1 scope
The standard is suitable for civil and
industrial indoor living drainage, rain and acid or alkaline drainage pipe
installation works.
2 construction preparation
2.1 materials requirements:
2.1.1 pipes unplasticized polyvinyl
chloride (UPVC). The adhesive used should be of the same manufacturers
accessory products should be suitable and sanitary connections, and product
certification and manual.
2.1.2 pipe inside and outside surface
should be smooth, without air bubbles, cracks, the wall thickness uniformity,
consistent color. Straight pipe deflection is not more than l%. Tube modelling
should be rules, smooth, Burr-free. Socket and socket support.
2.1.3 other materials: adhesives, steel,
bar, card, bolts, nuts, SOAP, etc.
2.2 the main tools:
2.2.1 hand drills, impact drills, hand
saws, milling mouthparts, steel scraper, adjustable wrench, hammer, level, sets
of silk, brush, cotton, thread, etc.
2.3 operating conditions:
2.3.1 pipes, should measure a good Groove,
Groove must be straight, must have a slope, bottom solid.
2.3.2 concealed piping (including equipment
and silos, pipes in the ceiling) should first check the arrangement of the
elevation, coordinates various pipes with or without contradiction. Reserve
holes, embedded with complete. Civil template has been removed, clean operation
site, install height more than 3.5M should make an outline.
2.3.3 indoor wall mounted pipe and
structural progress under two conditions apart to install. Indoor horizon
should be playing, early decorated plastering is complete. Installation site
without obstructions.
3 operational processes
3.1 process:
Installation preparation – perform the
installation standpipe installation → → → dry tube tube fixed
→ card →
Seal plug-hole water → → closed water test
test
3.2 operations: according to the drawing
requirements and the actual situation, reserved outlet position measurement,
draw processing sketches. According to sketches nice pipe size, broken pipe.
Flush fracture, fracture of milling cutter or scraper to get rid of fin, edge
milling outside the 15-degree angle. Bonding before the socket insert the test
first, not all inserts, General 3/4 of the socket depth. After passing the test
plug, with cotton and spigot required bonding parts of water, dust, wipe clean.
If oil needs to use acetone to remove. Use brush to apply adhesive, smear after
smear socket socket, then inserted vertically, insert the bonding socket a
little turn to facilitate adhesive evenly around 30s to 1min firm bonding.
Glued immediately after the overflow adhesive wipe clean. Attention should be
reserved more than adhesion.
3.3 pipe installation: first according to
the design drawings of the coordinates, elevation reserved slot holes or
service sleeve. When buried according to the design coordinates, elevation,
slope, direction of slope excavation grooves and solid. Tora hanging tube
should be used according to the design coordinates, elevation, aspect do care,
and hangers. Construction conditions, to perform a pipe, by number to the
installation site installation. Each section must by adhesion bonding process
one by one. After all the adhesions, pipe straight slope even reserved outlet
position accurately. Install riser need to install expansion joints, expansion
joints on the floor along the margin or squat 70~100mm. Closed water test
should be done after the dry tube installed, export with inflatable rubber plug
closed without leakage, the water level does not drop for qualified. Fine sand
backfill for underground pipelines should be to inhibit the 100mm, sift the
overlying soil, tamp not touch damaged pipes. Tora hanging tubes glued and then
pressing the slope in the direction of flow. Final provision sealing and
plugging the hole.
3.4 pipe installation: first by design
coordinates requirements, or after the tick will be reserved hole, hole size
not too large, but can not damage reinforcement. To clear the area before
installation, pitched on demand platform. Has good pipe transported to the
installation site. First clean up had been earmarked for expansion joints will
lock unscrewed, remove the u-shaped rubber rings to clean up debris. Review the
top hole is appropriate. Stand pipe insertion end insert length marks should be
marked, and then coated with liquid soap, locks and u-shaped rubber bands.
Installation place the State on the upper end of the tube into the hole in the
Insert vertical force to mark (general reserve amount of shrinkage and
expansion for the 20~30mm). Right after u made by steel hold card is fastened
on the expansion joints along. Being then attempt to find and measure the roof
from the tees estuary Center to meet the requirements. Errors can stop a hole,
reserved and upper expansion joint sealing.
3.5 branch pipe installation: first of all
remove embedded parts hanging tab hole or review is appropriate. To clear the
area, pitched as necessary operating platform. Good tubes by number to the
field. Remove the adhesive part of the dirt and water. Branch level up, Xu
adhesive, push nozzle into reserved. According to the length adjust the slope
of the pipe segment. Suitable fixing clamp closed reserved tube and plug the
hole.
3.6 connecting pipe installation:
verification practice building floors, walls, thickness. Find the provision of
coordinates, elevation. Then press results trimmed hole. Site measured dimensions
recorded and prefabrication, number. When you install a bonding, reserved
nozzle must be cleaned, then bonding. After the cement was found, looking for
straight, closed tube and plug the hole. Open the next layer of pipe cleaning,
using inflatable rubber plug closed the upper, closed water test. When removing
the rubber plug, and sealed the sweep.
3.7 drainage pipe installation, closed
water test required by the regulation. Every hidden embedded pipe must be
carried out according to a process. After the installation of sanitary ware and
equipment, water must pass ball test. And should be in front of the paint
finish last operation.
3.8 the underground pipes and roof
ventilation pipe do not use rigid PVC drainage fittings cast iron water pipe,
cement-twist can be used. To prevent leaks, pipe plug plastic pipe horizontal
sanding with a coarse sandpaper rough.
3.9 adhesive volatile after use should be
kept sealed. When winter construction adhesive, coagulation time and 2~3min.
Bonded areas must be well ventilated and away from open flame.
4 quality criteria
4.1 project:
4.1.1 pipe materials, specifications,
dimensions, technical performance must comply with the design requirements of
the bonding agent.
4.1.2 covert drainage and storm sewer water
test results must comply with the design requirements and construction
specifications.
Inspection methods: inspection zone (above)
irrigation experiment records, proof and adhesive pipe factory certificate.
4.1.3 the slope must conform to the design
or construction of the pipeline specification.
Inspection method: check concealed work
record or level (level), the cable and check.
4.1.4 the piping and pipe support (Tun),
laying on the permafrost and untreated soil is strictly prohibited.
Inspection method: observation of concealed
works of checks or check the record.
4.1.5 drainage pipe must be installed
according to design requirements the slip joint. If design is not required,
expansion joint spacing shall not exceed 4m.
Inspection method: observation and standard
checks.
4.1.6 the water test results after the
completion of the drainage system, provision must comply with the design
requirements and specifications.
Inspection method: water check or check
water test records.
4.2 Basic project:
4.2.1 the piping (crane, Torr) and socket
(Tun) installations should comply with the following requirements:
4.2.1.1 neat, brackets and pipe in close
contact.
4.2.1.2 bracket distance should according
to table 1-10 requirement.
Plastic horizontal drainage pipe fittings
the spacing table 1-10
Nominal diameter (mm) 50 75 100
Support spacing (mm) 0.6 0.8 1.0
4.2.1.3 allowable deviation is shown in
table l-11.
Indoor plastic drainage pipe installation
method for the determination of tolerances and table 1-11
Project tolerance (mm) method
Horizontal pipe bending in longitudinal and
transverse direction per 1M 1.5 level (level),
Full length horizontal pipe bending in
longitudinal and transverse direction (25m) is less than 38 rulers, cable and
check
Per 1M 3 hanging and foot check
Full length (5M) is not more than 15
hanging and foot check
5 finished product protection
5.1 pipe after installation is complete,
all nozzles should be closed tight, preventing debris from entering and causing
the pipe plug.
5.2 Installing the pipeline protection
should be enhanced, especially riser from below 2m, and bundled applications of
wood protection.
5.3 prohibit the use of plastic pipe as a
scaffolding stand or belt, ceiling suspension points. Do not allow open flames
Baking the plastic pipe to prevent pipe
deformation.
5.4 prior to paint pipes should be wrapped
to prevent pollution of pipelines.
6 quality problems to be noticed
6.1 good pipe bending or breaking. Straight
tube end of the stacked pads solid reasons, or due to exposure.
6.2 interface doesn't look clean and
beautiful. Adhesive spills bond after Liu Ying removed in a timely manner.
6.3 sticky interfaces is leaking. Due to
uneven coat of adhesive or adhesive is not clean.
6.4 install high or low floor drain, affect
the use. Because the horizon is not right.
6.5 seat tube through building leakage.
Because risers through building site is not waterproof.
Quality of 7 records
7.1 product certification of pipes and
fittings.
7.2 binding agent and duration of use of
the certificate.
7.3 horizontal drainage pipe inspection
records.
7.4 vertical sewer pipe inspection records.
7.5 drainage tube inspection records.
7.6 drainage pipes hidden records.
7.7 drainage pipe irrigation record.
7.8 drainage water records.
7.9 drainage pipe, horizontal pipe ball
records.
7.10 health apparatus water records.
7.11 storm sewer inspection records.
7.12 embedded water pipe pressure test
records.
7.13 rainwater pipes hidden records.
7.14 rainwater irrigation system records.