Installation construction of bi-steel
Composite plate
1 scope
This technology is applicable to
multi-layer and high-rise multiple civil composite slabs or panel installation.
Conditions suitable for industrial construction we can use.
2 construction preparation
2.1 materials and equipment:
2.1.1 double reinforced composite slab:
thickness are divided into 50mm and 63mm series. Plane size with three-mode as
a benchmark, 50mm, long-4.2m~6.3M, wide l.5M~3.9m. total 72; 63mm, long
4.2m~7.2m, wide 1.5M~3.9m, total 99. Precast composite slab of laminated
surfaces should be smooth differential of not less than 4mm artificial surface,
the surface shall not be a porous layer and laitance. BI-steel Composite plate
to have a factory certificate.
2.1.2 support joints and rigid frame
formwork planks, wooden or shaped pillars should be prepared according to the
construction plan.
2.1.3 implement vertical transport
machinery, steel measuring tape, crowbar, etc.
2.2 operating conditions:
2.2.1 according to drawings,
specifications, laminated sheet set and negotiate requirements, draw laminated
slab installation diagram. Which should express laminated slab surface, models,
seam dimensions, bearing length of shelving, bearing hard frame formwork,
temporary support positions, to laminated slab installation.
2.2.2 checking laminated slabs of quality:
check for cracks and defects in detail, checking laminated slab surface
quality. If it does not meet the quality requirements may be used. And
according to the installation diagram checked laminated slab models and
specifications.
2.2.3 check elevations and the axis of the
wall or beam. Beam and ring beam reinforcement and templates through yin and
pre-screening.
2.2.4 laminated slabs stacked and site
requirements:
2.2.4.1 prior copy of the space should be
flat, solid, and built 3:7 lime in two steps.
2.2.4.2 stacking position with the lifting point.
Under each piece of laminated slabs close to the rings should be placed along
the laminated slab length to full length wood, align, alignment, pads, pad
real. Different panels should be stacked, piled up plates, overlapping is not
allowed. Stacking height should be no more than 6 floors. Conditions should be
allowed to go upstairs.
2.2.5 hard around the wall frame formwork
and butt joints stiff frame support and temporary support, according to the
construction plan has been installed, finished and pre-screening.
3 operational processes
3.1 process flow chart:
Check bearings and joints on the hard frame
formwork lifting draw laminated slab elevation → line → laminated
slabs →
Adjust supports composite slab using length
→ finishing laminated board throw bars
3.2 for use on composite slab bearing
length is smaller (or not support), it generally should be adopted hard around
the wall frame formwork, usually single row of pillars and walls locking,
spacing between 60~100cm. Wall or beam top elevation decrease l~3cm. Also
located at the seam of hard supporting, typically a double row of pillars,
spacing of 60~100cm. Installing laminated slabs should be carefully checked
before hard frame formwork supporting system, check the wall or beam axis of
the elevation, and rigid frame formwork level cord to the top level, and
calibration.
3.3 draw laminated slab lines: Heng Leng,
on the walls, beams or rigid frame on the side seam line of position by the
installation pictures, and mark Board. Butt joints between 100mm, such as plate
arrangement when needed may vary between 80mm~170mm. But larger than 100mm seam
should be placed close to one side of the plate boundary. As shown in Figure
4-39.
Board retained in Figure 4-39 diagram
3.4 laminated slab hoisting: laminated slab
reserved at the hole, before lifting to clarify its position, clear direction.
While checking, remove barriers to rebar in place. Hoisting rings should be
reserved position, taking eight rings of synchronous lift. But, should make
stacks of plywood as delineated in the alignment plate line, design support
using slower annual drop in place, stable implementation.
3.5 adjust the use of laminated slabs
bearing length:
3.5.1 in crowbar by supports of drawings
using length, gently adjusted. If necessary, to help tighten the hook of the
crane ropes (but does not support), supplemented by manual lever adjust the
length using together.
3.5.2 drawings no requirements on the
bearing length of shelving, when the Board sits on your concrete, usually +20mm
(that is 20mm into the bearing). If row plate needs may also change between the
+30mm~-50mm. But if the wall thickness is less than 160mm, the cylinder
boundary length used should be >0. Must be less than -50mm should be dumped
as designed to increase muscle length. Use a length of status as shown in
Figure 4-40.
3.5.3 in brick-concrete structure in the
plate into the bearing length should be greater than 50mm.
3.6 Summary of design rules, finishing
four-week thrown out of reinforced composite slab shall not be bent 90 °, shall
not be under the pressure plate.
4 quality criteria
Figure 4-40
4.1 project:
4.1.1 components when lifting the concrete
strength must comply with the design requirements and the provisions of the
code.
Examination methods: examination components
factory and the test of sample cured in same condition report.
4.1.2 concrete composite slab joints must
be accurate measurement, concrete compaction, curing full, which provisions
must meet the design requirements or specifications.
Inspection method: observation and
inspection standard curing period 28D block compression test reports and
construction records.
4.1.3 laminated slab type, location, point
anchoring must comply with the design requirements and has no damage.
Inspection method: observation or standard
checks and inspection lifting records.
4.2 Basic project:
Laminated slab elevation, plasma, plate
width, should comply with the design requirements and the provisions of the
code.
Inspection method: observation, adequate
checks.
4.3 allowable deviation, as shown in table
4-37.
Table 4-37
Project tolerance (mm) method
1 axis displacement 5 foot check
2-storey ± 10 level or standard of
inspection
3 Board shelving ± 10 feet in length check
Plaster 5
Don't plaster 3
5 finished product protection
5.1 laminated slab pile up and pile site
requirements should be strictly in accordance with 2.2.4 implementation.
5.2 when installing laminated slab cast
walls, beams, its construction of concrete strength to achieve 4MPa.
5.3 laminated slab on the left bar
(anchorage bars) in the course of stacking, transporting, lifting to be
protected may not be repeatedly bent and broken.
5.4 hoisting laminated slabs should not be
used "reveals", more block lifted. Should be reserved for the rings,
synchronous single lifting with eight points. May not impact laminated slab
lifting.
5.5 hard frame formwork supporting system
of temporary support should be complete before hoisting. Each Panel in width
along the long to take additional full-length muleng as temporary support. Next
end all pillars should be pave the way through long hand, and under the
scaffold-based soil, levelling, compacting.
5.6 non-arbitrary cut holes in the plate,
plate holes if required, mechanical drilling and reinforcement design and
collection requirements accordingly.
6 quality problems to be noticed
6.1 overcome plate deflection and crack:
rigid frame formwork and seam to support its epithelial elevation must be
accurate and must have adequate stiffness, strength and stability, to ensure it
is not sinking, not tilted.
6.2 overcoming plate bearing shelve length
allowed, hoisting should be carefully adjusted.
6.3 failed boards shall not be lifted in
place to check before lifting. Especially the artificial surface of composite
slab should meet the requirements, loose layers and laitance should be cleaned
to ensure concrete laminated surface well.
7 quality records
The standard quality shall have the
following records:
7.1 concrete factory certificate.
7.2 structure lifting records.
7.3 precast hoisting pre-screening.
7.4 Sub-item project technology gives the
low-down.
7.5 quality inspection and assessment of
the project.
Because of the war, many people become homeless. I can't do it well. Please help me.my PayPal is xhhnet@163.com.
No comments:
Post a Comment