Light steel frame cover panel ceiling construction technology

Light steel skeleton cover panel ceiling construction
1 scope
The technology standard is applicable to industrial and civil buildings ceiling mounted with light steel frame cover panel ceiling installation.
2 construction preparation
2.1 materials and components:
2.1.1 light steel skeleton skeleton points u-shaped frame and T two kinds, and according to the load points and not two kinds of people on it.
2.1.2 light steel skeleton main parts have large, medium and small keel; Accessories have a crane accessories, fittings, hang plug-in.
2.1.3 parts with derrick, flower basket screws, screw, self-tapping screw.
2.1.4 cover panel according to the design requirements, use material varieties, specifications, quality should meet the design requirements.
2.1.5 adhesive: should according to the main performance of the adhesive material selection, do bonding test before use.
2.2 the main equipment:
2.2.1 saws, saw tooth and nail gun.
2.2.2 handsaw, hand plane, pliers, screwdriver, wrench, meters, steel rule and equality of the molten steel.
2.3 operation conditions:
2.3.1 structure construction, should be in cast-in-situ concrete floor seamed or precast concrete floor, the spacing of embedded parts according to design requirements from 6 ~ 10 steel derricks, general spacing is 900 mm, 1200 mm.
2.3.2 when the ceiling of the room for brick masonry walls, column, is to be according to the ceiling with masonry brick elevation embedded anticorrosive wood, wood brick wall along the distance 900 mm to 1200 mm, each side should be buried in the wood block in the column more than two blocks.
2.3.3 is installed in the ceiling of the pipeline and equipment, make sure good lamp, air vents, and various kinds of open hole position.
2.3.4 various materials all supporting resources.
2.3.5 roof cover panel before the installation, should be finished wall, ground wet operation projects.
2.3.6 set ceiling construction manipulator frame.
2.3.7 light steel roof in large area before construction, should be done between example, on the ceiling of the bulging, the lamp chamfer, vents and structure processing, by making decision between example block and fixed method, identified recognition after large area construction.
3 operation process
3.1 process:
Play the ceiling elevation to delimit keel along the line, install the horizontal to install the main keel, keel boom

Install a keel installed to cover panel to brush paint, layering

3.2 play ceiling elevation level: according to the floor level is horizontal, vertical to the ceiling design elevation, with your ruler along the wall, and went to play around the ceiling level is horizontal.
Step 3.3 cross keel line: according to the design requirements of the main keel span arrangement, time, in has good ceiling elevation level keel along the line.
Derrick: 3.4 install the keel play ceiling elevation and keel along horizontal line of position, determine the level of end under the boom, according to the main keel position and hanging space, will be no one end of the bolt screw thread with derrick floor embedded bar fixed connection. Not when embedded bar available expansion bolt.
3.5 install the keel:
3.5.1 track of with telescopic boom nut.
3.5.2 install hanging in the main keel accessories.
3.5.3: install the keel will be assembled crane accessories main keel, according to the step line position, the widget through corresponding cup bolt, screw like mother.
3.5.4 main keel thru installed connectors, adjust the elevation, arch of peace.
2.6.2 installation hole additional main keel, according to the atlas of the corresponding node structure, set up the connection card firmware.
3.5.6 nailed keel, using nail fixed. No specific design, nail spacing is 1000 mm.
3.6 installation times keel:
3.6.1 track along the line, according to the good times keel card put times keel accessories.
3.6.2 hang times keel, keel span of time, as stipulated in the design the first keel through condole hang hang on the large keel, design requirements, general spacing is 500 mm to 600 mm.
3.6.3 when times keel length needs to root for long, keel fittings in time, at the same time of hanging times keel, straightening and fixed.
3.6.4 radar echoes captured when using T keel of light steel keel keel card file should be in installing a cover panels, each with a hood panel has installed a level keel.
3.7 installation cover panel: before install cover panel pipeline inspection must be within the ceiling on a variety of acceptance, and after suppression test, are allowed to install the cover panel. Roof cover panel variety, generally in the design document should be clear to choose the type, specification and fixed way. Cover panels and light steel frame fixed way is divided into: cover panel self-tapping screw nail fixation method, cementing cement cover panel method, three kinds of cover panel topkapi fixed method.
3.7 l cover panel self-tapping screw nail fixation method: light steel skeleton has been installed and experienced the following, according to the cover of the specifications of the panel, gap, partition line, from the ceiling in the middle of shun tong long times keel direction to a row cover panel first, as a benchmark, then branches stretches out to the sides installation, fixed cover panel of self-tapping screw spacing is 150 mm to 170 mm.
3.7.2 cover panel cementing cementation method: according to the requirements of design and a variety of cover panels, material selection of cementing material, generally available 401 adhesive, cover panel shall be optional trim, uniform thickness, size, edge stare blankly, neat. Each cover panel bonding should be led the pack, then brush glue in pre-installed keel box bottom, and four surrounding the cover panel of 10 mm to 15 mm wide range brushing glue, after 5 min, to press the cover panel glued to the pre-installed parts; Each roof from middle row first, then to the adhesive on both sides of the branch.
3.7.3 cover panel topkapi fixed method: when the light steel keel is T, more for topkapi fixed method of installation.
T light steel keel installed long time, through inspection level, spacing, straightness and comply with the design requirements of hanging load, perpendicular to the tong long times keel block and keel line card file. Cover panels installed at the end of the line in the middle of the time by ceiling keel, keel, first to a root had class will cover panel slot again into the tee times keel flange or there can be no slot of cover panel is installed in the T on the edge, then install the other side long level keel. Stay adjustable branch installation according to the above procedure, the final branch tee Ming dragon bone.
3.8 installation layering: cover panel ceiling design requirements such as layering, with a roof cover panel installed, adjusted the position, make the seam evenly, to sew the whole hand, according to the layering position line, and then wiring for layering installation. The fixed methods appropriate USES self tapping screw, screw spacing is 300 mm; Cement paste is also available.
3.9 brush anti-rust paint: light steel frame cover panel ceiling, carbon steel and the surface of the welding place treatment done at the end of the (such as embedded parts, accessories, fittings, nailed accessories, etc.), in the process before installation should brush anti-rust paint.
4 quality standards
4.1 ensure projects:
4.4.1 light steel skeleton and the material of cover panels. Varieties, patterns and specifications shall meet the design requirements.
4.1.2 steel-frame installation, derrick, Lord, keel position must be correct, connection is firm, no loose.
4.1.3 cover panel should be no delaminating, warping, defects such as cracked, lack of stare blankly, off Angle; Installation must be strong.
4.2 the basic items:
2 light steel skeleton finishing should be straight, no bending, no deformation; Crane accessories and fittings shall comply with the requirements of the product portfolio.
4.2.2 hand the whole cover surface, clean, color is consistent; No pollution, anti rust and other defects.
Holdings cover panel seam form should comply with the design requirements, seam and layering width is consistent, straight, neat, seam should be tight.
4.3 allowable deviation projects, see table 9-13.
Light steel skeleton army panel ceiling allowable deviation table 9-13

Allowable deviation (mm)
Plywood plasterboard asbestos board plastic fiber board calcium plastic board
1 2 2 2 2 2 2 feet keel keel spacing quantity check
Keel straight 3 3 3 2 2 2 2 feet quantity check
3 bulging height plus or minus 10 + 10 + 10 + 10 + 10 + 10 short span to pull 1/200 scale
Frame around the level 4 + 5 + 5 + 5 + 5 + 5 + 5 feet or level examination
5 cover panel surface is flat and level 2 2, 3, 3 3 3 check with 2 m by ruler
6 seam straight 3 3 3 3 3 3, 5 m line inspection
7 seam height 0.5 0.5 1 1 1 1 with straightedge or feeler check
8 near the ceiling level + 5 + 5 + 5 + 5 + 5 + 5 arrows or use the level check
9 bead bead flat 3 3 3 3 3 3, 5 m line inspection
10 layering spacing 2 2 2 2 2 2 feet quantity check

5 finished product protection
5.1 when light steel frame and cover panel installation, should pay attention to protect the ceiling in the pipeline. Light steel derricks, keel are not allowed to be fixed on the ventilation pipe and other equipment.
5.2 light steel frame, cover panels and other condole top material in the process of transportation, entry, storage, use, should be strict management, do not deformation, not be affected with damp be affected with damp, do not rust.
5.3 engineering has been installed in the doors and Windows, has been finished, the floor, walls, window, etc., should be paid attention to during construction of the roof to protect, prevent fouling.
5.4 light steel frame shall not people trample; Other kinds of crane accessories shall not be hanging on the light steel frame.
5.5 in order to protect the finished product, cover panel installation must be within the ceiling pipe water, pressure test, insulation all process upon the acceptance of all.
6 should pay attention to quality problems
Condole carries on the uneven: 6.1 the main keel derrick leveling is not serious, caused the boom point elevation inconsistent; Construction should be carefully operation, check the hang tight degree of lifting point, line and pull through check the elevation and flatness standard meets the design requirements and norms.
6.2 light steel skeleton partial node structure is not reasonable: ceiling light steel frame on the hole, lamps and lanterns, air vents, etc, should be in accordance with the drawings of the corresponding node and tectonic setting keel fittings, make construction meet the requirements of the drawings on the hanging stiffness.
6.3 light steel frame crane is not firm: ceiling light steel frame should be hung on the main structure, and should be tighten derrick nut, to control the fixed design elevation; Ceiling in the pipeline, equipment parts shall not be suspended solid in light steel frame.
Block the gap between them are not straight: 6.4 cover panel cover panel specifications have deviation, installation is not straight; Pay attention to during the construction of plate specifications, the guy is, installing a fixed to ensure smooth straight.
Article 6.5 seam pressure, pressure side not tight straight: article processing material specifications inconsistent; Should be selected when using, guy looking for are fixed after operation and pressure to glue.
6.6 square aluminum alloy condole to pay attention to the color plate, to prevent the uneven color quality.
7 quality records
This technology standard should have the following quality records:
7.1 light steel keel, crane accessories, fittings, shall have the product certification.
7.2 cover panel should have the factory certificate.
7.3 acceptance of work should have the quality inspection evaluation data.