles,
steel drill pound, to supplement the lack of mechanical vibration.
6.6 distortion of steel cage: steel cage
processing spot when not in prison, is not supported for reinforcing,
transport, dipping time distortion, distortion. Machined steel cage should be
on a dedicated platform, main bars and hoops spot-strong reinforcement measures
to support reliable, lifted vertically so that it smoothly into a pile, keep
the skeleton intact.
7 quality records
This standard shall meet the following
quality records
7.1 cement factory certification and proof
of reinspection.
Factory certificate or certificate of 7.2
bars and rebar test single copies.
7.3 test pressure test records.
7.4 pile construction records.
7.5 test of concrete application form and
mix orders issued by the laboratory.
7.6 28D compressive strength of standard
curing concrete block test report.
7.7 floor map.
7.8 reinforced and pile covert acceptance
form.
No comments:
Post a Comment