Oil-paper insulated cable 10 (6) kV joint production process

1 scope
This technology is applicable to general industrial and civil building electrical installation engineering 10 (6) kV oil-paper insulated cable connector card.
2 construction preparation
2.1 equipment and materials requirements:
2.1.1 cable connector housing must be sealed well, no impurity and sand holes, inner wall is smooth, clean, model specifications must meet the design requirements. Lead casing with pure lead content of not less than 99.9%, and able to withstand 25 standard atmospheric pressure test.
2.1.2 insulation materials must conform to the voltage level and should have test data and factory certificate (form 2-6).
2.1.3 cable compound applied styling products, factory and chemical and electrical performance test certificate.
2.2 the main tools:
2.2.1 production machinery: Windbreak fences (open operations), plastic sheeting, oil pressure wiring pliers, blowtorches, iron pot, enamel plates, aluminum pots, aluminum pots, aluminum spoons, funnels, colanders, scissors, gloves, hacksaw, file.
2.2.2 testing tool: insulating shake table, steel ruler, thermometer and test instruments, and so on.
2.3 operating conditions:
2.3.1 an outdoor cable head should choose a sunny windless weather construction, therefore before making wires should pay attention to local weather forecast, its environmental temperature + 5 ° c or more. Humidity should not be greater than 70%.
2.3.2 making cable connectors around the construction site shall be kept clean and dry. Good Windbreak fence on all sides.
2.3.3 cable production should be operated by specially trained qualified personnel.
2.3.4 construction site should meet the prescribed safety, fire, flammable for safe keeping.
2.3.5 construction site should be equipped with 220V power supply and safe power supply.
3 operational processes
3.1 process:
Construction preparation shake test of equipment point checking and calibration dimensions-tidal stripping cable insulation and cable cover

Lead casing into dismantling the tripod and exclude moisture wrapped insulation removed temporary gauze sealing

Pouring insulation adhesive cement box planted standard anticorrosion and installation commissioning inspection

3.2 cable joints made according to the following procedure for, starting from strip-cut to the completed, must be carried out continuously, at once, so as not to damp.
3.3 equipment inspection and preparation:
3.3.1 opening checking and construction of joint inspection units, delivery units and construction units, and completes the record.
3.3.2 lead wire connector casing should be based on technical information or instructions, accessories and injury-free.
3.3.3 casing wall lead clean, beating with wooden clappers at one end to form the necking (shall be made into the cable slightly larger point) with a knife out of the vent and the injection hole and cover with wrap.
3.3.4 processed black insulation tape and gauze tape small volumes, soaking in a cable 150 to surge in oil (such as no cable available transformer oil to join 25%~30% Rosin with different), and then pull out, leaking oil for later use.
3.4 roll cable insulation measurement and calibration of moisture:
3.4.1 the cable head shake table 2500V opening shake test, insulation resistance after passing tide.
3.4.2 since the end of the cable the next 100mm, cables, turnkey and tear off a few of the core paper insulated, put about 150 in cable oil, such as tidal oil will be suffused with bubbles and make a hissing sound (Figure 2-19).
Another method for burning method. Will be that the tide of insulated paper in fire, such as moisture, insulation paper surface will bubble up and the hissing sound.
Such as when he found the cable insulation with moisture should be removed piece by piece, until no moisture is obtained.
3.5 determination of dimensional stripped cable cover:
3.5.1 straighten cable: cable to flat, straightened within two metres of the cable ends, clean overlap 200mm. In the Middle center line for the Joint Center. Saw blade disconnect (see Figure 2-20), and then cement protection box below the base plate in the centre line.
3.5.2 cable socket according to figure the proper dimensions. Bandwidth-two-thirds clamp-solid steel (or 2mm turns of bare copper wire lashing three), peel off layer (or sheath). Volume 50mm from the layer break and strip Kaku, used a hacksaw and close to the edge of the clamp saw a ring of dark marks and a depth not exceeding one-second of steel belt thickness, then use the screwdriver to pry the steel tip, and then clamp with pliers, tear strips, blank repairs steel burrs to make it smooth (Figure 2-21).
3.6 set into the lead casing:
3.6.1 Strip after Strip, uniform baking using a blowtorch, get rid of the lead Pack on the asphalt paper, wipe clean with a cotton-lead package. Korean paper wrapped on the cable end, and lead into the casing.
3.6.2 stripping lead. According to the dimensions shown in Figure 2-21 and stripping lead. How to: in the lead pack with electrical forces carved a ring-shaped gouges, its depth not more than half the thickness of the lead Pack. Then use the electric knife from the circular trace to the end by two parallel gouges, 10MM space between two deep scars, which will lead from the end torn off with pliers (Figure 2-21), finally, lead Strip.
3.6.3 expanded lead. Expanding lead with Shun turnkey paper-wound direction of expansion lead to lead expansion into 45-degree angle, Bell, Bell no burrs to smooth and symmetrical.
3.6.4 stripping turnkey paper trumpet turnkey insulation on the edge of a piece of paper in oil-impregnated gauze wrapped 25mm wide five-storey, the last trumpet 5mm as the temporary layer. Then strip turnkey insulation paper and packing (not to damage wire insulation paper) and cables along with the half overlap core insulation paper covered with a layer of oil-impregnated gauze, distance from end of the connecting pipe length of one-second and 5mm.
3.6.5 install triangular wooden frame. Frame outside end from Bell 110~120mm with oil-impregnated gauze tie, and then bent into a three-core work, the gap width 50mm, to bend shall not be bent hurt paper insulation (Figure 2-22).
3.6.6 proof of lead, saw alignment cable core. Expanded lead Bell to the end by PB one-second 35mm reduction of the length of the casing (welding reduction 25mm), saw off the excess wire.
3.6.7 series took over. Length measured from the end three-core connecting one-second and 10MM remove the insulation paper (last two papers use hands torn off, so as not to damage the wire), gasoline cotton wipe clean and connecting wires, wire and pipe fasten and remove burrs.
3.7 demolition triangle frame and excluded moisture demolition triangle frame and the the core line Shang of oil dip with, tore to phase color paper, with cotton dip alcohol put core line wipe NET, then with prior heating to 150 cable oil from ends asked Center for to tide processing (from cable of Commission package at to Center to tide), then in Middle head following Pu good rubber cloth.
3.8 winding insulation. In the core line Shang with oil dip black paint across with along core line insulation paper winding of direction, to half overlap method package wrapped around insulation, and package flat even took over ends of space, full length package wrapped around 3 layer, then in took over and the took over to ends extends, package thickened insulation, thickened paragraph ends should package into tapered, the Department size see table 2-7, package wrapped around Shi must layer Layer package tight Kanehira, each package three layer coated once Silicon oil.
Increased core winding insulation dimension tables 2-7
Rated voltage dimension (mm)
(kV) l l1 φ1 φ L
6/6 30 L+160 PHI +10 connection
8.7/10 45 L+240 PHI +15 pipe diameter pipe length
Note: 1. Increased core insulation around black glass paint materials using oil immersion or PCE. When using PTFE tape, additional specifications around the lead casing and the insulation thickness can be reduced.
2. the material number rated voltage 8.7/10kV, conductor cross section 120mm2 the aluminium core cable connector, for example.

3.9 remove temporary gauze, dismantle the temporary gauze on turnkey and peel off the masking paper, from expanded lead on 100mm winds 8 oil-filled black paint across the belt and crammed into bulging lead mouth enclosed Kanehira.
3.10-lead:
3.10.1 move the lead casing to the Middle, making the decision to tap both ends of the lead casing, knocking into a cone, tightly wrapped in lead casing cable lead-Pack on it. Knock hard and not too heavy, in case the lead casing split fold, not knocking injuries lead package.
3.10.2 seal. The lead casing injection holes up, using a blowtorch, baking lead casing and the lead pack with fat powder (stearic acid) to remove dirt, then seal, seal, there are two: l) drop of lead. Using a blowtorch to seal evenly coated to lead pipes and lead Pack, using a blowtorch to seal into a paste, using cloth to seal after forming, with fat powder cooling decontamination, forming beautiful, surface treatment of Chlamydia trachomatis in no light. 2) cast lead. Heat the seal into a paste, then evenly pour the lead pipe on Cone, to a certain amount, forming with a blowtorch, and other practices with drops of lead.
3.11 pouring insulation adhesive:
After appropriate heat insulation adhesive (170~180) by the end with glue-pouring in lead casing, filled for the first time, adding the second the temperature at 60 , and gluing agent holes in the lid, seal firmly. While the second layer of the steel belt and lead package with seals, and used as a grounding. Ground wire sealing requirements are as follows: coated steel belt and lead lead up to 25mm wide and 30mm.
3.12 anticorrosion and installation of concrete protection box:
Brushing a layer of thermal insulation glue around the lead casing, then Korea wrap two layers of (tarred), brushing the outer surface layer of bituminous paint, intermediate head protection box flat on the cement with fine soil fill.
3.13 planted flags:
Middle head will be installed in trenches filled with fine soil, and then laying cement joint stakes, and out of the ground, as symbol.
3.14 try running the acceptance:
3.14.1 the first cable production has been completed, as required by the test Department pressure and test.
3.14.2 acceptance power no load operation 24 hours without exception the acceptance formalities, AC units. Submit change negotiations, product certification, technical information such as specifications, test reports, and running records.
4 quality criteria
4.1 project:
4.1.1 cable head pressure results, the leakage current and insulation resistance code requirements must be met.
4.1.2 cable head closed tight, and full, no bubbles, no oil leakage, no cracks. Cored wires tightly.
Inspection method: observation of inspection and test records.
4.2 Basic project:
Cable head good looks, smooth and wrinkle-free, glossy.
Inspection method: Visual check.
5 finished product protection
5.1 device upon opening the box, put in order in a porcelain dish, covered with white cloth, preventing debris from entering.
5.2 cable is completed, install now fill. When the delay to fill, cable head and wooden box protection to prevent smashing, touch.
6 quality problems to be noticed
6.1 roast lead packages, torch to simmer, so as not to damage the lead Pack and paper.
6.2 cable insulating paper cannot be damaged, in particular the tripod broke off caution when bending, not too hard, wrap insulation when not moving the wires back and forth, so as not to damage the insulation paper.
6.3 when the seal, wrist to be flexible, faster, so as not to damage the lead Pack and paper insulation.
Quality of 7 records
7.1 product certificate.
7.2 cable test report form.
7.3 equipment inspection records
7.4 compound test report form.
7.5 mutual inspection records.

7.6 change record of negotiation.