Installation of stairs, rest and chute
1 scope
This technology standard used in building
prefabricated reinforced concrete stairs and chute installation works.
2 construction preparation
2.1 materials and equipment:
2.1.1 reinforced concrete precast stair
break, time sheet, single-flight stairs beam, waste and other components of the
model, specification, quality, the design requirements, with a factory
certificate.
2.1.2 cement: No. 325, Portland cement and
ordinary Portland cement and slag Portland cement.
2.1.3 sand: sand.
2.1.4 fine stone: size 0.5~3.2cm.
2.1.5 steel: flat outline specifications.
40mmx6mm, angles ∠ 50x6mm specifications.
2.1.6 electrode: E4303, to have a factory
certificate.
2.1.7 main machinery: crowbar, clasp,
horns, hooks, slings, steel wedge, water change, horizontal hanging beam,
chain, etc.
2.2 operating conditions:
2.2.1 components piling yard should be a
solid formation, stacked pads when water close to the hook, wood thickness than
the hook, and close to the hook. Wood, put it on the same vertical line.
2.2.2 quality checks before lifting the
stair components, members who do not meet the quality requirements shall be
used, and does not meet the requirements of component defects visible marks.
Common identification and design units, to take measures to handle the
negotiations, and after strengthening into a patch, can be used.
2.2.3 advance eject treads, resting on the
wall plate, stair elements, such as beam lines, elevations and control up and
down flights of stairs a horizontal distance and elevation to avoid when
installing the treads, supporting long enough or the support length too short
without it.
2.2.4 under first run, first floor stair
tread the bottom of the casting section and elevation should comply with the
design requirements of the drawing. Before you install the treads, must be
installed in concrete strength of cast beams.
2.2.5 template for concrete walls set aside
resting boards and stair hole cleaning and filling mortar by elevation.
2.2.6 building Board wall concrete strength
4MPa.
2.2.7 all components embedded parts removed
in advance on Lomond, mortar and other remnants of embedded parts and surfaces
clean.
3 operational processes
3.1 process:
→ Install the rest of mud water board welding crack → → → → install stair
safety chute
3.2 water the mud; rest plate should be
installed with the install in reservation location poured heavy cement,
water/cement ratio is 0.5. And ensure rest and wall contact density.
3.3 Installing the resting plate: first
check the installation location and elevation lines, installation sheet resting
one end of stretcher slings should be higher than the other, so that he could
rest tilting insert bearing hole. Slowly drop the rest Board lifting at the
installation location, safe and after checking the surface elevation and
location as per drawing requirements, with a crowbar and struck, equal to the
size of both ends of the unit into the bearing.
3.4 stair installation: when installing a
stair, by lifting one end of the sling chain adjustment on length DrawString,
stepping surface level. Resting on the support surface water wet cement slurries
and water/cement ratio is 0.5, support contacts close. Lax support when there
is a void, to use iron wedges leveling, and density of cement mortar impaction.
3.5 welding: stair installation after the
correction, according to the design drawings in a timely manner, with
connection plate (size not smaller than the drawing specifications) flight and
rest of embedded iron parts of surrounding weld, weld should be full, as shown
in Figure 4-50.
Figure 4-50
3.6 crack: each floor stair installation
finished, should be promptly break plates at both ends and the space between
the wall formwork concrete. In-mould cleaning, concrete C20 fine stone
concrete, vibrating compaction, and conservation.
3.7 chute installation:
3.7. more than 1 storey brick-concrete chute
mounted on the inside corner, generally every layer break plates after
installing or loading chute. The chute risers with connection plate welded
plate on the upper and lower end embedded iron parts, welding firm. Vertical
plate end plate joints with cement mortar block it. Central chute riser
embedded parts and walls embedded iron welding.
3.7.2 high-rise structure of rectangular
precast concrete chute, generally located at the stairs outside, with the
construction schedule for installation of floors.
3.7.3 chute lift on the next cutting chute
and catchy, lining up the temporary rings after grappling with the main
structure.
3.7.4 by checking the location is accurate,
straight up and down after no dislocation, welding can be carried out. Garbage
between the road and the main structure, between the chute and chute of
embedded iron parts, by binding of metal welding firm.
4 quality criteria
4.1 project:
4.1.1 hoisting structure concrete strength
must comply with the design requirements and the provisions of the code.
Type, location, point 4.1.2 component
anchoring must comply with the design requirements and no damage.
4.1.3 joints (joints) of concrete or mortar
must be accurate measurement, pouring dense and serious conservation should be,
which must meet the design requirements or provisions of the code.
4.2 basic item: connection joints weld
length shall conform to the design requirements, weld surfacing, no dents,
welding, and joint crack and blowhole, slag and the undercut.
4.3 allowable deviation:
Stair installation allows distortions in
the garbage
Offset to 10MM
Elevation 5mm
5 finished product protection
5.1 flight, rest should be taken forward
lifting, transport and stacking. When components of transport and stacking,
wood should be placed around the rings, and above the rings, and alignment.
Chute straight vertical stacking.
5.2 piling yard should be flat and solid,
the following Foundation Board. Stair duo pieces should not exceed 6, resting
Board duo of not more than 10 pieces each.
5.3 stairs once installed, will still be
protected in a timely manner to avoid construction of step-edge damage.
5.4 installation when resting boards and
stair, not collision brick or concrete walls on both sides.
6 quality problems to be noticed
6.1 flight support bad: the main reason is
false or lap support contact long enough. Install rest time to proofread the
elevation, in addition to proofreading elevation when installing the stair, a
diagonal length should also proofread the stair.
6.2 the stair set: mainly due to improper
operation, install without pulp, put floating shelves, after you install the
alignment fails to crack. Should be installed strictly in accordance with
design requirements water slurry, filling in time after installation.
6.3 welding does not meet the requirements:
Member connections only use short bar ends of spot welding, affect the overall
performance of the structure. According to the design requirements, by binding
of metal around the welding firm.
6.4 resting Board with a tread surface Cha
level does not meet the requirements: the main reason comes to flat line,
installation elevation does not meet the design requirements. Install rest
panels should pay attention to height and horizontal position accuracy of the
line.
6.5 junk not straight and trash mouth
position do not meet design requirements: installation not in strict accordance
with the design requirements the elevation in position and alignment.
6.6 flight about the reverse: be aware of
when installing handrails embedded parts location.
7 quality records
This standard shall meet the following
quality records:
7.1 component factory certificate.
7.2 cement factory certification and test
reports.
7.3 test reports for sand and stone.
7.4 welding certificate.
7.5 pre inspection records.