Plastics flame retardant, flexible (corrugated) pipe-laying technology

1 scope
This technology is applicable to buildings electric lighting, plastics, flame retardant, flexible (corrugated) tube dark laying. Not in places of high temperature, places vulnerable to mechanical damage and laying of the roof.
2 construction preparation
2.1 materials requirements:
2.1.1 plastics flame retardant, flexible (corrugated) pipe and fittings must be made of fire-retardant treated materials, the tube wall should be spaced not more than 1M the continuous flame marks and factory standards and product certification. Pipe wall thickness uniformity, no cracks, holes, bubbles and deformations, and so on. Corrugated pipe shall not be stored at high temperatures and open spaces stacker.
2.1.2 distribution box. General power distribution box, tank shell of steel, corrosion prevention measures. Whole set of distribution box shall be two certified manufacturers of products, product certification.
2.1.3 switch box, outlet boxes, lamp boxes, junction boxes, plastic boxes should look neat, complete knockouts, no splitting phenomenon.
2.1.4 tube clamps, pipe clamps, designer should use the flame retardant plastic products.
2.1.5 plated zinc material: flat steel, round steel, wood screws, machine screws, wire, etc.
2.1.6 supplementary materials: paints, wood bricks, Gordon, cement, sand, and so on.
2.2 the main tools:
2.2.1 hammer, chisel, and hacksaw, knife saw, semi-circular file, hand drill, hydraulic opening, adjustable wrench.
2.2.2 level, box feet, Gray Ash bucket, shovel, bucket, small line, line, high chair, etc.
2.3 operating conditions:
2.3.1 building horizontal and the thickness of the wall line is playing well.
2.3.2 laying pipeline should work closely with the construction work.
3 operational processes
3.1 process:
Prefabrication tube pre box positioning and so Kwun Wat

3.2 General requirements for pipe connection:
3.2.1 tube and pipe connection:
Generally bellows are mating coupling for pipe connections, connection tube counterparts should be at the center of pipe straps.
3.2.2 tube connection to the box, box:
3.2.2.1 tube head connection: bellows are supporting the pipe clamp head, can be used for pipes and connection boxes, cartons.
3.2.2.2 list of connected: corrugated pipe straight through the two holes in the box, constantly pipes. Template to remove, cut the tubes after clearing the box, installed before the nozzle at the thread protection.
3.3 operations: in accordance with design dressed hooks, bolts and wood blocks, embedded parts, fixed boxes, boxes of cards processed iron or bridge bar, and so on.
3.4 Pack, box positioning. According to the horizontal line and wall thickness determination of boxes, cartons, rows, rows of lamps should be ejected reticle determines the position lamps.
3.5 tube:
3.5.1 tube shall conform to the following requirements:
3.5.1.1 according to the design of pipeline laying the pipe direction, and should be laid along the shortest route and should reduce bending.
3.5.1.2 the bending of the pipe should not be greater than 90 °, bend radius should not be less than 6 times the pipe diameter, bend shall not have folds, pockets and cracks, bend flat should not be greater than the pipe diameter of 10%.
3.5.1.3 piping there shall be no visible phenomenon, embedded in walls or concrete pipes, surface distance should not be less than 15mm.
3.5.1.4 line straight line segment length over 15m or right angle bend when more than 3, are indirect box should be installed.
3.5.1.5 pipeline after deformation joints, should set compensation device.
3.5.1.6 tube boxes, box, tube should flush pipe Show box, boxes should be less than 5mm, and a tube of a hole, hole size should fit with the pipe diameter.
3.5.2 tube method:
3.5.2.1 laid masonry wall:
A wall should be combined with corrugated conduit in the wall. Upward tube, nozzle should be well plugging, and temporary support rods (rebars) along the direction of laying the tubes started. For making boxes, cartons smooth, accurate elevation, to laying pipe to the box, box 100mm, wall in place, stable boxes, cartons, and pipe connections.
Keep boxes, cartons. Line or horizontal alignment, boxes, boxes with the wall should hang level; and taking into account the thickness of plaster, box, box flush with the plaster walls.
B mark Groove routed pipe segment, allowing only vertical tick Groove, Tenon and a no reserve is too large, influence of wall strength. Pick your front, should slot line on both sides, with cold chisel tick. Wall of aerated concrete used saws saw blades on both sides, and then tick. Slot width and groove depth is larger than the outer diameter of the pipe 5mm is appropriate. Apply pipe, every 0.5M about using nails, thin wire to the pipe fixed, must then be protected with intensity not greater than M10 cement mortar, thickness should not be less than 15mm.
3.5.2.2 precast floor slab laid on:
A prefabricated light on a plate with a circular hole punch, should get a nice round hole from bottom to top for a; or prestressed slab of laminated plate light punch, power hammer in the top hole first, and then in the following reaming. Pore size is slightly larger than a lamp box.
Conduit Circular box installed iron or bridge card (laminated slabs prestressed piles of boards should be used or lamp boxes), after installation of a pallet in the Board, with the strength of cement mortar not less than M10 stability buried.
B to be solidified with cement mortar tubes. When the double-layer bars, pipe should be laid between two layers of steel, and should be reinforced at the end of laying. Line every around 0.5M, from the lamp box within the 0.15~0.2m are fine wire or nylon lashing, binding should be solid. For laying precast plate with a circular hole holes inside the pipe, should be worn along the boards directly to the lamp box, boxes of buried pipe cement mortar in prison. Laying of pipe cement mortar in the bedding protection.
Tube into the wall with reserved should not be too long. Upward tube steel stir up and blocked well pipe.
If ceiling fans, lanterns and other embedded hooks or bolts.
3.5.2.3 within the concrete wall installation:
A concrete wall boxes, boxes can be installed iron card, card on rail welding of vertical reinforcing steel bar in the wall, can also be drilled steel template, use wood screws on the box, the box will be fixed in the template, after a concrete pour, remove drain screw in a timely manner.
For making boxes, cartons elevation accuracy, ensure the control box, box recessed wall depth or stable box, box approach. With a simple wooden box, case or box instead of the box, in the box embedded in the wall, after removal, remove the wooden boxes, cartons and boxes, and stable box, box, and pipe connections.
B pipe laying in the middle of two layers of steel. Vertical pipes should be along the same side of vertical reinforcement laying straight horizontal pipes laid along with lateral transverse reinforcement (note that reducing the impact of concrete pouring on the tube).
Tube into the box, the box should be blocking good pipe and plug good boxes. Line about every 0.3M, from boxes, cartons 0.15~0.20m apply a thin wire or nylon solid banding location.
C when using sliding formwork construction, by the switch box or junction box to light the pipe to the bracket inside the wall, after sliding, shall promptly remove the tube, when the roof, causing light.
3.5.2.4 laying the concrete floor:
A concrete floor boxes can be installed iron rod or bridge, or use the wear bars, iron or bridge bar on welding in steel. Can also be drilled steel template, use wood screws securing the box directly to the template, after pouring concrete, remove wood screws in a timely manner. As for the wood template, available nails, thin wire lashing the box in template.
B pipe should be laid in two layers of steel, the attachment bar at the end of the deployment. Tube into the box, nozzle should be well plugging and plugging good box. Line about every 0.3M, distance 0.15~0.20m within the box, apply a thin wire or nylon binding fixed firmly.
Tube into the wall with reserved should not be too long, and should block well pipe. Upward tube steel stir up down tube while pouring concrete, it can reserve was vertically split with the wall holes (approximately 100mmx50mm), or embedded casing after removal, under the tube. When the masonry walls, then down to the boxes, cartons.
Such as fluorescent lamps, built-in wooden bricks, if ceiling fans, lanterns and other embedded hooks or bolts.
3.6 pre-Gordon:
Pipeline laying is completed, after the construction of walls, floor (concrete works should be removed after the template), should be carried out promptly and so Kwun Wat. Gordon in the process of implementation of the pipeline should be checked against the construction drawing, and promptly deal with construction of the pipeline by mistake.
General Gordon can use a thin wire or wire cloth and so Kwun Wat, with thin wire or wire line after penetrating tube, one end of the pipe fixed on the belt line strip, pulling away from the other end, clear the debris, water pipe. Gordon after the nozzle should be well plugging, and sealed the box.
4 quality criteria
4.1 project:
Bellows material and applicable provisions must comply with the design requirements and specifications.
Inspection method: observation of concealed works of inspection or inspection records.
4.2 Basic project:
4.2.1 connection close tube smooth, cover more than 15mm.
Inspection method: observation, standard checking and inspection of concealed work records.
4.2.2 box, box is set up correctly, reliable, pipe into the box, box straight, box, box showing the length should be less than 5mm.
Inspection method: observation, standard checks.
4.2.3 piping through the deformation joints compensator, compensator can move freely.
Inspection method: observation on concealed works of checking and inspection records.
4.3 allowable deviation:
Pipeline laying and installation tolerances boxes, cartons, as shown in table 3-4 below.
5 finished product protection
5.1 mark Groove, tick do not push too hard, don't pick too broadly, so as not to affect structures.
5.2 bellows on the platform after the laying, construction cart transportation through pipeline parts to be protected to prevent bruising pipe.
5.3 due care when pouring concrete, repair damaged boxes, boxes, or lines in a timely manner.
6 quality problems to be noticed
6.1 with the embedded box, boxes of civil structure prone to skew, not full of depth and mortar phenomenon.
6.2 side installation box, the box is not on the same level, beyond the allowed deviation. Should hang line stability with accurate measurement, level alignment.
6.3 pipe into the box, the box office is not straight, tube rough alignment. Margin boxes, cartons 0.15m pipe should be fixed, boxes, broken pipe inside the box should use sharp knives, operation should be carefully.
6.4 corrugated pipe bending Department should appear flat or concave die bending phenomenon. Selection of high quality pipes, tubing should not be long stored in the open air. Prefabricated building panels embedded pipe with wall connection, should be staggered in the horizontal direction and pipe bends floor and walls should tick into a curved shape. Crook installed half flame retardant casing or use hard bend, to ensure that the curvature.
6.5 when threading pipe clogging. Mainly because there is no pre-Gordon as required or not serious when Gordon. After Gordon, banged pipes in other types of construction. In addition to correct things, pre-Gordon work strictly according to the requirements and strengthen the work product protection.
7 quality records
7.1 plastics flame retardant, flexible (corrugated) pipes and accessories, test reports and product certification.
7.2 corrugated conduit pipes pre-screening, self-test, hidden inspection records.
7.3 change record of negotiation and completion.

7.4 project for quality inspection and assessment records.