1 scope
This technology is applicable to General
section steel roof truss installation works.
2 construction preparation
2.1 materials, semi-finished products and
equipment:
2.1.1 steel components: models, making the
quality of steel Member should comply with the design requirements and
provisions of the code, should have a factory certificate and shall be
accompanied by a technical file.
2.1.2 connection material connection
materials have quality certificates such as welding rods, bolts, and to comply
with the design requirements and the relevant provisions of the national
standard.
2.1.3 coating: anti-rust performance shall
conform to the design requirements and the provisions of the relevant
standards, certificates of product quality.
2.1.4 other materials: variety of horns,
and so on.
2.1.5 major equipment: lifting machinery,
lifting and rigging, welding, Electrode holder, welding wire, wood, Horn,
wrenches, pry, Torque Wrenches, hand wheel, electric drills, and so on.
2.2 operating conditions:
2.2.1 the component list, check the
entering the number of artifacts, inspection of factory certification and
related technical information.
2.2.2 checking components in loading and
unloading, transporting and stacking damage or deformation. Damage and
deformation of the components should be corrected or reworked. Anti-rust
coating of touch-loss, and once again check the acceptance formalities.
2.2.3 components of profile geometrical
dimensions, drilling, Assembly, welding, friction surface checks, making
records.
2.2.4 component should be the order of
installation of steel structure supply, field pile site to meet the needs of
field assembled and installed in the order. Roof fragment factory, groups
together at the scene should be prepared to assemble the Workbench.
2.2.5 component classification stacked,
stacked component can pave the way wood stiffness levels. When several stacked
on a vertical wood. Roof trusses should be standing, next to the post, binding
firm.
2.2.6 preparation of construction
organization design of steel structure installation, approval, and team cards.
2.2.7 checking for installed base and
embedded parts, total package made qualified acceptance of information.
3 operational processes
3.1 process:
Job preparation spell → group → roof truss
roof truss installation connected with fixed → → → rust inspection,
acceptance, brush coating
3.2 installation preparation:
3.2.1 to reinspect the installation
position the axis of the control points and measuring elevation benchmarks.
3.2.2 release level control line and axis
of the roof truss installation guides.
3.2.3 to reinspect the embedded parts of
the roof supports and supporting systems, its axis, height, level, location and
length of exposed embedded bolts, etc, when tolerances are exceeded, should complete
the treatment.
3.2.4 checking hoisting machinery and
hoisting, in accordance with the requirements of construction organization
design of erection of scaffolding or platforms.
3.2.5 truss Web design for rod, but when
lifting due to the hang point location so that it forces change-lever, to
prevent deformation, instability, reinforced measures should be taken, if
necessary, in the direction parallel to the roof top, bottom with steel, wood,
or other provisional measures.
3.2.6 measurement ruler and ruler for
making proof of steel structure and legal units of measurement achieved
approval and certification.
3.3 frame groups together:
Roof fragment brought on to the site to
assemble, Assembly platforms should be flat. When groups fight should ensure that
the total length of the roof truss and Arch sizes you want. Welding welding end
side after passing the examination, and then rolled over welded side, good
construction records. Check rear allow installation. Roof trusses, and
skylights can also be assembled on the ground lifting, but temporary
reinforcement to ensure lifting had sufficient stiffness when.
3.4 roof truss installation:
3.4.1 lifting point must be located in the
roof trusses on three concurrent node. Roof lifting off the ground 50cm pause, check
and correct to continue lifting.
3.4.2 when you install the first frame
roof, release the hook before the initial correction; align roof trusses
centerline or axis positioning of supports in place, adjust frame vertical and
check the roof direction bending, roof temporary fix.
3.4.3 second pin frame the same way when
the hoisting, don't loose hooks, use Cedar pole or beam to temporarily fixed
with the first frame roof trusses, support system and part of the Purlin,
finally correcting fixed, so the first pin roof trusses and the second frame
roof truss to form a spatial stiffness and stability as a whole.
3.4.4 starting from the third frame roof,
installed in the roof and the midpoint of the chord Purlin roof can be fixed
on, while room correction well.
3.5 Member connections and fixed:
3.5.1 components are installed with welded
or bolted joints, check the connections, qualified before welding or
tightening.
3.5.2 installation bolt holes are not
allowed to use gas cutting, reaming pad more permanent bolts washers, exposed
threaded length not less than 2~3 buckles.
3.5.3 install tack when you do not need to
load, weld design weld thickness of not less than 2/3 and less than 8mm, weld
length should not be less than 25mm, the location should be within the weld.
Installed full Visual inspection of weld, mainly according to the design
requirements of ultrasonic inspection of weld quality. These checks are
required to make a record.
3.5.4 welding and high-strength bolting
process as described in the standard.
3.5.5 roof bearing, support structure of
the system should be checked carefully, you must comply with the design
requirements and spare parts may not be missing.
3.6 check acceptance:
3.6.1 roof quality connection first check
after installation.
3.6.2 roof truss installation Center for
quality check roof for two supports vertical no vertical; compression chord
trusses of roof trusses on sides of the vertical surface, must ensure that the
deviation does not exceed the tolerances mentioned above, to ensure that the
roof with the design stress and stability requirements.
3.6.3 roof elevation, axial displacement of
the bearing, mid-span deflection, measured a record.
3.7 removing rust, paint:
3.7.1 connection weld without welding slag,
oils, derusting qualified before brushing paint.
3.7.2 dry paint film thickness of coating
should comply with the design requirements or provisions of the code.
4 quality criteria
4.1 project:
4.1.1 installation engineering quality
inspection and evaluation of steel structure, should be in the welding or
bolting after the quality inspection and assessment of compliance with
standards.
4.1.2 components must meet the requirements
of specification for design and construction, factory certificate check
components and accessories. Deformation due to transport, stacking and lifting
must be corrected.
4.1.3 support position, done right, contact
surface smooth and firm.
4.2 Basic project:
4.2.1 members tag; centerline and elevation
benchmarks complete clear.
4.2.2 structural surfaces clean, welding
scar-free, oil-sand and mud.
4.3 allowable deviation; see table 5-13.
Table 5-13
Project tolerance (mm) method
1 straight l/1000 truss chords between
adjacent nodes and not more than 5 cable and tools check
2 ± 5 Purlin spacing ruler check
3 vertical h/250 and not more than 15 with
a theodolite or hanging wire and steel rule check
4 lateral bending L/1000 and not more than
10 cable and tools check
Note: h for the roof height, l is length of
roof trusses, l for chords in the distance between adjacent nodes.
5 finished product protection
5.1 Installing the roof plate, slowly
falling, no collision has installed steel roof, skylight frames and other steel
components.
5.2 lifting damaged coating coating, to
ensure the film thickness meets the requirements set out.
6 quality problems to be noticed
6.1 bolt hole wrong: no any hole or to
welding, installation of such problems should report technical director, after
consultation and design units, as required for processing.
6.2 field welding quality is not up to the
design and specifications: welder must have a certificate of induction and
should be numbered, welding parts by number check records, all weld by Visual
inspection, where a site does not meet requirements, retesting after welding
should be.
6.3 does not use mounting bolts, installed
directly on high strength bolt installation must be installed according to
specifications using bolt temporary fixing, after adjusting the fastening,
high-strength bolts should be installed and replaced.
6.4 connected roof truss the base
structures do not meet design requirements: when installing the full and final
inspection and acceptance of steel roof truss, such as bearing structure does
not meet the design requirements, not the acceptance formalities.
7 quality records
This standard shall meet the following
quality records:
7.1 drawings of steel structures, design
changes, record of negotiation.
7.2 installation connected with the steel,
materials and coatings materials quality certificate or test report and
re-test.
7.3 installation process
engineering-related documents.
7.4 the welding quality inspection reports.
7.5 installation inspection records and
quality assessment for installation information.
7.6 data after installation of steel
structure painting.
No comments:
Post a Comment