Precast reinforced concrete frame structure
components are installed
1 scope
This technology is applicable to general
industry and civil construction of multistory frame of precast beams, columns,
slabs of concrete components are installed.
2 construction preparation
2.1 materials and equipment:
2.1.1 widget: precast reinforced concrete
elements, such as beams, columns, slabs, is given a factory certificate.
Component specifications, models, embedded parts location and quantity,
appearance and so on, should comply with the design requirements and the
standard for quality inspection and assessment of prefabricated concrete member
(GBJ321-90) of the.
2.1.2 steel bar and steel: size, shape, the
drawing requirements and should be steel factory certificate.
2.1.3 cement: No. 425, should be adopted,
No. 525 ordinary Portland cement. Seams in the column should be used, No. 525
expansive cement, or at least No. 525 ordinary Portland cement. Should not be
adopting slag cement or Pozzolanic cement.
2.1.4 stone: size 5~32mm. , Sediment is
less than 2%.
2.1.5 sand: sand or coarse sand, clay is
less than 5%.
2.1.6 electrode must be according to the
design requirements and welding is the process of selection of the relevant
provisions. Packaging order, no rust no tides, certificates and instructions
for use.
2.1.7 template: according to structural
requirements and specifications needed to prepare complete, brush release
agents. 100mmx100mm,100mmx50mm wood as well. 50mm plank.
2.1.8 main machinery: lifting machinery,
welding machines and related equipment, welding rod drying boxes, wire ropes,
rings, baskets of correctors, post lock clamps, slip line, supports, hooks,
theodolite, level, leveling rod, foot boards, iron pole, Jack, chains and
crowbars. Tools and so on.
2.2 operating conditions:
2.2.1 familiar drawings: drawings,
especially structure diagrams, component fabrication, joint construction detail
drawing, related to the Atlas should thoroughly understand and be familiar
with. Carefully grasp the component model, quantity, weight, joint practice,
construction operations, safety technologies, Spider-man-related provisions and
the interaction between components.
2.2.2 preparation method: according to the
structural characteristics of the building and construction process, based on
the actual conditions, the fabric carefully lifting plan. Safety, quality and
construction personnel, technology gives the low-down.
2.2.3 main components for pre-screening:
based on the structure construction drawing and component processing,
verification entry type, quantity, specification of components, concrete
strength, embedded reinforcing iron, reserved position, number of conformance
to design drawings, whether the component factory certificate.
2.2.4 line: the embedded parts and exposed
on the reinforcement of cement paste and clean of rust and other debris
management. On the members to play axis (centerline) is to say, the positioning
line, indicate directions, axes and elevations. Axis of the columns should be
playing on three sides. Axis post, first floor in addition to playing out, and
mark 0.00mm horizontal lines on three sides. Embedded cross centre line of
play. Play at both ends of the beam axis, axis control of positioning.
2.2.5 control floor installation elevation:
the component connection anchoring the structure after construction, good floor
column grid axial and elevation control lines, good post connection of
superimposed layers, embedded positioning and leveling plates and calibrate
their elevation. Floor column grid axis as clear and accurate.
2.2.6 adjust upper part of composite beams
with exposed steel bars, welded at the ends of the main bars straighten buried
along, check the connecting parts according to design requirements, length,
location main bar. In the case does not affect the normal installation, upper part
of the basket of flowers Leung of beam main bars fastened, head positioning
embedded parts can also be welded composite beams of steel, but must ensure
that their elevation, location accuracy.
2.2.7 in accordance with selected
construction organization design of hoisting machinery comes into play, and the
commissioning of identification in accordance with safety procedures ready for
lifting appliances, lifting shall be put into operation.
2.2.8 erection of scaffolding, safety
protection: in accordance with the provisions of the construction organization
design in the lifting job putting up lifting scaffolding and platforms, and
security guards. And associated personnel inspection, inspection,
certification, compliance with safety regulations, to be fully operational. No
security and safety measures, shall not carry out the job.
2.2.9 the floors need of beams and columns,
Board member of plane position close to flat. To prevent post flip when
lifting, little stigma lifting touchdown crack or bend reinforcement, security
leg can be used, or the addition of wood column end reinforcement to prevent
bending deformation of main bars for lifting.
2.2.10 welder certificate and designation,
official before brazing welding trials will be required to adjust the welding
parameters, providing simulated weld and qualified through test and operation.
3 operational processes
3.1 process:
Column lifting (correction, positioning → welding) → girder
lifting (correction, reinforcement welding) → beam-column joint
core →
Shear wall construction → installed
3.2 pillars lifting:
3.2.1 structure hoisting hoisting in the
order provided, generally along the longitudinal axis push, segmented flow
layer by layer, each floor from end to started to reduce repetitive task when a
transverse axis of the column after the installation is complete, and then hung
the next post on the horizontal axis.
3.2.2 clean up post mounting area of
debris, loose concrete and high position of embedded steel plates bonded clean,
check the columns axis, position location, elevation, and anchorage and meet
the design requirements.
3.2.3 hanging main bar up and down to check
out the posts, according to the designed length will exceed the part cut off,
ensure that the positioning of small pillars head steadily and is located in
the joint position on the plate. Will lower out of the main bars straighten,
smooth, and pledge to lower pillars reinforced overlap Nestled close, easy to
weld.
3.2.4 pillars lifting: pillars hanging
points location and hanging points number by pillars length, and section shape
decided, General selection are buckle lashing, hanging points selected in from
column top 600mm at card good special of column Hoop, in column hoop below lock
good clasp wire rope, lifting mechanical of hook rope and clasp phase hook
district with clasp card live, hanging rope should in hanging points of are
above. Slow lifting, tense pause after lifting rope up, check the reliability
of automatic clasp in a timely manner to prevent tripping on their own, to
control the lift in place without swinging back and forth, in the lower part of
the column hung well slip rope, check all connections, right before the lift.
3.2.5 pillars in place: when post lifted
from the 500mm pause, remove the protective pillar reinforcement of wood and
leg, clear the stigma in mud, and then by the signalman command, column lifted
onto a floor in place. In place, slowly over the landing to the installation
location, stop, check the post number, adjust the direction, controlled by the
two make small stigma full range line is correct, before falling on to the
installation location. Post check-check the shear wall inserted iron (steel),
completion of directional seat, sided with hanging flower baskets bolted,
oblique cord, additional temporary support fixed to ensure safety.
3.2.6 correction and positioning:
3.2.6.1 column vertical correction: hanging
plates, and set up in the two mutually perpendicular directions Theodolites,
vertical axis aligned with the installation location grid on the column axis,
vertically. Corrects the time to find a two axis axis of the surface, then
align on the third axis of the last pillar axis alignment in the middle or on
the three axes. Pillars were in place well, careful theodolite calibration axis
and vertical, confirm that does not exceed the deviations, stigmas positioning
plate welding can be carried out.
3.2.6.2 column (pillar) installation
calibration and orientation: the column centerline shall prevail, in place
after four supports. Using two Theodolites are adjacent on the cylinder axis,
at the pillar axis, vertical deviation correction. Observe the correct column
axis, full height from bottom to top through. When two Theodolites calibration
from two directions after a good, then check the other two axis of the plane,
surrounded by supporting strong, small pillar steel plate and welded steel
plate fixed on the head, and then welded reinforcement, the second correction.
3.2.6.3 side columns, corner post
installation, calibration and location: edge, corner post installation wood
only on the 2~3 from the floor taut basket correction correction. Except when
installing the corner post after correction for three-axis positioning, and
check on the fourth axis on the surface, ensure that the upper and lower pillar
does not produce twisted, dislocation and migration at the nodes.
3.2.7 indispensable prior to positioning
the main bar and the stigma, spot-fix to prevent support in prison, tighten
TURNBUCKLE tie in with each other without coordination, resulting in posts to
tip over.
3.2.8 adjust main bars, welding: during the
lifting process is reinforced by collision in welded reinforcement before
straightening and smoothing, so upper and lower reinforcement is correctly
positioned, close to each other, easy to weld. When used for welding, steel
bars should be used has the same gluten level when using lap welding, should
meet the requirements of lap length, consists of two double-sided welds. Two
welding machines for welding required, diagonal, symmetric, and so speed up the
arc, ARC basic synchronization. The intermittent welding, to prevent thermal
effects lead to uneven stress, excessive deformation are generated to avoid
burns and reinforcement of concrete. Positioning small stigmas surrounding
welding of steel plates on all sides. Welding post. Quality meets the
specification for welding requirements, complete construction record,
indicating the welder code. Pillar reinforcement after finishing welding, weld
cooling in order to withdraw support. Review correction: theodolite review the
verticality of column and line, controlled within tolerance range, found ultra
deviations available chain for correction, may not be hit with a sledgehammer,
pry hard, hard to pry, damaged main bar.
3.3 girder lifting:
3.3.1 the sling in place: in the programme
provides for the construction of the installation order the relevant type,
specifications of the beams supporting code, playing well at both ends of the
axis (or the middle), straightening and straightening out the ends out of the
bar. Hanging out in the Bay of pillars, beams for the crane main beam and then hung
the first time, between the floors.
3.3.1.1 lift: in accordance with drawing on
the provision or construction schemes identified in the hang point location,
hook and rope lock. Pay attention to the angle between the slings must not be
less than 45 degrees. If using the lifting rings, you must tie safety lines.
When using the fallback when lifting, have to CLASP one prison. After hanging
the hook-and-line upgrade slowly, tighten the hook-and-line, 500mm stop rise
off the ground, carefully check spreader firmly tied hung safe and reliable, to
be lifted into place. Lifting AWB or local pick side beams, to give serious
consideration to its center of gravity, avoid eccentric to prevent tilting.
Lifting point should be as close as possible to the rings or beam end position.
3.3.1.2 in place: check again before
lifting the stigma pivot steel pad elevations, location meets the installation
requirements, in place looking for good on the stigma of axis positioning and
relationship between the beam axis, so that the beam is seated correctly. The
pillars at both ends of the beam in prison.
3.3.2 beam correction and reinforcement
welding: in place after a solid, elevation, position of the beam to make
corrections. Finishing steel and corresponding Liang Tou main bar after you
close to each other, for welding. In order to control the displacement of the
beam, end of center line of both ends of the beam should be aligned with the
top of the pole and line, and if the error is small, crowbars available minor
chord so that it sharply when the error is large, don't pry roots hard to pry,
or otherwise affect the pillars vertical changes. Beam should be lifted again,
slightly off the base steady operation by officers from both ends, Visual
alignment axis left hook to a smooth, slow seating and top end of the beam axis
alignment axis. Vertical beam deviation correction is a wire pendant hanging
from both ends, and standard deviation, and beam floor mats with crowbars, iron
pad smooth tight, until the ends of the vertical deviation control within the
allowed range, note in the entire calibration process, must also be observed
with a theodolite vertical pillars have no change. Installation to make the
post as a result of beam the vertical deviation exceeds allowed value must be
adjusted. When the beam elevation and position correction right, top firm,
weld, weld quality shall conform to the requirements.
3.4 core area of beam-column joints:
3.4.1 the practice of core area of beam and
column in line with design drawings and building Atlas of seismic requirements.
Prefabricated welded closed Stirrup stirrup, Stirrup spacing throughout the
encrypted area, diameter, quantity, 135 ° hook, straight part length shall meet
the requirements of specification for design and construction. In composite
beam of iron part should be set 1 φ 12 welding on closed position Hoop, used to
control the correct position of column main bars and joints.
3.4.2 edge, corner, capped columns node:
Liang Hezhu main bar anchorage length and lap welds, design drawings,
specifications and code requirements must be met. Top floor Corner column joint
beam on the steel removed and rebar lap welding of beams in addition to
remaining top reinforced with embedded anchor bar on welding in prison. Top
anchorage reinforcement angles welded in prison.
3.4. the 3-node strength than concrete
strength class of concrete should be level to 10MPa. Seams with dry concrete
column joints (lighter than concrete face stiff bean), preferably by pouring
cement, cement at 0.3 and increase its strength than the concrete strength
10MPa. Seams seams clean before using hemp ropes, sacks water fully wet;
two-side template block. Both symmetrical side chisel action, with twist-filled
reality. Construction finished maintenance 7d, to prevent shrinkage cracks.
Prior to the installation of upper structure, columns should be joint
construction is completed.
Joints can also be pouring UEA
shrinkage-compensating concrete, its strength than concrete strength grade
should also improve 10MPa, design of mix proportion and pouring method, with
the consent of the Department.
3.5 installation (floor or roof): rigid
frame formwork can be used directly or in-place method.
3.5.1 position of line: on the side beams
according to the design drawings drawn panels and Panel seam line, indicating
the type of plate.
3.5.2 Board in place: clean up the beam or
wall epithelial, check level, review the axis. The required hoisting. On board
the Setup begins on installation technology of prestressed concrete hollow
plate standard.
3.6 shear wall construction: on the floor
after installation is complete all the beams, columns, slabs, interspersed
within the hollow beams with vertical reinforcement, and insert the horizontal
ribs and pillars embedded in iron (steel) welding in prison. Connector
locations should comply with the provisions of the code. The construction
organization design requires a good template, vibration compacting of concrete
poured, and strengthen conservation.
4 quality criteria
4.1 project:
4.1.1 hoisting structure concrete strength,
lower internal forces of structures subjected to joint (joint) strength of
concrete or mortar must comply with the specification for design and
construction requirements. Check the component factory certification and the
test of sample cured in same condition report.
4.1.2 component anchoring must comply with
the design requirements and no damage. Observed or standard checks and
inspection lifting records.
4.1.3 joints (joints) of the concrete
(mortar) must be measured accurately, pouring dense, careful conservation,
which must meet the design requirements or provisions of the code. Visual check
and 28D sample test report and check construction records.
4.2 Basic project:
4.2.1 beams, columns, slabs in place
anchorage: axis position, elevation, pulp and node construction practices, end
plug holes, Board-end anchor, Board width, should comply with the design
requirements.
4.2.2 joints welding practices should comply
with the design requirements and the provisions of the code. Component main
bars and plates are connected with the weld length, width, thickness, and shall
meet the requirements of specification for design and construction. Weld
surfacing, soldering wave uniform, no dents, welding tumor and burns, joint
crack and blowhole, slag and the undercut. Clean welding slag, covering and
spatter.
4.3 allowable deviation, as shown in table
4-39.
5 finished product protection
5.1 axis to maintain through the floor of
the column grid, clear installation node level to indicate that need to be
addressed should be clearly marked, and not any apply, change, and pollution.
5.2 installation locating buried parts of
the beams and columns to ensure accurate elevation cannot be reached, any move,
hit and shift.
Prefabricated frame components installation
tolerances and inspection methods table 4-39
Project tolerance (mm) method
1 column centerline axis positioning
position offset 5-foot check
2-column interface up and down center line
position offset 3 foot check
3 5M in column 5
>5M vertical 4 column column-10 using a
theodolite or hanging and foot check
5 >10m column 1 ‰ high and <20
6 5M +0,-5 level or standard of inspection
7 >5m +0,-8
5 foot 8 axis displacement deviation check
9-storey ± 0 level or standard of
inspection
10 Board shelving ± 10 feet in length check
Plastering at 5 feet and feeler gauges
check
Don't plaster 3
12 center line axis positioning wire 5 foot
check
13 +0,-5 surface of the beam elevation
level or wait and check
14 vertical deviation of 3 hanging and foot
check
15 stairs, offset 10 feet of horizontal
displacement check
16 terrace elevation ± 5 with the level,
standard checking
5.3 the reinforcement may not be crooked,
bent at the nodes, removal of rust and dirty in the process not knocked down. Φ
12 before the pouring of concrete steel welding into closed position hoop
fixed-column main reinforcement position. Node encrypted area hoop welded
closed, the amount in line with design and seismic provisions of the Atlas,
binding firm.
5.4 Installing the beams, columns, plates
shall be arbitrarily bracing and tie rod removal, all cooling needs to be
welded reinforcement rear detachable calibration facilities. When installing a
beam, shall at all times observe the verticality of column changes, offset
should be stopped or remedied.
5.5 members while in transport and
stacking, wood mat location shall conform to the provisions, generally close to
the rings, the pad thickness should be above the ring, and wood into a straight
line up and down. Preventing cushion unreasonable, cause damage to the
components. Piling yard should be smooth, solid, not water. 100mmx100mm timber
at the bottom or double feet smooth hand pad. Each duo construction
organization design provides a high degree of code should be neatly stacked.
5.6 when the pipeline is installed, shall
be arbitrarily picking cut component. Construction shall be arbitrarily cut
rebar or bend to bend in damaged products.
6 quality problems to be noticed
Defects 6.1 component: the component model,
specification error. Component factory has yet to achieve the required
strength, causing breakage or damage. During transport and installation, check
the component quality, the strength of concrete. Using the correct methods of
handling and transport. Damaged or defective component without technical
department identification, may be used.
Displacement deviation 6.2 component:
component models and parts should be marked before installation, check wire
size were installed to prevent setting errors caused by component offset.
Different climate change adjustment of measuring error. When serious and
responsible, careful correction. Component location, elevation, vertical, met
the requirements.
6.3 above and below the axis does not
correspond to any affected components are installed: construction on line, top
of the line should be from the bottom up, using theodolite vertical, axis of
the determination of the correct floor. Guarantee perfect match between the
upper and the lower axis.
6.4 node concrete pouring is not compact:
node template does not run pulp. Node template should be sewn block before
pouring. Denser core reinforcement, pouring should be careful when vibrated.
Has a good workability of concrete and genuine slump. Template to leave a clean
out, carefully cleaning to avoid inclusions.
6.5 displacement of main bars:
reinforcement displacement nodes lower pillars, causing difficulties to lap
welding. Because components production without taking measures to control where
the main bar; component reinforcement caused deformation in the process of
transportation and installation. Therefore measures should be taken when
production, guarantees the proper beam main reinforcement position, lifting the
collision avoidance, before installing straightened out.
6.6 the core structure does not meet the
requirements: because the core steel more, so when should seriously look at the
pictures, according to the joint requirements. Steel connection position
accurately, lapping each other close, easy to weld. Stirrups quantity shall
conform to the drawings.
6.7 floor high: mainly the lifting process
of elevation control is lax, drove up installation elevation. Starting from the
first floor, measuring actual relative elevation of plinth epithelium, find the
right column bottom screed's elevation. When you install the floor pillars, to
adjust the locating plate to control the floor elevation above sea level,
positioning plate leveling application level, according to the post's actual
situation, set by column positioning plate negative deviation. Negative
deviation to 3~5mm, available steel plate adjustment.
6.8 column are skewed: the cause is poor
welding methods. Improvement is the joint of beam and column with two or more
than two welding points, conveying welding method should be used. Hard to pry
bars are not allowed in the welding process, welding of reinforcement in the
process of using the theodolite to observe a vertical deviation, find the
problem corrected.
6.9 pillars displacement: stigma in place
only in accordance with small cross line in place, rather than controlled axis
on the pillar; reinforcement welding, thermal deformation effects distort, led
to post them.
6.10 pillars vertical overload and
unbalanced, pillar is not straight: when installing, in the adjacent of two
surfaces that are perpendicular to the fall line of correction. After column
connection on the steel sheet spot welding, pillars and corrector for the
second correction. Main bar with symmetrical, such as speed, intermittent
welding. Arrange the welding sequence from Plum point should be applied as a
whole to stagger the framework welding method to prevent the welding process,
effects of stress, avoid frames have varying degrees of deformation.
6.11 quality does not meet the
requirements, should be strictly observed welding procedures.
7 quality records
This standard should have the quality
records
7.1 component factory certificate.
7.2-steel factory certificate.
7.3 steel factory certificate and retest
report of mechanical performance.
7.4 certificate of welding electrode
factory.
7.5 welding operation certificate.
7.6 test report.
7.7 cement factory certificate and retest
report.
7.8 test reports for sand and stone.
7.9 structure hoisting records (pre
inspection records).
7.10 reports 28D strength of concrete
block.
7.11 components install section for quality
inspection and assessment records.
Because of the war, many people become homeless. I can't do it well. Please help me.my PayPal is xhhnet@163.com.
No comments:
Post a Comment