Prefabricated balconies, rain cover,
channel installation
1 scope
This technology is applicable to General
residential buildings prefabricated reinforced concrete balconies, rain cover,
channel plate components installation works.
2 construction preparation
2.1 materials and equipment:
2.1.1 widget: prefabricated reinforced
concrete balconies, rain cover, channel model, quality should meet the
requirements of the Board. And should have the widget factory certificate.
2.1.2 cement: No. 325 more than Portland
cement and ordinary Portland cement and slag Portland cement. Factory
certified.
2.1.3 sand, stone: sand or coarse sand
particle size 0.5~3.2cm stones.
2.1.4 concrete admixtures: early-strength
admixture, superplasticizer, etc should be consistent with the relevant
provisions of the standard. Content determined by the laboratory.
2.1.5 electrode: grade ⅰ E4303
electrode for steel welding, welding ⅱ E5003 or E4303 for
steel rod, factory certified.
2.1.6 anchor reinforcing bars:
specification, variety and size requirements are commensurate with widget sets.
2.1.7 wire: wire, 20th.
2.1.8 supporting materials: 100mmx100mm
wood stud or tool-steel pillars, 50mmx100mm wood Rod 50mm Atsugi base plates,
wooden wedges and nails.
2.1.9 main machinery: crowbar, hooks,
slings, clasps, steel wedges.
2.2 operating conditions:
2.2.1 installed before the widget and
pop-up widget size overhang on the walls and on both sides of the line of
control border, checking level.
2.2.2 cut and straightened the balcony edge
welded connction and embedded within the corridors ring ribs.
2.2.3 check balcony anchorage reinforcement
of cantilever beams and boards on both sides of the aisle out of the diameter
and length of exposure in accordance with design requirements and left bars
straighten.
2.2.4 Installing balcony, rain cover, MCP
brick walls with cement mortar or concrete wall and catchy elevation leveling.
2.2.5 balcony, rain cover, temporary
support channel plates should have sufficient strength and stability. Put
scissors at the pillar, wall jambs and horizontal tie firmly. Before installing
should copy the temporary support to the top flat, wedge a nail and plate
nailed at the bottom. When lifting the upper balcony or walkway, following at
least three layers of support.
3 operational processes
3.1 process
Pulp adjust welding → → → → hoisting poured
concrete
3.2 pulp: install components before his
screed the walls clean and water cement ratio is 0.5 grain slurry with a layer,
then installed, to ensure that members and leaving no gap between the wall.
3.3 lifting: lifting component when making
each hook load lifting rope angle should not be less than 45 ° with the plane.
When components hang suspended from slightly higher than the flat on the floor,
place unit on the wall on the sideline, and then according to the line size
overhang, determine the wall gently firm (such as design requirements, pressed
into a wall not less than 10cm), pick out the parts placed on the temporary
support.
3.4 adjustment component dislocation
spotted when using crowbars pad gently move out of wood, adjust the components
to the correct location. The layers already installed balcony, channel up and
down vertically, horizontally straight, consistent elevation.
3.5 welding anchor bar: the component in
place should be reserved on the inner edge beam ring ribs to straighten and
beam reinforcement. Lateral beams protruding bar should also lap welding anchor
bar, anchorage reinforcement type, size, length and length shall meet the
requirements for design and component standards set. Electrode types should
comply with the design requirements, double-sided weld, weld length ≥ 5 times the
anchor bar diameter. Weld quality inspection in line with requirements, go
through the preflight procedures. Anchor bar anchor into the wall or in a
circle, as shown in Figure 4-51.
Figure 4-51
3.6 concrete: a balcony overhanging welded
steel finish, inner ring ribs and ring beam reinforcement through the balcony,
and inspected the hidden check formalities, and ring beam pouring concrete at
the same time. Prior to pouring concrete, die within the clean water the wood
template should run mode, dynamic reinforcement of vibrated concrete pay
attention not to touch, vibration after compacting, followed with a wooden sock
erase beam surface (pay attention to the upper surface of the beam elevation
lines). Channel installation joints should be uniform, Board templates, tags
should be strong, sew with fine stone concrete, vibrating compaction, concrete
strength grade to meet the design requirements.
4 quality criteria
4.1 project:
4.1.1 lifting the concrete strength of the
Widget, you must meet the requirements of specification for design and
construction.
Type, location, point 4.1.2 component
anchoring must comply with the design requirements and no damage.
4.1.3 prefabricated balconies, rain covers,
walkway paving mortar must be dense at the bottom, without pores. Channel width
gap between panels to meet the design requirements.
4.2 Basic project
Anchorage bar lap length should comply with
the requirements of 4.2.1, welds smooth surface without cracks, dents, welding
tumor, pores, defects such as ash and undercuts.
4.2.2 balconies for each line should be
aligned with the above and below the balcony slab edge.
4.3 allowable deviation, as shown in table
4-41.
Table 4-41
Project tolerance (mm) method
Plaster 5
Don't plaster 3
Horizontal deviation of 10
5 finished product protection
5.1 components overlap when stacking wood
should be added, to make the rings will not be crushed, wood thickness should
be not less than 90mm, and upper and lower wood should be vertical. Piling yard
should be flat and solid. Stacked no more than 10 blocks each component.
5.2 cut embedded tick embedded iron and
steel parts, damage components.
5.3 transport and installation process,
exposed steel bars shall be arbitrarily cutting components.
5.4 when the component is installed, not
chipped brick walls or concrete walls.
6 quality problems to be noticed
6.1 installed: temporary support on top of
cement mortar and screed must be on a level surface.
6.2 position is inaccurate: the
installation must be according to the line of control and the elevation is in
place, if any deviation should be adjusted in a timely manner.
6.3 bearing false: formation of the screed
should be noticed, installation should be watered pigment cement slurry, still
pore is installed, using dry real hard mortar.
6.4 anchorage reinforcement length and lap
welding does not meet the requirements: because any bend off balcony exposed
steel bars, which anchoring length is not enough. Anchorage used lap welding,
the weld on both sides should be used, it seems sometimes to one-side welding,
resulting in anchorage or welded length is not enough.
6.5 anchorage bars are not into a wall or
beam: when installing components position is not accurate, anchoring bars and
concrete walls to stagger. Lifting should be according to the position line in
place.
6.6 balcony not vertical, channel up and
down: the main reason is that no line in place by location when you install.
6.7 seam seepage under the balcony, MCP: as
there are no serious waterproofing treatment. After installing shall keep the
outside seam 3cm wide pad scrape pulp, waterproof according to the design
process. Gap between the channel plate must be of fine stone concrete
compacting.
7 quality records
This standard shall meet the following
quality records:
7.1 component certificate.
7.2 steel factory certification or
inspection reports.
7.3 steel mechanical performance test
report.
7.4 tensile test for welded joint report.
7.5 cement factory certification and test
reports.
Sand 7.6 test report.
7.7 welding certificate.
7.8 bar hidden inspection records,
component installation inspection records.