Aerated concrete panels installed
1 scope
This technology is applicable to general
industry and civil architecture wall, partition wall with aerated concrete
panels installed.
2 construction preparation
2.1 materials and equipment:
2.1.1 aerated concrete panel size: length
2.7m,3.0M,3.3M, width 0.6m, 10cm, 15cm. Product performance meets the design
requirements.
2.1.2 cement No. 325 and more send ordinary
Portland cement or slag silicate cement.
2.1.3 stones: 0.5~1.2cm fine stone.
2.1.4 coarse sand: average particle size
not less than 0.5mm.
2.1.5 sand: sieve before use, average
particle size 0.25mm, sediment is not 33%.
2.1.6 107 adhesive, emulsion.
2.1.7 main equipment: mixer, wheel saws,
with gray iron, trolleys, drays, spade, size of the transported gas block
buckets, hose, brooms, brushes, pink bag, iron trowel, hammer, holding Board,
drills, wood wedges.
2.2 operating conditions:
2.2.1 according to the stud, depth size,
aerated concrete panels with abrasive cutoff saw cutting. Floor dimensions
minus the height of at 150mm.
2.2.2 short cord out of a corner of the plate
to fix it, wash the dust of the tear, then 207 glue (water: rubber =4:1), and
1:1:3 (cement plaster: aerated concrete powder) with a good proportion, then
add the above 107 glue mixing, membrane.
3 operational processes
3.1 process:
Elastic line → addressing Strip
length and width dimensions → clean installation location upper end → concrete →
Spring mounting block → plate
install plate
3.2 shell line: according to the design
requirements of the drawing size, wall or exterior wall line of position play.
3.3 addressing Strip length and width
dimensions: according to the requirements of the design drawings, annual and
width of the handle, wall Board to adopt mosaic method of external wall
clearance dimensions (width and height) to splice or cut. Splicing steel mosaic
on the rack. First stitching to clean up, removing dust, sweep with wool dipped
in water with a little moist. Operated on external coated in an adhesive strip
on the mosaic surface, thickness of 2~3mm, forced to squeeze by two splice
plates, seam-sealed. Mosaic extrusion adhesive scraping with a knife outside
the net and on foot to check straight and square. Installed height should be
higher than the net high 3cm, easy to install using the wedge will be fixed at
the lower end tight.
3.4 clean installation position the upper
and lower ends: clean the upper and lower ends of the strips will be installed,
short of cord angle fixed firmly. Then install location top bottom clean on the
concrete, bottom of the concrete damp with water.
3.5 concrete: according to the design
drawings shown concrete partition Board location. High 12cm, inner casement PU
2 φ 6 bar by C15 concrete, it tastes good and smooth, as concrete has a certain
value, then install the wall plate.
3.6 play Board mounting block line: in the
installation location on the block line: doors and Windows line of position
play.
3.7 installation plate:
3.7.1 prepared adhesive weight ratio of
cement: sand: 107 gum: water =1:1:0.2:0.3. Preparation is to cement and sand
dry mix, then add water laced with 107 glue mix. Adhesive should be used with
mix, parking time does not exceed the 1h, tool should be promptly cleaned after
use.
3.7.2 installation Shi first in article
Board of top and the a side, cleaning clean, Yin water, with surgery coated
scraping adhesive, will article Board erected erect, end with crowbar pad up,
helped stability, makes Board bottom and the side had alignment wall sideline,
again with supporting Board find are find straight, adjustment Hou forced to
side extrusion, makes article Board contact surface of adhesive uniform
consistent, last with crowbar from bottom pry tight, makes article Board top
and floor bottom advance scraping of adhesive parts coincide, and stick tight,
lower timely with wood wedge wedge tight, C15 concrete wedge stiff bean twist
plug the gap between tight, conservation of 3D will wedge down, and twist bean
stone concrete.
3.7.3 installation plate the contact
surfaces should be brushing adhesive to facilitate bonding.
3.7.4 of the connector is installed when two
adjacent strip joints should be staggered up and down position.
3.7.5 plug door holes, reserved 2cm
allowance width to each side of the doorway.
3.7.6 the door frame before installation,
on the installation location should be aerated concrete wall drill a deep
100mm, 30mm diameter hole, blowing dust, wet with water, again with the same
diameter and long round wood stained with gum into the holes in the rubber mix
for 1:2:0.5= emulsion: cement: water (by weight). Hole spacing less than 50cm,
when you install a wood door frames, wood screws getting started with embedded
on a log.
4 quality criteria
4.1 project:
4.1.1 use of raw materials should comply
with the design requirements and the provisions of the code.
4.1.2 performance, specifications,
location, methods must comply with the design requirements. Deformation and
damage-free.
4.1.3 plate installed with pea stone
concrete, accurate measurement of mortars and adhesives, pouring, uniform brush
density. Careful conservation, strength shall meet the design requirements.
4.2 Basic projects: joint construction,
component location, anchoring methods should comply with the design
requirements and installation stable and secure and straight.
4.3 allowable deviation, as shown in table
4-43.
Aerated concrete panels installation
tolerance table 4-43
Project tolerance (mm) method
1 3 adjacent surface flatness 2m on foot
and wedged feeler Gage check
2 elevation of 5 2m supporting plate check
5 finished product protection
5.1 finished hoisting Special lifting
device should be used, or use a hose hanging rope light with care.
5.2 code support to obtain a duo high and
not more than 10 blocks to prevent rain, exposure, the side pieces of the
mosaic, in case the force open.
5.3 transport increased protection after
installation to avoid collisions.
6 quality problems to be noticed
6.1 construction of aerated concrete wall
of reinforced concrete with time, location of the roof should be napping,
compacting concrete has been poured, and strengthen conservation.
6.2 installation uniform coat of adhesive
to the walls, the bottom wedge rolling back tight, to increase the pressure.
6.3 check carefully when installing to
prevent damage no patch panels on the wall.
6.4 installation to seriously look for
first Board, prevent the installation joint is not normal.
6.5 seam out of excess adhesive should be
blown away in time.
7 quality records
This standard shall meet the following
quality records:
7.1 aerated concrete panels factory
certificate.
7.2 installation quality of aerated
concrete inspection and assessment records.