1 Scope
    This process standard applies to the public and civil construction of plastic skirting board installation works.
2 construction preparation
    2.1 Materials and accessories:
    2.1.1 plastic skirting board products: According to the design requirements to buy, have a factory certificate, in line with the corresponding product specifications. Approach must be acceptance, specifications, color should be consistent with the purchase of samples.
    2.1.2 plastic "|" shape fixed card specifications: should be based on the skirting board height matching purchase.
    2.1.3 wood screws, self-tapping screws, plastic expansion screw plastic (generally used 4mm × 25mm).
    2.2 The main equipment: hacksaw, pliers, electric stove, screwdriver, portable electric drill, cotton wire, oil pan, glycerol and so on.
    2.3 Operating conditions:
    2.3.1 installation of plastic skirting board room and parts of the ground, the surface layer of the wall decoration construction have been completed, and complete the completion of the acceptance procedures.
    2.3.2 plastic skirting board and accessories have been matching approach.
    2.3.3 installation tools and materials ready. The installation part of the bomb level of the elevation line.
3 operating process
    3.1 Process Flow:
Pin → fixed points → drilling and security wedge → bending yin and yang angle skirting board → 安装 skirting board

    3.2 Spring Line:
    3.2.1 level skirting board skirting elevation line; according to the height of the plastic skirting board, according to the ground level to find the target skirting board high elastic horizontal line.
    According to the fixed card specifications, the depth of the card to determine the location of the fixed card in the card limit the height of the two screws stretch the card, and then press the fixed card spacing (usually 400 to 400 mm) 500mm) in the two horizontal lines on the line card fixed position.
    3.3 drilling and security wedge: According to the designated fixed card position, fixed in the horizontal line with a hand drill hole, the hole diameter of the smallest 10mm, the depth of the shallowest 30mm, the logs wedge adhesive into the hole, and And the wall trim.
    3.4 bent yin and yang angle skirting board:
    3.4.1 According to the length of the sides of the skirting board at the yin and yang angles, the molds of wood or other materials shall be machined.
    3.4.2 according to the size of the mold material, cut into the required length.
    3.4.3 softening the plastic plate: the glycerin into the container, heated to 140 ~ 160 ℃ with an electric furnace, will be bent to the plastic skirting board into the heated glycerol container (this time can not be heated) for about 1min, remove the add The temperature of the plastic skirting board into the mold has been prepared, to be cooled to shape.
    3.5 safety skirting board:
    3.5.1 Installation of fixed card: in the lower position of the wedge will be fixed card alignment has been good two horizontal lines, with a wooden screw will be fixed on the wooden wedge wedge (or not equipped with wooden wedge, drill holes have been used Expansion bolt plastic bolt). If the light wall can be self-tapping screws.
    3.5.2 Installation of plastic skirting board:
    3.5.2.1 Installation of the skirting board at the corner of the yin and yang: Before installing the plastic skirting board along the wall, install the special skirting board at the corner of the yin and yang, pull the line and measure the thickness of the wall, and align the skirting board with the well Catchy horizontal line.
    3.5.2.2 Installation of the skirting board along the wall: According to the length of the skirted board which has been installed, the joint of the skirting board is made to be tight, smooth and free from dislocation.
4 quality standards
    4.1 Warranty items:
    4.1.1 plastic skirting board variety, size, color to meet the design requirements. Products must have a certificate.
    4.1.2 The quality of the appearance of plastic skirting board shall not have cracks, blistering, bending, twisting Alice and other defects.
    4.2 Basic Items:
    4.2.1 installation joints flat, the same height, card solid solid, consistent thickness of the wall.
    4.2.2 surface tone evenly, clean.
    4.3 Allowable deviation items, see Table 9-53:
                          Plastic skirting board mounting tolerances Table 9-53
Line item Allowable deviation (mm) Inspection method
1 catch straight 3 pull inspection
2 upper and the wall gap 2 foot size check
3 straight surface 4 cable inspection

5 protection of finished products
    5.1 installation of plastic skirting board in the process, pay attention to the construction has been completed to protect the walls, floors, doors and windows, so that it is not damaged and contaminated.
    5.2 The installation of plastic skirting board in the process, its material should be reasonable stacked, so that without folding, not under pressure, not to be contaminated.
    5.3 End of the installation of plastic plates of the room and parts, should pay attention to protection, not free to move, collision. Other construction projects to prevent contamination of the installation of the skirting board.
6 should pay attention to quality problems
    6.1 skirting board rugged: the main is to install a fixed card up and down inconsistencies. Operation should be accurate on the line, fixed card should be room inspection and acceptance.
    6.2 Skirting board joint uneven, fixed card out of the wall is not a plane, screw fixed card before checking the wedge out of the wall is consistent, pull the line to find smooth, you can make the skirting board joints solid smooth.
    6.3 The gap between the skirting board and the wall is too big: The main reason is that when the fixing card is installed, the wall size is wrong. When the wooden wedge is inserted, the wall size should be controlled so that the wall gap can be controlled within the allowable range.
7 Quality records
    This process standard shall have the following quality records:
    7.1 Materials and accessories of the material certificate.
    7.2 Installation of assessment data.