Thursday, September 29, 2016

nstallation technology of prestressed cross plate with a circular hole

Pre installed short to the plate with a circular hole
1 scope
This technology is applicable outside the brick and concrete structure, brick mold, plate mode, frame structure prestressed concrete hollow plate (long and short).
2 construction preparation
2.1 materials and equipment:
2.1.1 prestressed plate with a circular hole: there should be no cracks, warping, and other defects. Product should comply with the quality requirements, should have a factory certificate. Country license components, products should be required to have the license number.
2.1.2 cement: the label over No. 325 of slag Portland cement and ordinary Portland cement and Portland cement. Cement factory certificate, required for the second interview.
2.1.3 sand: sand.
2.1.4 tools: steel Board, pry, casing, pipe supports, 100mmx100mm wood pillars, tools, hard frame formwork fixture, and so on.
2.2 operating conditions
2.2.1 plate with a circular hole into stacked in a specified place, piling yard should be flat and solid, 300mm wood close to the rings or distance plate, align the wood, there shall be no corner slabs, stacking height of no more than 10 blocks. Different panels, piled up.
2.2.2 floors before installation according to the design drawings, check, and check the quality of the plate with a circular hole, deformation, breakage, damages shall not be used.
2.2.3 extreme hole, by Han 50mm before they go out M2.5 mortar Grouting. Installing the front should check whether well plugging. Mortar from the extreme distance to 60mm. Pre-short end anchor plate with a circular hole plate stiffened (bearded wheat), casing should be straightened out, bent 45 ° bend, bend not into a dog leg to prevent faults.
2.2.4 component if there is damage, but through the reinforcement of fair use, and design joint research on reinforcing measures and changes after negotiated procedures only allow installation.
3 operational processes
3.1 process:
Screed or hard Board frame formwork line lifting floor adjust tying or welding anchor bar

3.2 screed or rigid frame formwork: plate with a circular hole before installation clean the top of the wall or beam, checking the elevation and axis dimensions, according to the design requirements of cement mortar screeds, thickness for 1.5~20mm, with the ratio of 1:3. In the in-situ concrete wall mounting plate with a circular hole, General wall concrete strength reached more than 4MPa, installed. Installation plate with a circular hole or by using frame formwork methods: by the end of the elevation of 100mx100mm wood with steel or wooden pillars supporting the load-bearing wall, above the party bearing slab of wood to the straight, steel or wooden pillar bottom pad through long hand, Poles root wood wedge back to ensure slab elevation.
3.3 line of position: in a load bearing wall or beam of prestressed concrete hollow plate side, according to design drawings and drawing board seam line should be marked on the beam or wall plate model, press design open seams between plates with a circular hole, when design provided, Board width is generally 40mm. Joints wider than 60mm, shall be reinforced according to design requirements.
3.4 lifting floor: uniform force lifting requires the lifting point, surface level, avoiding torsional warping cracking. Such as walls with cement mortar screeds, sprinkled on the floor before a wall or beam lifting pigment slurry (water/cement ratio 0.45). According to the design drawings to check the wall plate number is correct and accordingly may not be misplaced. Line end alignment during installation, slowly decreased after the stand allows decoupling.
3.5 adjust position: lever toggle plate end, plate ends up wall length and distance between plates in accordance with design drawings.
3.6 tying or welding anchor bar: short Board, will end out of a sheet anchor bar (bearded wheat) collated and bend into a 45 ° bend and cross each other. Tie 1 φ 6 connection bars at the intersection. Joints should not be less than 40mm, is greater than 60mm, shall be reinforced according to design requirements. Is strictly prohibited on the anchor bar bent under 90 ° or to the Board. Bent anchor bar bushings when slow bend to prevent bending and breaking. If he is to board a long time, after installation according to drawings will be welding anchor bar, 1 φ 12 long bars, end each plate out of the prestressed steel plate end out of a sheet steel with another isolated spot, but at least every Board spot 4. Meet the requirements of specification for welding of welding quality.
4 quality criteria
4.1 project:
4.1.1 hoisting strength must conform to the design requirements, such as when there is no requirement, should not be lower than the design strength of 70%. Check the widget factory certificate.
Type, location, point 4.1.2 component anchoring must comply with the design requirements and no damage. Check the lifting records.
4.2 Basic project:
4.2.1 elevation, slurry, end plug holes, seam width should comply with the design requirements and the provisions of the code.
4.2.2 welded joints smooth surface, no dents, weld, and weld length to meet the requirements, the joints free of cracks, pores, inclusions and undercuts.
4.2.3 allowable deviation
Floor shelving length: ± 10MM standard check.
Small floor surface height difference:
Plaster 5mm
Don't plaster 3mm
5 finished product protection
5.1 at the plate with a circular hole in the transport and stacking of different panels should be stacked. Stacking ground leveling and tamping, stacking plates and when there is a gap between the ground and drainage measures, transportation Board assembling firm, in case of moving, jumping, or dumping, both on the plate and concrete at rope contact, gasket should be used to protect it.
5.2 structure of concrete wall when installing the floor, under normal circumstances, concrete strength in wall 4MPa above, installed floor.
5.3 short to the pre on the plate with a circular hole, which allowed rejection digging smaller holes, and continuously break two ribs, gently scrape, and must not damage the rest of the Board; when you need to tick a lot of holes in the plate, should be invited to designers to calculate and reinforcement. For the long boards are also only allowed rejection of small holes and not hurt and the main bar, if there are difficulties, should be invited to designers to calculate the relative reinforcement.
5.4 anchorage plate with a circular hole reinforced to properly protect, no bending or breaking.
5.5 after you buckle the plates and middle of the Board should be supported to ensure construction safety and installation quality of the floor.
5.6 installation floor must not tread on the beam.
6 quality problems to be noticed
6.1 Installing the unqualified floor: before you install the floor not only to check the certificate, you should also check for cracks or other defects. Prevention is in place and found not qualified.
6.2 end of lap length in the bearing is not enough: installation not allowed, pull both ends of lap length. Or feel free to move the panels after installation.
6.3 floor blind stitch: not according to the design drawings before installation drawing width line; hoisting without cable in place other people feel free to move the Board, blind, will cause the floor joints.
6.4 lap false floor and support: gusset plate should be checked before the wall elevations, good mortar screed, lining of water the mud during pulping.
6.5 plug hole too shallow and floor anchorage bar broke: check the holes before buckle-blocking design requirements. Short plates anchoring stiffened to straighten out, in accordance with the regulations tying rebar to prevent under pressure into the wall, long to the welding of plate anchorage reinforcement in accordance with the regulations.
7 quality records
This standard shall meet the following quality records
Certificate or test report 7.1 quality steel.
7.2 steel mechanical test reports.
7.3 widget factory certificate.
7.4 certificate of welding electrode factory.
7.5 prefabricated lifting records (pre inspection records).

7.6 components install section for quality inspection and assessment records.
Because of the war, many people become homeless. I can't do it well. Please help me.my PayPal is xhhnet@163.com.

No comments:

Post a Comment