Sunday, January 29, 2017

Wall cabinet, hanging cabinet installation process

Wall cabinet, hanging cabinet installation

1 range
      The process standards for general construction and hotel building closet, hanging cabinet installation works.
2 construction preparation
    2.1 Materials and structural parts
    2.1.1 Wall cabinet, hanging cabinet products manufactured by the factory into finished or semi-finished products, wood products, moisture content shall not exceed 12%. When processing the frame and the fan comes into play, should check the model, the quality, the authentication product certificate.
    2.1.2 Other materials: preservatives, plugs, wood screws, handle, lock, touch beads. Hinge, etc., according to the design requirements of the species, specifications, models purchased.
    2.2 The main equipment:
    2.2.1 electric tools: welding machine, hand drill, small table saw.
    2.2.2 hand with a large plane, two shaver, small plane, cut planer, wood saws, ax, flat shovel, wood drill, tap, screwdriver, hacksaw, steel level, chisel, steel setback.
    2.3 Operating conditions.
    2.3.1 structural engineering and related closet, hanging cabinet of the Siamese structure has been installed with wall cabinets and hanging cabinet conditions, the level of indoor elevation has been.
    2.3.2 closet, hanging cabinet finished, semi-finished products have approach, and acceptance. Quantity, quality, specifications, varieties correct.
    2.3.3 Wall cabinet, hanging cabinet product acceptance acceptance, should be promptly on the installation location against the wall, paste the ground part of the anti-corrosion paint brushing, the other side should be painted with a paint at the end. Storage flat, to maintain ventilation; generally should not be open-air storage.
    2.3.4 Wall cabinet, wall cabinet and fan box, before installation should check whether the channeling angle, Alice, bending, splitting. If the above defects, should be qualified to repair line after assembly. Hanging cabinet steel skeleton should check specifications, deformation should be corrected and then installed.
    2.3.5 Wall cabinet, hanging cabinet box should be installed before plastering; fan should be installed after plastering.
3 operating process
    3.1 Process flow:
Line positioning → frame, frame installation → wall partition support point installation → wall (hanging) frame fan installation → Hardware Installation

    3.2 to find the line positioning: plaster before the use of indoor uniform elevation line, according to the design and construction plans requirements of the closet, hanging cabinet elevation and the height of the mouth, plaster thickness of the relationship to determine the appropriate location.
    3.3 Wall cabinet, wall cabinet, frame Installation: wall cabinet, hanging cabinet frame and frame should be carried out before the indoor plastering, installed in the correct location, the two sides of the box fixed point should be nailed two nails and wall wood Nail, nail cap shall not be exposed. If the wall is lightweight material, should be fixed according to design requirements fixed firmly. Such as the design does not require pre-drilling depth of 70 ~ 100mm φ5mm hole, embedded in the wedge, the method is corresponding to the hole with the large wooden wedge glue 107 glue, cemented into the hole firmly, .
    When the steel frame is used, it is necessary to embed the iron parts at the position where the hole fixing frame is installed.
    Fixed in the framework of the former should be corrected, sets of square, hanging straight, check the elevation, size, location, accurate, fixed.
    3.4 Wall cabinet partition support point installation: according to the construction map partition height position and support point of the structural requirements, install the partition of the solid bar, frame, pieces. Wood partition of the solid point is generally solid wood will be nailed to the wall wood bricks; concrete partition is generally 匚 type iron or set angle bracket.
    3.5 Wall (hanging) cabinet fan installation:
    3.5.1 According to the size of the fan, to determine the model and specifications of the hardware, the direction of the opening of the cut fan, the general should be to open the direction of the right fan cover four.
    3.5.2 Check box 4 size: the height of the frame should be on both ends of the mouth; frame width, should be on both sides of the box between the upper, middle and lower three points in the corresponding parts of the fan designated dash.
    3.5.3 frame fan repair plan: according to the drawer on the cabinet fan for the first time to repair, so that the gap between the right to stay between the frame, test equipment and plan a second repair line, and draw the box, fan hinge slot Location, note the line to avoid the upper and lower head.
    3.5.4 shovel, tick hinge slot hinge installation: According to the designated hinge position, with a flat shovel chisel out the hinge edge, you can tick the slot.
    3.5.5 Installation fan: When installing, press the hinge first into the hinge slot of the fan. After fixing, tighten the fixing screws, make trial installation, adjust the gap between frame and frame, fix the hinge slot on the frame, When the box on each hinge first screw a screw, and then close, check the box and fan formation, no defects meet the requirements, all the screws installed on the tighten. Wood screws should be nailed into the full length of 1/3, screwed into 2/3, such as box, fan for yellow flower or other hardwood when the hinge is installed. Screw installation should be targeted drill hole diameter of wood screws 0.9, eye depth for the screw length of 2/3.
    3.5.6 Installation of the fan: First frame frame size is good, to determine the middle of the mouth seam, cut the depth of the mouth, after the planing slot, test equipment is appropriate, first installed left fan, after the cover fan.
    3.6 Hardware installation: The variety, specification and quantity of the hardware should be selected according to the design requirements. When installing, please pay attention to the location selection. If there is no specific size, the operation should be done according to the technology. Generally, the sample should be installed first.
4 quality standards
    4.1 Warranty items:
    4.1.1 frame fan varieties, models, installation location must meet the design requirements.
    4.1.2 Frame fans must be installed securely and the fixing points meet the design requirements and the standards specified in the construction and acceptance specifications.
    4.2 Basic Items:
    4.2.1 cabinet fan cut straight mouth, planing surface smooth, live fan installation should be flexible, stable, no rebound and inverted Alice.
    4.2.2 Hardware installation location appropriate, the same deep groove, the edge of neat, accurate size. Hardware specifications to meet the requirements, the number of complete, wood screws tighten the level, the plug open flexible plug.
    4.2.3 Cover the mouth of the box, pressure seam blanking the same size.
    4.3 Permissible deviation items, see Table 9-48.

                            Allowable deviations in wall cabinet and wall cabinet installation Table 9-48
Line item Allowable deviation (mm) Inspection method
1 box, the vertical side of the side 3 with 1m care board inspection
2 Diagonal line 2 Check the size of the box
3 box and fan, fan and fan height difference 2 with ruler and feeler check
4 box and fan, slit width between the mouth fan value of 1.5 to 2.5 with a feeler to check

5 protection of finished products
    5.1 wood products into the market after a timely brushing base oil, by the basic level should be brush preservatives; copper products should be promptly brush anti-rust paint into the library.
    5.2 wall, hanging cabinet installation, non-collision plaster and other decorative surface of the mouth, to prevent damage to the finished surface layer.
    5.3 installed wall cabinet partitions, not demolition move to protect the integrity of the product.
6 should pay attention to quality problems
    6.1 plaster surface and the box is not flat: more vertical deviation for the wall is too large or the box is not caused by vertical installation. Attention to the standard frame and plaster to ensure that perception of quality.
    6.2 cabinet installation is not strong: embedded parts, wood bricks have been loose before the installation or fixed point less. Connection, nail to the number of solid points to install a solid.
    6.3 Hinge, screws loose, nuts are not straight, missing screws: The main reason is the hinge slot uneven, the depth of inconsistency, the installation screw into too long, resulting in tilt, screw down. Operation should be the standard screw into the length of 1/3, screw into the depth of 2 /
    6.4 cabinet frame and hole size error is too large; matrix construction holes are not allowed. The size and elevation of the structure or foundation shall be in accordance with the requirements when the hole is to be constructed.
7 Quality records
    The process standards should have to plant the quality record:
    7.1 wall cabinet, hanging cabinet products should be products