Friday, November 18, 2016

Installation technology for indoor gas fire extinguishing system

1 scope
The standard is suitable for civil and industrial buildings set in carbon dioxide fire extinguishing system, Halon 1211, 1301 fire extinguishing system of pipeline and equipment installation.
2 construction preparation
2.1 after receiving the task, earnestly familiarity with construction drawings, checked against the renovation and the construction site pipe and nozzle position is consistent, as problems with design consultation and the negotiation formalities in time. Determined according to the characteristics of the construction method, is equipped with the resources required.
2.2 equipment and materials:
2.2.1 fire service fire extinguishing system main equipment selection of materials shall comply with 611 "General requirements for the installation of fire engineering" of the relevant content.
2.2.2 major equipment: fire extinguishing agent storage containers and system components including valves, container valve, selector valves, valve drive device and nozzle. These system components should be addressed to the national quality supervision and testing center qualified. Cannot retest products used in the system, such as security patch and so on, should be issued by the manufacturer of the same batch of product test reports.
2.2.3 General material: pipes and fittings, steel, welding rods, nitrogen, oxygen, acetylene, PTFE tape, expansion bolts, bolts, nuts, and gaskets; oil, paint, thinner, smaller lines, wire, batteries, and so on.
2.3 main machines: saw tube machine, casing machine, bench drill, hand drill, shot nail gun, welding machine, air compressor, dedicated bent tube machine, step phone, tube clamp, pressure case, handsaw, hammer, adjustable tube dedicated bracket, hacksaw, file, die, wrench, live wrench, screwdriver, hammer, cold chisel, steel tape, flat feet, square, oil standard caliper, level feet, line pendant, white silk or white, pencil, chalk, pencil,.
2.4 operating conditions:
2.4.1 reserved embedded should be aligned with the structure of construction.
2.4.2 required for network installation reference line shall be determined and marked. Ceiling in the pipeline should be completed by the ceiling.
2.4.3 equipment should be installed in the device after you complete the crude decoration.
3 operational processes
3.1 process:

Installation ready to install network system equipment and accessories installed commissioning and function of acceptance

3.2 installation preparation:
3.2.1 familiarity with drawing paper and review pipelines to control site, identify problems and design solutions in a timely manner. Check for correct reserve embedded; interim pick your cut and design, construction coordination.
3.2.2 enter testing equipment and materials: equipment and material specifications: model shall meet the design requirements, look, defects, deformations and corrosion-free, galvanized or painted uniform no shreds, interface thread and flange seal surface damage; pressured pharmaceutical cylinder pressure gauge pointer should be within the specified range. Select valve, check valve, high pressure hose, collecting pipe hydrostatic test pressure and leak test results one by one, shall meet the specifications provided.
3.3 network installation:
3.3.1 gas fire suppression system pipe should be selected according to design requirements or the storage pressure, cold-drawn precision seamless steel tube and is usually used inside and outside galvanized. When the nominal diameter less than or equal to 80mm, the threaded connections should be used when 80mm mm nominal diameter pipe, flange connection should be used. Threaded and flanged fittings should meet the test pressure and inside and outside galvanized. For corrosive environments can be used for zinc coating or stainless steel pipes.
3.3.2 the piping installation should be carried out before straightening and cleaning up debris. Flange connections, were damaged by welding zinc plating to do with preservatives. Thread connection, thread packing polyethylene PTFE tape should be used. Cutting nozzle application file NET Burr.
3.3.3 fire extinguishing pipe must be fixed firmly. Nominal diameter mains greater than or equal to 50mm, the vertical and horizontal direction should at least install a baffle brace. When through the floors of buildings, and shall have a baffle on each bracket. When the horizontal line changes direction, slosh bracket should be added. Piping support and hanger maximum spacing should be installed in accordance with the following provisions:
Nominal diameter (mm): 15 20 25 32 40 50 65 80 100 150
Maximum spacing (m):1.51.82.12.42.73.43.53.74.35.2
3.3.4 dry tube installed, a bottle of pipe should be installed first, find the right size after immobilization, distance between tubes and tube should be in strict accordance with construction drawings to determine, ensure the equipment installation size, then order other pipelines. All piping installation size should be consistent with the design drawings, do not arbitrarily changing the pipe direction and length.
3.3.5 halon 1301 and tee diversion of export carbon dioxide pipeline should be installed horizontally.
3.3.6 ceiling sprinkler branch pipe installation, nozzle position should be determined according to the drawings in the field, can fit ceiling decoration of the conditional, but ceiling panels should be completed before the system pressure, tightness test. Sprinkler branch pipe should be added to the attachment bracket, bracket and the nozzle duct length should not exceed 500mm.
3.3.7 network strength test shall be performed is installed, such as the use of hydraulic pressure test, the test pressure is 1.5 times working pressure. Such as air pressure test, the test pressure is 1.2 times times the working pressure. Test pressure regulator 5min, no significant leakage, I think the pipe deformation for qualified. Pipe hydrostatic strength test pressure high pressure carbon dioxide fire extinguishing system should be 15MPa.
3.3.8 strength test, the network should be purged. Purging pipe ends should ensure the flow of 20m/s when using checked cloth until no rust, dirt, water stains and other booty appears qualified.
3.3.9 pipe network pressure test, after the purge gas pressure leak test should be carried out, test pressure working pressure regulator 3 minutes, pressure drop not greater than 10% qualified.
3.3.10 network volume not work when the pressure is not high, strength testing, purging and nitrogen leak test should be used.
3.4 equipment installed:
3.4.1 pharmacy cylinder installation: cylinders transport protection measures need to be taken to prevent collisions, bruises. Install the pressure gauge when the observation plane and the product label should be facing out. Cylinders should be arranged in space comply with the design requirements. Cylinder weight floor commitment fixed is generally fixed a channel on the wall first, and cylinders with holding cards with channel lock together. Hold card height should be around cylinders 2/3 and try to avoid the sign. When the channel cannot be fixed on the wall, and also be a framework for rooting in the ground.
3.4.2 set pipe installation: chemical cylinders through the elbow joint, high pressure hose and nonreturn valve is connected with the collecting pipe. Collecting pipe welding method should be used, each product should be used before welding machine manufacturing, galvanized after welding. When storing the pressure is not greater than 4.0MPa, diameter not greater than 80mm, or threaded connection. Collecting pipe should be located at least two reliable fixation. Ends of shall have a safety relief valve.
3.4.3 select valve installation: select the vent valve installed in the flow tube, when the installation height exceeds the 1.7m operational measures should be taken. Select valves with threaded connections should be increased when a flanged interface. Select valve installation should be a high degree of consensus.
3.4.4 valve drive installation:
3.4.4.1 valve drive device function is in a protected area of fire opened the pharmacy when the cylinder container valves and fire selector valve. Driving mode electromagnetic, pneumatic and mechanical manual drive, and so on. Control mode of automatic, manual and emergency braking.
3.4.4.2 electromagnetic drive device of the electrical connection cable should be fixed fire extinguishing agent storage containers, frame or wall fixing.
3.4.4.3 manual cable-drive unit includes: protection box, cable box, pull handles, wire ropes and manual valves. Steel wire ropes shall have a casing and internal and external corrosion protection. Cable bend special pulley. Sleeve and protective case should be fixed firmly.
3.4.4.4 install objects when the gravity-driven mechanical drive device, should ensure that the weight falls trip no barrier, required for their journey should exceed the valve opening stroke 25mm.
3.4.4.5 pneumatic actuators of nitrogen bottles, copper pipe and pressure activated valve and so on. Nitrogen bottle installation and the cylinder installation is basically the same, copper tubes expanded mouths flaring Suo Mu connector parts connection. Copper tube should be installed horizontal even vertical fixed support spacing and the parallel conduit clip spacing should not exceed 0.6m, pressure tightness test shall be performed after installation, test pressure shall not be less than the nitrogen bottle storage in pressure regulator 5 minutes, not qualified.
3.4.5 pressure switch installation: the pressure switch's role is to work in the system under pressure feedback signals, usually in the collecting pipe tapered at the end of the installation, or cones on the fitting connector wire installation.
3.4.6 nozzle nozzle towards open specifications and open holes must meet the design requirements, special wrench should be used during installation.
3.5 system commissioning and function of acceptance:
3.5.1 gas fire extinguishing system is installed according to the total number of protected area (less than 10 by 10 meter) simulated Jet test on 10%. Jet region should prepare protective measures. Test results shall meet the design requirements.
3.5.2 halon fire extinguishing gas spray should be simulated using nitrogen, nitrogen cylinder charging pressure shall not be less than the pharmacy cylinder storage pressure, structures, models, specifications and container should be the same number of 20% pharmacy bottle, and shall not be less than l.
3.5.3 carbon dioxide fire extinguishing system using carbon dioxide to simulate the Jet tests, test the number of containers should be used for the protective District 10% of the total actual use of chemical storage containers, and shall not be less than 1.
4 quality criteria
4.1 project:
System pressure test results must comply with the design requirements. Completion must be done before the purge.
4.2 Basic project:
System pipe length and direction, rainfall showerheads and nozzles must conform to the design requirements.
4.3 allowable deviation:
Sprinkler branch pipe fixation distance between nozzle pipe length is not more than 500mm.
5 finished product protection
Installed gas cylinders room should have professional management to prevent sprayed errors lead to false positives.
6 quality problems to be noticed
6.1 pipe galvanized pipe-cone bit bad because pipe wrench old, caused by tight.
6.2 cylinder transport damage the coating. Due to lack of protection measures.
7 quality standard

6-3 "indoor sprinkler system installation standards."

No comments:

Post a Comment