Wednesday, September 28, 2016

Cast in place structures (formwork) construction technique of lightweight aggregate concrete

Cast in place structures (formwork) construction of lightweight aggregate concrete
1 scope
This technology is applicable to on-site mixing of ceramic, light pumice aggregate, sand the whole cast of lightweight aggregate concrete formwork.
2 construction preparation
2.1 materials and equipment:
2.1.1 lightweight aggregate:
Pumice: maximum size should not be larger than 20mm, do not allow more than the maximum size of twice times more particles. Grading requirements for 5mm mesh not greater than 90%, through the 10MM mesh 30%~70%; 200mm mesh not greater than 10%. Void fraction is less than 50%, 1h water absorption ratio is not greater than 25%, clay is less than 2%, loose bulk density, cylinder compressive strength in accordance with the design requirements.
Ceramic: the requirements are the same as above, and shall not be mixed or inclusions of clay blocks.
2.1.2 sand: sand or coarse sand sediment when the concrete strength grade of C10~C30, and no greater than 5%, when concrete strength is greater than, the C30 is not greater than 3%.
2.1.3 cement: No. 325, No. 425 Portland slag cement or Portland cement.
2.1.4 additive: product quality certification, dosage must be determined through laboratory and technical performance in line with the relevant provisions of the standards.
2.1.5 major equipment: mixer, skip, carts, scales, inserted vibrator, shovel, tiepan, wood float, small shovels, small spoons, buckets, rubber pipes, additive metering containers.
2.2 operating conditions:
2.2.l raw materials including cement, lightweight aggregates, admixtures comes into play, such as checking the factory certificate, its technical performance indicators must comply with the requirements, and retesting should be lightweight, 2003 (less than 200m3), must be tested: loose bulk density, particle size distribution, cylinder compressive strength, 1h water absorption. Natural light weight aggregate testing sediment, reinspection is not qualified, the reasons should be identified and measures taken.
2.2.2 laboratory test to determine the distribution ratio and the slump. The strength of lightweight aggregate concrete density shall meet the design requirements.
2.2.3 light aggregate pile site drainage measures, try to keep particles when using mixed evenly, avoid small particles separated by natural graded when stacked, its height should not be more than 2m, to prevent leaves, mixed with earth or other harmful substances.
2.2.4 template seam should be tight if when using shoe trees, watering must be moist. Formwork for exterior wall outer swallow ring beam spot measures should be taken to prevent leakage.
2.2.5 familiar with the drawings of the design before construction requirements, technical clarification.
3 operational processes
3.1 process
Job preparation materials measurement mixing transport construction vibration maintenance

3.2 material measurement: aggregate, and cement, and water and plus agent are by weight meter, aggregate measurement allows deviation should is less than ± 3%, cement, and water and plus agent measurement allows deviation should is less than ± 2%, light aggregate should be in mixing Qian pre wet, so according to tie than determine water Shi, also must calculation aggregate of moisture (mixing Qian should determination aggregate containing water rate), do corresponding of adjustment, in mixing process in the should often began assessing, rainy day or slump exception should timely determination containing water rate, adjustment water. W/c total available water/cement ratio, the total water consumption should include a mix of effective water demand and water absorption of light weight aggregate LH in two parts.
3.3 mixing:
3.3.1 charging sequence: using down mixer with 1/2 water. Then add the coarse and fine aggregates and cement mixing 1min, then add the remaining water and continue stirring at least 2min. Compulsory mixer, first add fine cement and aggregate, coarse aggregate, mixing 1min add water stir not less than 2min.
3.3.2 the mixing time should be slightly longer than the ordinary concrete, the mixing time is about 3min. In the mixing process of lightweight aggregate concrete and lightweight aggregate absorb water, it should be treated with the slump in the construction of concrete values to control water consumption, and control the water/cement ratio, so that more relevant year is easy to master.
3.4 transport: lightweight water-absorbing ability at an early stage is very strong, so should be as short as possible in the construction of concrete mixers were exported to job placement, this process of time, generally not more than 45min. Wish to skip directly to the mixer outlet hanging to job placement, to avoid or reduce the Middle out of luck, if it leads to mixture of poor and vulnerable, the slump goes, suitable artificial two-stage mixing before pouring.
3.5 pouring: should continuous construction, not left or less left construction sewing, pouring concrete should layered for, on big template engineering, each layer pouring height first layer not should over 50cm, yihou each not over LM, if left construction sewing should vertical left in both inside and outside wall handover at and the water paragraph boundaries at, set wire network or blocking head template, continues to construction Qian, must will joint at cleanup clean, watering wet, then again pouring concrete.
3.6 vibration: light weight aggregate density light, easily causing the mortar to sink, lightweight aggregate float. Quick vibrating needle insert slow pulling, vibration points to appropriate encryption, distribution, its vibrating spacing spacing is less than normal concrete, should not be greater than 1 time times the radius of the vibration, insertion depth should not exceed the construction height. Time should not be too long, preventing layered segregation. Tools for concrete surfaces will be exposed in lightweight aggregate in mortar, and then use wood trowel the surface smooth.
3.7 conservation: the stripping strength of lightweight aggregate concrete under normal temperature should be greater than 1MPa. Water conservation or covered film in time after stripping moisture conservation, prevent shrinkage cracks in the water. Complete casting formwork when the exterior wall shelf bracket, wall strength control of concrete not less than 7.5MPa, safety requirements for ensuring shelf bracket.
3.8 in winter: winter programme implementation.
3.8.1 shall not use aggregates with ice and freezing.
3.8.2 transport container for concrete insulation measures.
3.8.3 winter period light aggregate impossible watering pre wet, dang using natural dried state of light aggregate Shi, should adjustment slump control value, General take 12~14cm, than at room temperature Xia increases 4~6cm, concrete out tank Hou by transport to pouring locations about fell to 8~10cm, can guarantee get can vibration pound dense of concrete, and can control concrete not due to plastic had big, occurred rough aggregate floating, and caused segregation phenomenon.
3.8.4 mixing pumice concrete can be used on the secondary material, method of two-stage mixing. First floating on stones, admixtures (fly ash) mixing of water and 1/3 1min, the second is expected to be on cement, sand, additives and stir the rest of the water to join to improve the workability of the concrete, and avoid holes absorb pumice admixtures.
3.8.5 template removed and the walls hung when the tripod, the strength of concrete conditions block needs to be done. Intensity control 4MPa and 7.5MPa, respectively. Ensure mixing of antifreeze concrete the frozen critical strength and hang tripod safe.
4 quality criteria
4.1 project:
4.1.1 use of lightweight aggregate concrete cement, aggregates, admixtures, mixing ratio, measuring, mixing, conservation and treatment of construction joints, must conform to the specifications and requirements of the relevant standards, check the factory certificate, the test report.
4.2.2 strength of lightweight aggregate concrete in accordance with design and evaluation standard of inspection requirements, and density meet the design requirements.
4.2 Basic project:
Vibrating compaction, surface, honeycomb, Matt surface, does not reveal tendons, joints and no holes slag layer.
4.3 allowable deviation, as shown in table 4-33.
Table 4-33
Tolerance (mm)
Multi-layer high
1 axis displacement 8 5 foot check
Storey ± 10 ± 10
Full height ± 30 ± 30
3 section dimensions +5-2 + 5-2 ' check
Check every 5, 5 2m supporting plate
Overall height of 1 and 20 1 and 30 using a theodolite or hanging and foot check
5 smooth 4 4 2m m on foot and wedged feeler Gage check
Center line of embedded steel plate of 6 and 10 10
7 embedded pipe, reserved holes, embedded bolt centerline offset 5 5
8 is hole centerline offset 15 15

5 finished product protection
5.1 when pouring and vibration protection of good holes, embedded and embedded pipes, boxes of water, electricity and so on.
5.2 enter lightweight aggregate to take good care of to prevent crushing and mixed with debris.
5.3 concrete pouring and tamping and finished to keep the exposed reinforcement position correctly.
6 quality problems to be noticed
6.1 concrete slump and instability: water master no, changes in the moisture content of lightweight aggregate, determination of adjustments in a timely manner at the end of water.
6.2 poor and vulnerable: insufficient mixing time, the material too quickly.
6.3 surface light aggregate exposure: concrete vibrating when the accept header, seeking and vibration on the surface, has yet to carry out pressure and smooth.
6.4 low strength: measurement is not accurate, vibration is not dense, poor conservation.
6.5 Cha imperfect: the outer wall beam Cha shall be no leakage, pay attention to the vibration density.
7 quality records
This standard shall meet the following quality records:
7.1 materials (cement, sand, lightweight aggregates, admixtures, etc)-factory certificates, test reports.
7.2 test report, strength evaluation for lightweight aggregate concrete block.
7.3 concrete construction records.
7.4 project for quality inspection and assessment.
7.5 hidden inspection, inspection records.
Winter construction of 7.6 recorded.
7.7 design changes, record of negotiation.

7.8 other technical documents.