Spiral drilling caisson pile construction technology

1 scope
This technology is applicable to industrial and civil construction of groundwater in the General clay, sand and Auger hole filling pile in artificial filled soil Foundation.
2 construction preparation
2.1 materials and equipment:
2.1.1 cement: appropriate uses, No. 425 Portland slag cement.
2.1.2 sand: sand or coarse sand, clay is less than 5%.
2.1.3 the gravel: gravel or crushed rock, size 5~32mm, clay is less than 2%.
2.1.4 steel: steel grade, diameter must conform to the design requirements, certificate and retest report of the factory, the surface should be free of old rust and grease.
2.1.5 blocks: 1:3 cement mortar buried wire preformed in advance, 22nd or plastic cards.
2.1.6 wire: wire specifications 18~20, firing.
2.1.7 admixtures: admixtures; under construction need determined through experiments.
2.1.8 main equipment:
2.1.8.1 Auger boring machine: common technical parameters is shown in table 2-7.
Auger boring machine main technical parameter table 2-7

Motor power
(KW) rotary speed
(R/min) Rotary torque
(N • m) into the pressure
(N) the drilling speed
(M/min) external dimension
Length x width x height (m)
Crawler-LZ-30 81 3400 2800 2 8.0x3.21x21.78
-Auto-QZ~4 17 120 1400-1 7.3x2.65

2.1.8.2 maneuvering small dump trucks or carts, load and unload earth-moving or transport of concrete.
2.1.8.3, short Rod-type vibrators. Some long flexible shaft, concrete mixers, flat-nosed shovel, hose, etc.
2.1.8.4 slipped cylinder, cover, measuring line, hand lamps, low voltage transformers and lines, and so on.
2.2 operating conditions:
2.2.1 aboveground and underground obstacles were processed to achieve "three connections and one leveling". Temporary facilities are ready for construction.
2.2.2 landmarks in general we should cap the epithelium of the beam elevation and rammed or rolled.
2.2.3 good fabricated steel cage, its length to 5~8M is appropriate.
2.2.4 released axis according to the drawing and pile points, Gao Mujue horizontally on the copy, and pre-screened visa.
2.2.5 construction hole should be made before trial, the number of not less than two.
2.2.6 to select and determine the order of access routes and drilling drilling machine, and formulate programmes, technical clarification.
3 operational processes
3.1 process:
3.1.10% hole process:
Drilling machine in place drill bottom cleaning quality hole orifice plate drilling machine

3.1.2 concrete process:
Move cover plates measuring depth, vertical slip concrete pouring of concrete of steel cage (with the cast with vibration) Insert pile head reinforcing bar

3.2 drill in place: drilling machine in place, must remain stable, do not tilt and displacement, for control and accurate drilling depth should be made at the rack or pipe control rods, to observe, record in the construction.
3.3 borehole: straightening racks tappet, good position (on), start the machine drilling, unearthed, to control the depth after drilling, drilling.
3.4 checking the quality of hole:
3.4.1 drilling depth determination. Sounding-line (hammer) or Lantern holes deep and tilled soil thickness. Difference of the imaginary depth equal to drill deep. Tilled soil thickness should not exceed 10cm.
3.4.2 aperture control. Drilling of soil containing more blocks whenever, or when large water content soft plastic clay stratum, we must prevent the pipe shaking caused aperture to expand, resulting in holes wall attachment of disturbed soil and the hole end of fall.
3.5 hole the subsoil cleanup. After drilling to a predetermined depth, must be idling in the hole at the end of Qing dynasty, and then stopped, carry the pipe may not be music Kelly. Thickness of downhole deficiency exceeds quality standards, to analyze the causes and take measures to deal with. Scattered on the ground of the soil in the drilling process, must be cleared away.
3.6 moving the drilling rig to the next pile. Through hole inspection, should fill in the pile hole construction records. Then, cover the orifice plate, and to prevent the cover driving, or on leave. Finally, remove the drilling rig to the next pile.
3.7 concrete:
3.7.1 removing Burr hole cover plate once again review the depth, diameter, bubble wall, vertical and hole bottom of tilled soil thickness. When you do not meet the quality standards, should be qualified, then the next procedure.
3.7.2 dipping steel cage: steel cage should tie before in mortar blocks (or plastic card); dipping steel cage, must aim at the hole, hanging straight steady, slow down, avoid collision wall. Steel cage to design position, should be fixed immediately. In case of two-stage connection of steel cage, weld should be taken in order to ensure that the bar is correctly positioned to ensure the thickness meets the requirements.
3.7.3 on slip tube pouring concrete. In front of the sliding tube should be checked again and measure virtual depth. Concrete should be continuous, layered vibration compacting, lamination height to tamping tools may be. Must not be greater than 1.5M.
3.7.4 when pouring concrete pile, due over the pile design elevation to ensure cut after removal of laitance, top level meets the design requirements.
3.7.5 withdrawal slip tube and plug the top bar. Concrete poured pile 1.5M, pull out the sliding tube, directly into concrete. Steel inserted perpendicular to the rail must be inserted at the top of, there is enough cover and anchorage length to prevent Plug and insert diagonal.
3.7.6 the slump of concrete suitable for 8~10cm; to ensure its workability and slump, should adjust the rate and the addition of superplasticizer sand and fly ash.
3.7.7 the same mix of blocks, each class shall not be less than a set.
3.8 in winter and rain during construction:
3.8.1 in winter when the temperature is lower than 0 when pouring concrete, heating and insulation measures should be taken. When pouring, temperature of concrete in winter construction programmes shall apply. Top of the pile is not to design strength 50% must not be frozen. When the temperature is higher than 30 , the retarded should be taken depending on the situation of the concrete measures.
3.8.2 strictly adhere with the drill with the rain pouring concrete provisions in case of rain into hole collapse caused by irrigation. Rainy days drilling is not possible. Site must have drainage measures, prevent surface water into the tank, so as to avoid collapse or the base of the slope and soil subsidence, drilling machine incline.
4 quality criteria
4.1 project:
4.1.1 piles of raw material and concrete provisions must comply with the design requirements and specifications.
4.1. the 20% hole depth must meet the design requirements. Pile dominated by friction, sediment thickness no greater than 300mm; end-bearing piles, sediment thickness no greater than 100mm.
4.1.3 the actual pouring of concrete, no less than the calculated size.
4.1.4 top elevation of pouring concrete pile and treatment of laitance must meet the requirements of specification for design and construction.
4.2 allowable deviation, as shown in table 2-8.
5 finished product protection
5.1 during the process of fabrication, transportation and installation of reinforcement cage, measures should be taken to prevent deformation. Into the drilling, there should be protection pad. Tubes and the pad or pad.
5.2 reinforcement cage in the hanger into the holes, no collision hole. When pouring concrete, should take steps to fix its position.
5.3 basic excavation pile construction is completed, should formulate a reasonable construction and technical measures in order to prevent displacement and tilt. And review the level of vertical and horizontal deviation of each pile.
Auger drill hole filling pile tolerance table 2-8
Project tolerance (mm) test method
1 steel cage reinforcement spacing ± 10 ' check
2 Stirrup spacing of reinforcement cage ± 20 foot check
3 steel cage diameter ± 10 ' check
4 length of steel cage ± 100 foot check
1~2 pile
Perpendicular to the center line of the pile of single rank of piles d/6 and not more than 200 cable and check
5 positional deviation of group piles foundation piles

Strip foundation piles
The Middle pile of pile foundation
H/100 hanging wire and vertical 6 foot check
Note: d for diameter of the piles, and h is the length.

5.4 after the hole in the steel cage, to pour concrete in the 4H. In the pouring process, and there should be no reinforcement cage floating mud pollution prevention measures.
5.5 installing the drill when the reinforcement cage, transport and pouring of concrete, should pay attention to protect the scene of the axis, elevation.
5.6 external reinforcement inserted iron to protect, not any bending or breaking.
5.7 strength of pile head concrete, without up to 5MPa shall not be laminated to prevent damage.
6 quality problems to be noticed
6.1 well tilled soil by the end of excess: drilling is completed, should cover the openings in a timely manner, and prevent the cover on a car and walk. Operations should be cleared up in Virtual Earth. If necessary, second vote for drilling soil of Qing dynasty.
6.2 collapse crater: note changes in soil, sand and gravel, or plastic mud, perched water leakage and so on, should be studied in conjunction with the relevant authorities.
6.3 quality of pile concrete difference: necking, empty, folder and so on, must be strictly according to the operating regulations of the pouring process of concrete vibrated. No debris mixed with soil and pouring in concrete.
6.4 deformation of steel cage: steel cage stacking, transporting, lifting, into the hole in the process, there is no strict according to the operating regulations. Technology gives the low-down on workers must be strengthened, strict implementation of the reinforcement of the quality measures.
6.5 when the drill pipe to beat Hoang, rack, shaking, drilling footage and other anomalies, should immediately stop checking.
6.6 when the water closer to the pile of concrete, to measure elevation at the top, so as to avoid cutting off too much and remedial piling.
6.7 drilling into sand when groundwater is encountered, drilling depth should not exceed initial water level in case of collapse.
7 quality records
This standard shall meet the following quality records:
7.1 cement factory prove and retest proved.
7.2 certificates or certificates of steel bar and shop test of steel bar single-copy.
7.3 test pressure test records.
7.4 repair sketch pile.
7.5 pile construction records.
7.6 test of concrete application form and mix orders issued by the laboratory.
7.7 28D compressive strength of standard curing concrete block test report.

7.8 factory certification of ready-mixed concrete.