Monday, October 3, 2016

Unbonded prestressing tendon process

Unbonded prestressed tendons
1 scope
This technology is applicable to 8 degrees in Beijing area of post-tensioned Unbonded prestressed concrete structures for earthquake.
2 construction preparation
2.1 materials and equipment
2.1.1 production of Unbonded-wire and should be in line with national standards of the prestressed concrete steel wire strand (GB5223
185), of the prestressed concrete steel strands (GB5224-85) requirements.
2.1.2 the coating layer of Unbonded Tendons "special construction of oil", its performance, product quality indicators should conform to the standard Bureau of Hunan province on June 6, 1983, on July 1, 1983 the pilot "condition of Unbonded prestressed tendons with antirust grease lubrication technology" requirements.
2.1.3 Unbonded Tendons using low density polyethylene coating material (190 temperature, melting index for the 1.5~5 range).
2.1.4 has been completed the Unbonded Tendons quality requirements should conform to the Beijing standard of the Unbonded prestressed concrete structure system (BUPC) design and construction rules (draft) (DBJ01-7-90) in chapter II of part two 2nd. 2.5 requirement (see table 4-44). Unbonded steel wire, steel wire, dog leg is not allowed, see dog leg cut off. Wires should be long, no joints.
2.1.5 of Unbonded prestressed concrete structure with influenza a, b-type anchorage system structure, technical requirements, must comply with DBJ01-7-90 requirements proposed in chapter III of part two.
Construction of anchorage system as shown in figure a, and b 4-52~4-57.

Influenza a and b-type anchorage performance and condition is shown in table 4-45.
Usually steel wire beams is equipped with type a or b, strand was equipped with b-type.
2.1.6 supporting the tensioning device have an oil pump jacks, the technical properties as shown in table 4-46. Machine has a voltage divider (both hydraulic and springs), tension rods, anchor, etc.
2.2 operating conditions
2.2.1 tensioned concrete strength to meet the design requirements, General design strength of not less than 70%, a test report form.
2.2.2 Unbonded tendon compound and steel processing to complete.
2.2.3 anchor has inspection and acceptance.
2.2.4 tensioning equipment has been certified equipment is ready.
2.2.5 stretching parts of the scaffold and fence installation has been completed and inspected in accordance with operational requirements.
2.2.6 design made to Unbonded tendon tension, tension, elongation value, Unbonded tendons of laying and operation, to technical quality standards of disclosure.
3 operational processes
3.1 process:
Construction preparation of beams and formwork pitched non-prestressed rebar placement, lashing

Ends of Unbonded prestressed tendons placement, node installation on non-prestressed rebar placement, lashing

Unbonded prestressed arch, lashing hidden test collection of concrete pouring and tamping

Concrete curing tension ends



3.2 check patch no bond reinforced: no bond reinforced entry Hou, should timely verification reinforced of specifications, and size and number, by root check reinforced of outside package layer quality and the end Department accessories, on distribution has methyl anchor wire beam, should seriously check anchor Cup both inside and outside thread, and heading head shape size, and leak heading phenomenon,, and will positioning Rod twist into anchor Cup within, twist into depth see table 4-47. After checking correct can be classified and piled up. Coating damage of Unbonded tendons, with plastic repair.
3.3 mode reserved hole location: Zhang Laduan die outside, according to construction plans by Unbonded elastic wire, numbering, and drilling. Equipped with a anchor bar diameter for PHI 40, equipped with anchor bars b hole diameter for PHI 30.
3.4 installation of bearing plate: plate is set for Unbonded Tendons Zhang Laduan, installation should prevent tension due to bearing plate face tilted cylinder and plate perpendicular to each other and affect the normal tension. Vertical deviation of bearing plate as described in section 4.3.
Shop 3.5, the Unbonded Tendons: Unbonded Tendons usually configured with one-way and two-way curved configuration in two ways. Placement should be noted:
3.5.1 for assurance of Unbonded curve rise requirements, Unbonded Tendons sing with non-prestressed reinforcement configuration in the same direction at the same horizontal location (and support).
3.5.2 before placement, iron stool should be established to control the curvature of Unbonded tendons, generally every 2m a horse stool, stool height determined in accordance with design requirements. No horse in stool, direct lashing at the end of the muscles.
3.5.3 two-way curved configuration, you should also pay attention to the placement of the reinforcement sequence. Due to the reinforcement of the ups and downs of different heights, there will be two alternating pressure to the reinforcement. To avoid laying wear bars, must be made before construction of manual or computerized sequencing. Sequencing is the elevation at the intersection of Unbonded tendons (from the height of the plate from the end of the Unbonded Tendons epithelial) marked, taken on the intersection of the two elevations, a reinforced point in one direction Jun Gao respectively when the elevation is below instead intersects the tendons, this bar can be placed. According to this pattern to find placement order. In this order, finished tied at the end of non-prestressed reinforcement bars, putting the Unbonded tendons in your template.
3.5.4 the Unbonded Tendons below should be laid in raceways, avoid down Unbonded tendon tension force, resulting in under the wire and tube bending and breaking of concrete.
3.6 end of node installation:
3.6.1 swine anchorage system of tension-side installation: gently into the bearing plates reserved for plastic protective sleeve hole to prevent pouring concrete, cement slurry into the socket screw, and tension. And according to design requirements, determine the embedded depth of anchor glass. In order to ensure its correct position can be achieved by positioning the connecting rod. Position the connecting rod length is 160mm, with two end threads will be screwed into the socket at one end (its provisions into lengths as shown in table 4-47), pushing inside the wire heading, at the other end fixed in end mode. By measuring the positioning Rod dew in mode to check the size of anchor Cup embedded depth. In the process of locating operations, embedded depth of anchor Cup to be checked one by one, checking, and strictly control the positioning Rod exposed. Exposed dimension tolerances of the connecting rod as shown in table 4-47, exposure size calculated figure 4-58.

Lr=A-B-ΔL+30-C

Lr-connecting rod in an exposed-end model external dimensions (mm);
A--connecting rod length;
B-the fixed length of the connecting rod is screwed into the socket:
Δ calculated after L-a Unbonded tendon tensioning elongation value (mm);
C-side template thickness (mm).
3.6.2 swine anchorage system installed on the fixed side: according to the design requirements of the elevation, will end seven-hole anchor plates held together by wire prestressed tendons or muscles attached and in its configuration with spiral reinforcement to enhance local bearing strength of concrete. Heading should be flush with the anchor plate snaps, wire, does not allow random phenomena.
3.6.3-anchorage system installed on the tension side: when installing, the Unbonded Tendons from the bearing plate reserve holes out, its perpendicular to the bearing plate sections with a wire tie, beams exposed length inside of the end die straight section length see table 4-47. When installing recessed concrete with tensioned anchorage side, the plastic surface oiled to prevent bonding. While prior to pouring concrete, outsourcing will be provided on the inner surface of the bearing plate of prestressed tendons around the pipe along the cut, tension and then remove it.
3.6.4-anchorage system-end of installation: fixed according to the design in the template, and configuration with spiral reinforcement. Fixed by steel wire end need to be disseminated, steel arch Board header.
3.7 fastening: check the protective plastic sleeve without damage. Soft plastic and tie both ends to the protective sleeve on the Unbonded tendons, and elevation according to the design of Unbonded tied to end non-prestressed reinforcement or additional muscles, when binding, Unbonded Tendons should be protected with the socket overlapped, and perpendicular to the plate, in order to facilitate smooth pulled out of the socket when the tension plate end.
3.8 arch: after you tie the non-prestressed reinforcement, construction drawing design of Unbonded prestressed tendons in number position, Unbonded, reinforced curved high point horse bench locations are secured. Reinforced arch quality requirements as detailed in table 4-47.
3.9 concrete pouring and tamping:
3.9.1 the Unbonded Tendons assemblies after the placement is completed, by the construction unit, quality inspection departments, in conjunction with the joint hidden design unit test charge, confirmed only after pouring concrete.
3.9.2 concrete pouring, forbidden step stool and prevent touching stroke, sure Unbonded beams and anchor location accurately.
3.9.3 Zhang Laduan and end serious vibration should be concrete, no leakage, and avoid the voids, its density, and is strictly prohibited to touch the tension-side plastic sleeve, avoiding impact tensioning sleeve off violations.
3.10 alpha anchor tensioning process:
3.10.1 construction preparation: tension to remove location link, end templates, cleaning, scaffolding and a protective barrier.
3.10.2 equipment installation: the tension rod is screwed into the socket, installing Jack, tension lever lock nut (must buckle). Jack installation location should be on the same axis with Unbonded tendons, and perpendicular to the plate. Does not meet requirements, available pads adjust pad on the end surface of the support frame.
3.10.3 tension: switch on pump, pressure. When the hydraulic expression to 5MPa, stopped pressured, adjust the fuel tank position, continued to pressure until the desired tension value is reached, turn off the pump power, stop giving oil pressure. And then anchor glass cleaner for cleaning outside, screw on the nuts, connect pump again, and pull to tension, tighten the nut.
Electric oil pump under pressure, to control the speed, to control the hydraulic oil time cannot be less than 0.5min.
Tensioning process, when the fracture occurs when individual wires, can reduce tension. But the number of faults should not exceed 2% of the same total number of prestressed tendons, multi-span continuous two-way slabs, calculate the same section by each.
3.10.4 measuring record: in order to check the pre value during stretching process, should be graded a random record Unbonded tendon extension value. Normally each takes oil pressure reading to 10MPa multiple is appropriate.
Start to tension, Unbonded Tendons placed in plastic sleeve is free, to use a certain tension tightening, so it is difficult to measure the tension of the starting point, that is, of zeros of Unbonded prestressed tendons stress, which in theory is to measure muscle elongation value of tag.
0 points of determine method is: will Jack pressure to 10MPa, in Jack Shang note mark, as measurement no bond reinforced elongation value of starting points, see Figure 4-59 in the a, points, then gradually increased pressure to 20MPa, until reached requirements of last pressure value, and group records each level pressure Hou reinforced of elongation value, can obtained Figure 4-59 in the b, and c, and d points. In the elastic range, elongation proportional to the stress, so that the points in Figure 4-59 in a straight line and extend the horizontal axis in O1, O1 is ask zero, unbounded bundles total elongation values should be δ L1+ δ L2.

Elongation value is 10% when the measured value of extension of the calculation above, should be studied.
Elongation elongation when the value 10% value is greater than the calculated measured, should stop the tension, check that the meter is in error and, if necessary, it should check and calibration.
When the observed elongation elongation values less than the calculated 10%, should identify the reasons may continue to pressure relax or Unbonded beams, a second tensioning, but neither tensile stress over Unbonded tendon tensile strength of standard 75%.
3.10.5 anchorage and dismantling equipment: tighten the nuts, but gradually oil, relaxing the Unbonded tendons and remove Jack. Oil should slow in operation, shut off power, after moving the position of valve oil return to, and then oil the piston back, dismantle the jacks.
Socket submerged errors causing tension to meet the design requirements, glass exposed face is too long (greater than 50mm) or too short (less than 20mm), add nuts or socket connections should be taken to anchorage.
3.11-anchor tensioning process:
3.11.1 construction preparation: before tensioning plate surface should be cleaned, stripped of the exposed strands (wires) outsourcing of plastic casing, check them one by one to anchor, no rusted anchor. And one by one, measure the length of exposure of the Unbonded tendons, recorded as the original length before tensioning.
3.11.2 tension: switch on pump, pressure, when the pressure reaches 2.5MPa, stopped pressured. Adjust Jack's position, and continued to pressure the tension until it meets the design requirements. When Jin trip meets no tensioning required extension value, stretching to stop in the Middle, as a temporary anchor, back Jack tour, and then a second tensioning. Both the tension and stretching speeds to be consistent on both ends, the pressure difference should not exceed 10MPa.
3.11.3 pushing and removal of equipment: there are two ways, automatic hydraulic pressure and spring pressure. Hydraulic pressure is used to manually pump top pressure pressure. When stretching to control stress, stopped pressured, under the required pressure, using hand pressure pump top pressure, pressure 30MPa, pushing and Jack slowly back to oil, finally dismantled tensioning devices. By spring pressure, when tensioned control stress, you can return, due by spring pressure is anchored, anchor neck-in large secondary tension should be taken. The second tension, you must remove the top pressure equipment, put on the supporting frame, Jack supports on the members. Tension jacks and anchorage must be kept on the same axis, pressure should be the design stress values. Using open type gaskets, pad in Anchorage and bearing plate gaps.
3.11.4 measurement records: tensioned Unbonded Tendons exposed length measurement again after subtracting measures before measuring the length of income the difference between the actual elongation values for which calculation length, its deviation is +10% or 5%.
3.12 anchorage zone of protection must be adequate rust protection and fire safety measures to prevent moisture to enter, rusted anchors or prestressed reinforcement.
There are two common approaches:
3.12.1 enclosed reinforced concrete ring beam outside anchorage. Anchorage for influenza a, should oil the gun through the socket within the ducts to the protective plastic sleeve and enough lubrication antirust grease fill (grease ducts out from another), to outsourcing of reinforced concrete. B type anchor, it should first be exposed the Unbonded Tendons cut, leaving only 20cm, and then spread its bending and pouring concrete.
3.12.2 anchor embedded in concrete structure in advance until after tensioning, cutting away the excess of Unbonded tendons (to abrasive saws, not arc or oxy-acetylene flame), epoxy mortar used up.
3.13 Unbonded Tendons-tension after the prestressing form should be filled in, operation signatures for future reference. Archive: high strength steel wire or steel stranded wire, anchor clamps factory certificate and retest report of mechanical properties of steel; Unbonded prestressed reinforcement and anchoring clamp certificates; supporting sensors, pump Jack calibration test; tensioning elongation of Unbonded records.
4 quality criteria
4.1 project:
4.1.1 production of Unbonded steel wire and strand to be in line with national standards of the steel wire for prestressed concrete
(GB5223-85) and of the prestressed concrete steel strands (GB5224-85) requirements.
Inspection method: quality inspection certificate and test report.
4.1.2 the Unbonded Tendons coating, coating material shall conform to the provisions of the relevant standards of quality.
Inspection method: quality inspection certificate.
4.1.3 use of Unbonded prestressed BUPC swine anchor system, b-type anchorage quality shall conform to (DBJ01-7-90) the relevant provisions of chapter III of part two. See 4-45.
Check amount: according to construction specifications Chapter Sixth 6th. Article 2.12 extract specimens.
Inspection method: check the anchor factory certification and inspection, hardness inspection, static load anchoring tests report.
4.1.4 the strength of concrete provisions must comply with the design requirements and specifications.
Inspection method: check the same condition curing concrete block pressure test report.
4.1.5 anchoring phases stretching tendons neck-in end, swine anchorage is not more than 1mm type b, anchorage is not more than 5mm.
Inspection method: examination of prestressing records.
4.1.6 heading strength shall not be less than steel standard steel strength of 98%, its dimensions and appearance quality meet the requirements.
Inspection method: check the heading test reports.
4.2 Basic project:
4.2.1 each beam of Unbonded prestressing anchorage actual prestressed value with design value is the relative tolerance to ± 5%.
Inspection method: examination of prestressing records.
4.2.2 broken wire and slide number should be no more than one section of wire 2% of the total number of roots.
Check amount: total inspection.
Inspection method: comprehensive observation or examination of prestressing records.
4.3 allowable deviation shall conform to the requirements in table 4-47.
Unbonded Tendons end node installation and beam deviation table 4-47
Tolerance (mm) method
End-node plate vertical deviation of ± 3
Screwed into the socket length
Anchoring-link
Show template dimensions not less than 20
+10
-5
Measurement

Unbonded Tendons-tension-side exposure of dimensions not less than 600
Bar in tension-side template vertical plate on the inside of the curve length of the straight section not less than 300
Spacing
Unbonded tendon control point rise errors
Standard deviation of 20
± 5
± 30 Visual horizontal even vertical
Entrance of Unbonded size detail

A not less than 75
B not less than 300
Measurement
 finished product protection
5.1 the Unbonded Tendons shall be classified according to different specifications into bundles, reels listed stacked neatly. When air storage, need to cover ponchos, the following should be added to wood to prevent anchorages and corrosion of Unbonded tendons, no crash crushes stacked finished products, avoid damage to the plastic sleeve and anchor, the anchor fixtures used for tensioning required coated oil in indoor storage, to prevent rusting.
5.2 the Unbonded Tendons during transport should travel light light discharge, no fall flip and sharp surface damage of Unbonded tendons and accessories. Slings wire rope required plastic pipe, to avoid damage when handling the Unbonded Tendons plastic sleeve, if shall promptly plastic repair of damage, its winding rubber lap length 1/3 width.
6 quality problems to be noticed
6.1 Unbonded prestressed steel wire, steel wire, dog leg is not allowed, see dog leg cut off. Each wire, steel wire should be long, no joints.
6.2 the Unbonded Tendons selection, the muscle length is less than 24m, and generally choose wire harness is greater than 24rn, with an optional strand.
6.3 the Unbonded Tendons the design stress σ con control for Prestressed reinforcement tensile strength of standard 70% and, if necessary, can be increased to 75%. In order to reduce the relaxation effects of prestressed reinforcement and construction method of hyper-tension method can be used, but the maximum tensile force shall not exceed the standard tensile strength of Unbonded Tendons 75%. Tensioning method usually uses a hyper-tension, or 0 10% σ con, or secondary, σ 0 100% con is relaxed to 0, plate pressed again after pulling 0 100% σ con
(Con for design stress σ).
6.4 Unbonded curve when you configure both ends or longer than 24m tension method, stretching speed two devices should be consistent.
6.5 Unbonded tendon tension should be carried out according to the design requirements, such as when there is no special requirement, followed by stretching.
6.6 in order to avoid large-span prestressed cast beam top during an additional bending moment bearing and the column constraints impact beam bearing sliding hinged steel bearing can be used, as described in Figure 4-60, after treating the tendons and, buried parts of bearing and beam welding with concrete pouring qi.

Figure 41-steel bracket, 2-column

7 quality records
This standard shall meet the following quality records:
7.1 the strength of concrete test piece test report form.
7.2 Unbonded PC wire and strand the quality certificate.
7.3 mechanical properties of PC steel wire and strand test report form.
7.4 non-bond prestressed anchor certificate and inspection records.
7.5 heading test reports.
7.6 tensioning equipment calibration record.
7.7 for Unbonded Tendons laying hidden inspection records.
7.8 record Unbonded prestressing.
7.9-end strength of concrete test piece test report form.
7.10-side concrete cement factory certificate.

7.11 the design requirements of other technical information.
Because of the war, many people become homeless. I can't do it well. Please help me.my PayPal is xhhnet@163.com.

No comments:

Post a Comment