Operating instructions ------ closet, hanging cabinet and fixed furniture installation

First, the material requirements
1. Wall cabinet, hanging cabinet wood products processed by the factory or semi-finished products, wood was not more than 12% moisture content. Processing of the box and the fan should approach the model, the quality of verification, the need for product certification.
2. Other materials: preservatives, plugs, wood screws, handles, locks, touch beads, hinges according to design requirements of the species, specifications ready.
Second, the main equipment
Electric welding machine
2. Large planer, two shaver, small plane, cut planer, wood saw, ax, flat shovel, wood drills, tap, screwdriver, steel level ruler, chisel, steel file, steel ruler.

Third, operating conditions
1. Structural engineering and related closet, hanging cabinet structure Siamese has been installed with wall cabinets and hanging cabinet conditions, the level of indoor elevation has been.
2. Wall cabinet frame, the fan in the field after the timely processing of products against the wall, paste, the top surface should be painted anti-corrosion coating, the other side should be painted with a base oil, and then classified code should be flat, the underlying pad level, Ventilation, should not be stored in the open air.
3. Wall cabinet, wall cabinet and fan box, before installation should check whether the channeling angle, Alice, bending, wall crack, if the above defects should be qualified after repair, and then assembled. Hanging cabinet steel skeleton should check specifications, there should be modified deformation after installation.
4. Wall cabinet, hanging cabinet frame installation should be carried out before the plaster; fan installation should be carried out after plastering.

Fourth, the operation process
1. Process flow
Finding → Locating the frame → Installation of the wall → Wall cabinet, partition, fulcrum → Wall (hanging)
Hardware installation
2. Line positioning: plaster before the use of indoor uniform elevation line, according to the design and construction plans requirements of the closet, hanging cabinet height and upper and lower mouth height, plaster thickness to consider the relationship to determine the appropriate location.
3. Frame, rack installation: wall cabinet, hanging cabinet frame and frame should be carried out before the indoor plastering, installed in the correct position, the two sides of each fixed frame nail 2 nails and wall wood nails nail, nails Cap shall not be exposed. If the partition wall is aerated concrete or light partition wall, the structure should be fixed according to the design requirements. If the design does not require pre-drilling Φ5mm hole, deep 70-100mm, and pre-embedded in the hole in the wooden wedge
Sticky 107 glue slurry, into the hole after the bond firmly fixed cabinet installation.
The use of steel cabinets, the need to install the location of the fixed hole fixed iron frame, the welding of solid pieces of the box.
In the frame, frame fixed, should be corrected, set square, hanging straight, check the elevation, size, location and then correct the accuracy.
4. Wall cabinet partition fulcrum installation: according to the construction map partition height position and the requirements of the fulcrum structure to install the partition support point (frame). The wooden fulcrum of the fulcrum, the general is the fulcrum of wood nails in the wall of wood, the concrete partition is generally iron-shaped iron or set angle bracket.
5. Wall (hanging) cabinet fan installation:
1) According to the installation position of the fan to determine the hardware model, the direction of the opening fan cut mouth, the general direction should be to open the right fan for the mouth fan.
2) check the size of the frame: the height of the frame should be on both ends of the mouth; frame width, should be on both sides of the frame, the next three points, and the corresponding part of the fan designated dash.
3) According to the crossed line for the first frame frame repair, so that box, fan left suture appropriate, test equipment and plan a second repair line, and draw the box, fan hinge slot position, pay attention to avoid the crossed Up and down the head.
4) shovel, tick hinge slot installation Hinge: According to the standard hinge position, with a flat shovel chisel out the hinge edge, you can tick the page slot.
5) Installation: The hinge should be pressed into the hinge of the fan first, then screw the fixing screw properly, and then fix the depth of the hinge slot, and adjust the gap of the frame fan. First screw a screw, and then close, check the box and the fan formation, no defects, meet the requirements of all the screws on the tighten.
Wood screws should be nailed into the full length of 1/3, screwed into 2/3, such as box, fan for the yellow Ying or other hardwood, the hinge mounting screws should be designated drill hole diameter of wood screws 0.9 times the diameter, eye depth 2/3 of the length of the screw.
6) Installation of the fan: first box, fan size and good, to determine the middle of the mouth of the seam, cut the depth of the mouth, after the planing slot, try to install the right time, first installed left fan.
6. Hardware installation: hardware varieties, specifications, the number required by the installation, installation, attention to the location of choice, no specific size operation according to the technical description of the end, the general model should be installed after confirmation of large area installation.

Second, quality standards
According to GB-50210-2001 Article 12.2.1 to 12.2.10 of the standard implementation.
1. Guarantee the project
1) box, fan varieties, models, installation benefits must meet the design requirements.
2) box, fan must be installed firmly, the fixed point to meet the design requirements and construction specifications.
2. Basic items
1) frame, fan cut straight mouth, planing surface smooth, flexible installation switch, no rebound and inverted Alice.
2) Hardware installation location appropriate, groove deep consistent, neat edge, the size is accurate. Hardware specifications to meet the requirements, the number of complete, wood screws tighten the level, the plug open flexible plug.
3) Cover the mouth of the box, pressure seam blanking the same size.
3. Allow the deviation items as follows:
Wall cabinet, hanging cabinet installation allowable deviation
Line item allowable deviation
Test method for width of stay seam (mm)
1 box is the side of the verticality 3 with 1m care board inspection
2 Diagonal line 2 Check the size of the box
3 box and fan, fan and fan contact height difference 2 with ruler and feeler check
4 box and fan, fan-to-mouth gap between the width of 1.5-2.5 with a feeler to check
Third, product protection
Wood products approach a timely brush oil, relying on the wall should be treated with brush preservatives; steel products should brush antirust paint, storage storage.
2. Installation of closet, hanging cabinet, is strictly prohibited collision plaster and other decorative surface of the mouth, to prevent damage to the finished surface layer.
3. Install a good wallboard partitions, not demolition move to protect the integrity of the product.

Fourth, should pay attention to quality problems
1. plaster surface and frame uneven, resulting in paste the face plate, pressure seam uneven: mainly due to the box is not vertical, surface layer flatness inconsistent or plaster surface is not vertical.
2. The cabinet is not firmly installed: embedded wood brick installation touch activities, fixed point less fixed with a nail, to the number of enough, wood bury buried solid.
3. Hinge uneven, loose screws, nuts are not straight, missing screws: The main reason, hinge groove depth varies, the installation screw into too long. Screw into the length of the operation 1/3, screw into the depth should be 2/3, shall not tilt.
4 cabinet frame and the hole size error is too large, resulting in the border and the side wall, the gap between the top and the frame is too large, pay attention to the size of the structure of construction holes, strict inspection to ensure the hole size.