Saturday, December 3, 2016

Installation technology of sanitary ware

1 scope
This technology is applicable to General Civil and sanitary installation in public buildings.
2 construction preparation
2.1 materials requirements:
2.1.1 sanitary specifications, models must meet the design requirements and product certification. Sanitary ware skins rule, handsome boy, the surface is smooth, beautiful, no cracks, smooth edges, the tone is consistent.
2.1.2 sanitary ware parts specification standards, quality should be reliable, sleek, electroplating, uniform, clear thread, lock tight moderate, no sand holes, cracks and other defects.
2.1.3 sanitary ware water tank water-should be used.
2.1.4 other material: plating zinc fittings, and skin money as valve, and horoscopes valve, and water mouth, and silk buckle returned water bent, and drainage mouth, and plating zinc yan tail bolt, and nut, and rubber Board, and copper wire, and oil gray, and lead skin, and screws, and solder, and cooked hydrochloride, and lead oil, and Ma silk, and asbestos rope, and white cement, and lime cream, are should meet material standard requirements.
2.2 the main tools:
2.2.1 machine: Threading machines, grinding machines, abrasive cutoff saw, hand drill, impact drill.
2.2.2 tools: pipe wrenches, hand, iron, cloth paper scissors, adjustable wrench and homemade die wrench, fork wrench, hammer, hand shovel, chisel, nippers, square, round-ended nail file, screwdriver, soldering iron, etc.
2.2.3 other: horizontal ruler, compasses, linear pendant, small line, box, and so on.
2.3 operating conditions:
2.3.1 all connected to the sanitary pipe pressure, closed water test has been completed, and has run hidden preflight procedures.
2.3.2 tub of steady wear should stay civil finished waterproof layer and layer of cooperation after construction.
2.3.3 other sanitary ware installed in the interior decoration completed a steady.
3 operational processes
3.1 process:
Installation preparation inspection sanitary installation of sanitary ware and fittings sanitary fittings pre-installed

Stability sanitary ware with walls of sanitary wares, gap Visual inspection sanitary ware water test

3.2 sanitary ware in stability checking, cleaning should be carried out before loading. Matching accessories and sanitary wares. Parts should be conducted before the prefabrication and installation of sanitary wares.
3.3 sanitary installations:
3.3.1 high tank, squatting installation:
3.3.1.1 high tank fittings installation:
A siphon, lock, parent, under pads removed, apply Putty to insert the siphon high tank outlet. Under the mat, eyes set on the pipe. Tighten the mother loose moderation. The lock screw on the siphon. Siphon and position depending on the case to determine.
B float ball screw in on the float rod and ball valves (floating gate) connected, floating ball valve installation and wind installation.
C BRACKET: remove nut on eye, then insert the bolts on the water tank side along the (lateral direction and set as water provision) and washer fastened. Adjust the retractable Rod distance (pick the pulling distance is generally 40mm). Pick pull rod connection at the other end (the former may also submit), the spare water the water tank cover with plastic blocking the eyes.
3.3.1.2 squatting, high stability with the water tank (figure l-22):
A first, the rubber Bowl set in squatting on the intake, and real. Finished hose clamp fastening (or 14# copper wire tied two, respectively, but does not allow compression on a line, wire twisting critical dislocation around 90 degrees).
B reserve drains clean around the mouth, pipe plug removed temporarily, also check the tubes free of debris. Find the centerline of the drain, and paintings on the wall. With a horizontal ruler (or line) to find a good bar.
Put oil in the pipe socket under ash, squatting position pave lime paste, and insert the squatting pan drain drain socket stability good. Simultaneously with the spirit level on squatting along, and two-way leveling and alignment. Intake of squatting at the center line on the wall. While squatting Pan sides brick good finishing, squatting drains and drain socket contact compaction, finishing PuTTY. Finally, squatting pan drain with a temporary plug seal.
C stability when loading multiple squatting, elevation should first check the drain, dumped from the wall dimensions are the same. Find out the standard ground elevation, measured the height of good squatting needs, leveling with a small line, find a good wall distance as described above then steady loading them one by one.
D high stability with the water tank: squatting should steady after loading the. First check for squatting and wall center line are the same, such as dislocation should be adjusted in a timely manner, and to squatting does not become skewed. Identify water tank outlet center locations, provision is measured height (water supply from the step surface 2m). Combined with high water tank mounting holes and the distance between water holes identify the fixing bolt height, on the wall drawn cross line, tick φ 30x100mm deep into the hole, rinse water holes in the debris, and will dovetail bolt into the hole in the cement firmly twist. High water tank installed accessories hanging on the fixing bolts, plus pad, eye, bring the nut is screwed to the elasticity moderate.
E hang multiple high-water tanks shall be according to the above practices at both ends of the tank, and thread level, get a straight and steady with middle water tank.
F high water tank flush pipe connection: good character, measured high water tank floating ball valve from the Bazi pipe size in the Watergate, with a good short sections, packed in eight on Watergate and the water inside the mouth. Copper tube or pipe break well needed light simmer well bent the fork bending. Float valves and eight water lock is then removed, back to back on a copper tube or pipe, two asbestos-wrapped oil lead rope or twine, insert float valve and Bazi Watergate import screw locking.
G time-lapse self-closing flush valve installation: flush valve of the Centre is 1100mm. According to the distance from valve to rubber Bowl, breaking good flush pipe 90 ° bend, right on both ends. The flush valve lock and the rubber ring is removed, respectively on the flush pipe straight pipe, the lower end of the pipe is inserted into the rubber Bowl, 40~50mm, hose clamps in prison. Then insert the upper end of flush valve, push rubber ring, straightening and alignment, lock screw to tension properly.
Wrench wrench spout flush valve should be directed to the right. Button flush valve button should be directed to the front.
3.3.2 back tank toilet installed (Figure 1-23):
3.3.2.1 back tank fittings installation:
A back water tank drain with overflow pipe installation and wind installed the same. Overflow pipe must be less than 10~20mm tank fixed screw.
B back-flush ball valve installation with the same high water tank, repairing after the fill tube simmering bending the pipe to the overflow tube in the mouth.
C when installed, the first disc into the back left corner square holes in the tank, put the disc into the square nut with a pipe wrench to unscrew the elasticity moderate, Simmers picked good spoon bending, the wrench shaft into the circular hole, cantilever bar tighten the set screw on the set.
D when you install the back plate over the drain the water tank, will pick the rod and a flap with a nylon cord connected. Flip flap on the wrench to pick Rod movement.
3.3.2.2 back tank, toilet stable binding:
Reserved a toilet drain to clean around the mouth, remove temporary pipe plug, check the tube free of debris.
B align the toilet outlet reserved outlet flat alignment, in the eyes at the toilet mounting bolts on both sides draw after mark, remove the toilet and mark cross.
C in the center of the crosshair tick φ 20x60mm holes and bolts were inserted into the holes in the 10MM cement plant, and will try the steady toilet, so fixing bolts coincide with toilet, remove toilet. The toilet drain and drain grease around the mouth align the toilet bolts after ash flat, alignment, bolt put good rubber pad, RIM nut is screwed on to the elastic moderate.
D at end of the toilet Center, draw a vertical line on the wall, to flat 800cm high, draw a horizontal line at a distance of. According to the back of the tank fixed hole distances, in drawing the crosshairs on the horizon. Φ 30x70mm tick at the crosshair Center deep in the hole, galvanized bolts with a swallow-tail (specification of φ 10x100mm) inserted into the holes in the cement plant in prison. Back tank hanging bolt leveling and alignment. Centre for toilet is, bolt put good rubber mat, eye, the nut is screwed on to the elasticity moderate.
Toilet water lock-free rubber Bowl connection methods can be used.
Sheung Shui Bazi Watergate connection method with the same high water tank.
3.3.3 lavatory installation (Figure 1-24)
3.3.3.1 washbasin components installed:
A install the basin drain: first drain the root parent, eye, pad removed, insert mat good will after the PuTTY wash-basin drain holes in the drainage water overflow to the mouth on the basin overflow eyes. Plus pad well outside PuTTY rubber, on the set of circles, take root, and self-wrench jammed drain cross bar, with a flat wrench to tight the moderate.
B installation washbasin tap: the tap root parent, the lock is removed, tap root mat oil ash, insert basin water holes, pad eye on the next, bring his mother left holding down the tap right hand made eight die wrench to lock tightly to elastic moderately.
3.3.3.2 washbasin stable binding:
A wash basin bracket installation: shall be in accordance with the drain outlet Center draw a vertical line on the wall, measured out specified height from the ground up, draw a horizontal line, according to basin-wide horizontal lines drawn on the position of the crosshairs. By Mark tick φ 30x120mm holes. Washbasin bracket leveling planted in prison. Then put the washbasin bracket leveling, alignment. Hook in the fixing holes in the basin, tighten the fixing bolt frame, looking for citizens.
B cast iron lavatory installation: looking for a cross as described above, by Mark tick φ 15x70mm holes, planting good lead volume, with 2 1/2 2 screws fixed to the wall. Active frame fixing bolts to loosen, pull the adjustable shelf will hook in the fixing holes in the basin, tighten the fixing bolt frame, leveling, and alignment.
3.3.3.3 washbasin drain connection:
A connection to s-trap: the basin drain outlet threaded bottom lead-coated oil, wrapped around a little hemp thread. Screw on the drain trap on section, elastic moderate. Then under water bends around oil packing line at the lower end of the section in the drain inside the mouth, place the cushion in the joints where water bends, hand tighten the lock after straightening and alignment. Then use the wrench to unscrew the elasticity moderate. Pipes under the strict, with a PuTTY trowel.
B connection of the p-trap: the basin drain outlet threaded bottom lead-coated oil, wrapped around a little hemp thread. Screw on the drain trap State section, elastic moderate. Then traps as required length with a good cross section. Disc lock guard and back to back sets in cross section, end wrapped oil packing line, try height is appropriate, inappropriate vertical adjustment available, then put the rubber mat inside the lock, the lock screw to tight moderately. After filling the PuTTY to the retaining plate wall leveling, according to real. Spillover PuTTY removed, clean the wall surface. Exposed hemp thread of the drain clean.
3.3.3.4 basin water supply pipe connection:
First, good size, with a good short. Fitted with eight Watergate. Again will short tube another end silk buckle at coated oil, and wrapped around Ma, twist in reserved to pipes mouth (if is dark loaded pipeline, with nursing mouth disc, to first will nursing mouth disc sets in short section Shang, pipe Shang finished Hou, will nursing mouth disc within fill oil gray, to wall surface leveling, and by real, cleanup spills oil gray) to elastic moderate. The copper tube (or plastic) size broken well, simmer the simmer well bent the fork bending the light you want. Bazi Watergate lock remove mouth with water, back in the copper pipe (or plastic), one wrapped packing oil lead rope or twine, top inserts tap root, inserts a character at the lower end in the Watergate,
Play respectively the upper and lower lock to the elasticity moderate. Looking for straight, alignment, and clean up the exposed wire.
3.3.4-PT type wash basin installation
3.3.4.1-PT type wash basin fittings installation:
A mixing faucet installation: mixing tap roots and 1mm pad, PuTTY. Insert basin, along the Middle holes, bottom with glue pad and rim, strengthening water nozzle and tighten to elastic moderate, with a good water supply and lock.
B cold or hot water remove the valve cover, out of lock, leaving the valve insert basin with cold or hot water hole from the bottom up. Valve lock and glue traps into four horizontal pipe, then valves fuel ash and 1mm thick pad, tighten the root and threads. Cover the valve cover and tighten the cover screws.
C, the washbasin drain plus 1mrn thicker rubber, PuTTY, insert basin drainage holes, without pads, and eye, put oil, wrapped thread. Drain stuck with self-wrench cross bar, screwed into the water tee, back, align the overflow basins overflow nozzle.
D universal ball mount hand lever and spring three-way Centre lock screw to tension properly. Then pole through mix nozzle hollow tubes to cross out, four and pole connector around oil packing line, tighten the compression nut. State, rail crossing points with fixtures join well positioned at the same time.
3.3.4.2 PT type wash basin mounted stabilization:
A in accordance with the drainage pipe to draw vertical lines, prop up, will turn the basin placed on the pillars, basin Center at the vertical line drawn after leveling the washbasin fixing holes position. While pillars on the ground mark. By Mark tick φ 10x80mm holes on the wall, planted well fixing bolts. Will put the lime cream pillars mark the ground, stable good pillars and basins, mounting bolts plus rubber mats, circles, the nut is screwed on to the elastic moderate. Washbasin surface leveling again, prop. Important contact with the basin and pillars at the contact with the ground with white cement seam finishing.
B PT pillar-type methods according to washbasin washbasin drain connection drainage pipe installation.
3.3.5 bidet installation (figure l-25)
3.3.5.1 install bidet fittings:
A mixing valve and remove door cover for cold and hot water valves, under the appropriate, with three valves mounted after good root and valve neck threaded with the level is appropriate. Preinstalled nozzle turn heart valve mounted on the mixer tap of four-way out.
Cold and hot water valve outlet lock in the mixing valve four-way cross pipe, plus assembling rubber ring or around oil packing rope together, twist lock female. Add the three valve neck cushion while the bidet from bottom to top through the holes. Three valves on the pad, RIM take root. Mixing angle-valve on the rubber mat and a little Putty and rectangular chrome-plated protection plate on the buckle, with a good mother. Then hollow bolt through the nurse and bidet. Basin plus pad eyes and mother, tighten to elastic moderate.
Tighten the mixing valve, its neck and turn the heart valves threaded flat. Put the valve cover valve rotation, can make the heart valve cover rotate 30 °. Again on the cold and hot water valves to the root symmetrically tighten. Separately installed three valve cover, tighten the fixing screws on the cold and hot water valve door door.
B nozzle: a nozzle plus 1mrn thicker pads on porcelain surface, wipe a little PuTTY, shaped copper pipe connected to the nozzles and the other end connected with the mixing valve four heart valves under. Twist lock, turn valve door with four parallel side, so as not to affect the hand lever installation.
C drain installation: drain with glue pad, through the bidet drain hole. Screwed into the drain tee and catchy. While check drainage mouth and purification basin drainage eyelets of concave whether close, as has loose and the not closely phenomenon, can will drainage mouth saw off part, size right Hou, will drainage mouth disc Xia added wipe oil gray, outside added rubber pad, and circles, with homemade fork wrench card into drainage mouth within cross reinforced, makes spill water mouth alignment purification basin spill water eyelets, twist into drainage tee catchy.
D hand lever installation: the retractable Rod spring bead mounted drain tee, twist lock to elastic moderate. Hand lever is then inserted hollow bolts, clamps connected with the cross to pick Rod adjustments to our positioning, hand lever movement.
E bidet fittings after loading, temporary water leaks should be connected before the steady wear.
3.3.5.2 bidet stable binding:
Reserved a drainage tube to clean around the mouth, temporary pipe plug removed, check for debris. Bidet tee out of copper pipe installed.
B insert the bidet drain reserving drainage pipe inside, bidet stable alignment. End of the bidet from the walls the same size. Good to draw the base of bidet fixing bolt holes and mark, remove the bidet.
C the fixing bolt holes mark drawn cross line, tick φ 20x60mm hole, bolt into the hole in the kind of good. Then align the bidet eyelet bolt away, after agreement with the original mark bidet underlying good Lime plaster, designer on the drainage copper tube. Bidet steady prison, leveling and alignment. Mounting bolts on the pad, RIM and tighten the nut. Clear the ashes and wipe clean. Designer dish filled with PuTTY and ground according to reality. Bidet base, and there are gaps between the ground, embedded in the mud filled whitewater, finishing.
3.3.6 plane urinal installed (1-26)
3.3.6.1 first, at the water Center draw a vertical line from the specified height is up to draw a horizontal line. According to the product specification, from Center to side fixing hole distance on the line drawing the crosshairs, and then draw the top and bottom hole locations.
3.3.6.2 hole location tick φ 10x60rnm holes, into the 6mm bolt. Lifted hung urinals on the bolt. Trap into the pad, eye bolts, nut is screwed to the elasticity moderate. Urinal and wall surface crack embedded whitewater mud filled, finishing. Other installation method as above.
3.3.7 standing urinal installed:
3.3.7.1 standing urinal before installation should check for reserved, drainage tubes are on a vertical line, spacing is consistent. Meets those requirements in accordance with the center line of the tube to find out. Clean around the pipe, remove the temporary plug, good oil, under the standing urinal paving of cement and Lime plaster mixed lime (1:5 per cent). Urinal vertical steady load leveling and alignment. Pedestal urinal and wall surface, surface crack embedded in white mud, finishing trowel.
3.3.7.2 Bazi Watergate threads lead oil, wrapped hemp, into the water, with the Board to moderate elastic. Its designer plate and wall. Bazi Watergate exports on duck-billed lock, volume size, broken well pipe, set lock and buckle Bowl, insert the Duckbill and Bazi Watergate outlet, respectively. Packing rope wrapped around oil to loosen the locking screw loose moderation. Then press the buckle Bowl come on gray.
3.3.8 furniture installation (figure l-27):
3.3.8.1 before planting the pots should be line with the furniture basin a try. Cold and hot water split equally between reserve pipe draws a vertical line (when only cold water, furniture Center should be aligned to the pipe). Specified height is from the ground up, draw a horizontal line, in accordance with the furniture around frame widths up to the center line drawn cross line, tick φ 50x120mm holes, water in the rinse holes debris, frame leveling, alignment. Cement plant in prison. Furniture will be placed on the frame horizontal leveling and alignment. Furniture side gaps embedded in the whitewater mud against the wall joint finishing.
3.3.8.2 drainage pipe connection: first drain the root parent release the unloaded, put furniture basin drainage holes, measure from the reserve pipe size. Good thread on the short end, oiled, wrapped. Leave traps to the exposed screw 2~3 ring, according to good size spool a broken well, insert one end of the drain flange processing should be done. Drain disc under 1mm thick pad, hand PuTTY, insert furniture basin drainage holes, pads, eye on the outside, take root. Anointing with oil at the drain outlet threaded linen, wrapped, cross bars within the self-wrench jammed drain, drain overflow nozzle at furniture basin of overflow hole, self-wrench tighten to tension properly. Hung straight alignment. Interface twist grey, girth should be uniform.
3.3.8.3 faucet installations: water will screw apply oil around the mouth, packed in water, leveling and alignment and tighten. NET exposed wire.
3.3.8.4 blocking chain installations: porcelain basin above 50mm and φ 10x50mm alignment Center tick into the drain hole, cement slurry will bolt and Grouting in prison.
3.3.9 tub installation (Figure 1-28):
3.3.9.1 tub mounted stabilization: tub tub surfaces should be wiped clean before loading stability, also check the porcelain surface is intact. Bathtub with legs first remove screws of the legs, to insert the PIN end of the tub lying tank, buckles in the tub on legs with a good nuts tighten leveling. When tub such as bricklaying, should relate to the civil construction built brick leg elevation. Tub steady at brick platform leveling, and alignment. Tub and tile topical 1:3 leg gap filling cement mortar trowel.
3.3.9.2 tub drain installation: on the tub drain tee in horizontal drainage pipe, wrapped oil packing line, insert links, twist lock female. Tee out pipe installed, insert the drainage reserve pipe (copper tubing bottom edge). Drains under the disc and pads, Putty and insert tub drain holes outside pad, circle, put lead-oil, wrap thread. Homemade stuck drain fork wrench cross bar and into in the elbow.
Overflow standpipe lock at the lower end, tied oil packing line, insert links and catchy at the tub overflow hole with locks. Overflow pipe elbow with LMM thick pads, oil ash, bath tub plug bolt through the overflow hole disc, into the elbow on "-" word on the thread, no loose. Then tee head lock screw to tension properly.
Tub drain tee outlet and drain connection winding oil packing rope twist reality, then PuTTY closed.
3.3.9.3 mixing faucet installation: cold and hot water leveling, alignment. Mouth turned to lead oil mixed with water, wrap hemp thread, take good care, self-wrench (commonly known as the key) into the turn to, respectively, is screwed into the cold, reserved hot water nozzle, good size, leveling and alignment. Retaining plate close to the wall. And then mixing faucets are turned on, twist lock leveling, after the pad alignment. Using a wrench to unscrew the elasticity moderate.
3.3.9.4 water mouths installed: first the cold, reserved hot water nozzle with a short tube leveling, alignment. Embedded pipe into the wall a deep, you should measure the short tube, good short tube, cold and hot water nozzle out from the wall. Tighten the faucet alignment, with the exception of net exposure.
3.3.10 shower installation (Figure 1-29):
3.3.10.1 chrome shower installation: concealed piping cold, hot water reserve tube and tube-leveling, alignment. Good short size, broken pipes, wire, lead oil-coated, round, elbow: good morning. Out elevation of pipeline required to simmer well "" bent (commonly known as the silver piece bends), a good coupling.
Shower head lock wire wire grease regularly. Inner rib stuck self-wrench, pipe into the elbow or on the hoop. Then align the shower outside the lock wire and tighten the lock. Fixed disc holes for leveling, alignment. Draw the mark, remove the shower will mark tick φ 10x40mm holes, planting good lead volumes. Then lock Silk Pad outside wipe oil, shower at the lock wire, using a wrench to unscrew the elasticity moderate. Fixed disc with the walls, holes for smooth, use wood screws to the wall.
Will shower the upper brass tubes pre-installed on the tee, the pipe vertically, fixed disc with wall stickers real holes smooth, draw the holes marked, into the lead volume, lock plus pad forest oil, lock screw to tension properly. Fixed disk on the wall using wood screws.
3.3.10.2 pipe shower Assembly: pipe shower Assembly must use galvanized pipe and pipe fittings, valves, the sizing must comply with the specifications of the Department.
From the ground up 1150mm, draw a horizontal line as a Center height of valve. Then cold and hot valve centre location drawing, measurement, piping components. Union valves should be added.
According to the number of prefabricated short tube, assembled in sequence, kind of fixed the standpipe riser card, head stuck. Standpipe should be hanging straight, head alignment. Installation should pay attention to the height of the men's and women's shower.
4 quality criteria
4.1 project:
4.1.1 quality sanitary ware type, specification, must comply with the design requirements;
Sanitary drainage outlet with drain socket connections must be tight and no leakage.
Inspection methods: inspection factory certificate, water check.
4.1.2 sanitary drainage pipe diameter and minimum slope must meet the design and construction specifications.
Inspection method: observation or standard checks.
4.2 Basic project:
Bracket corrosion well planted neat and firm, ware place smooth and clean. Brackets and fixtures in close contact.
Inspection method: observation and hand checks.
4.3 sanitary ware installation tolerances and inspection methods are given in table 1-15.
Sanitary installation method for the determination of tolerances and table 1-15
Project tolerance (mm) method
Separate instruments 10
Row 5
Individual device ± 15
Rows of ± 10
Level 2 with a spirit level and ruler check
3 vertical with hanging wire and check

4.4 hygienic sanitary equipment installation design requirements shall comply with the provisions of l-16.
Sanitary ware installation height table 1-16
Sanitary ware installation height (mm)
Residential and public buildings kindergartens

Slop sink
(Pool) type
Model 800
500 800
500
2
3
4
5 wash basin (pool)
Washbasins and flush the hand basin (without plug)
Washing trough
Tub 800
800
800
520 800
500
500

Squat
Stool for high tank
Tank 1800
900 1800
900 steps to high water bottom
Steps to low water bottom
High 1800 1800 out of step to high water the water tank bottom
7-exposed exhaust pipe
Siphon jet type 510
470-
370


Vertical
Hanging type 1000
600-
First 450 out of the ground edge
From the ground to the bottom edge of
9
10
11
12 and urinates
Fecal tank washing tank
Women's health
Test 200
Not less than 2000
360
800 150
-From the ground up to the steps
Steps to the water bottom
From ground to top edge of the apparatus
From ground to top edge of the apparatus

5 finished product protection
5.1 sanitary ware in the handling and installation to prevent knock. Steady load after supplies blocked sanitary drains application good, chrome-plated parts paper bag to prevent blockage or damage.
5.2 in the glazed ceramic tiles, terrazzo wall when picking his holes, to use the hand drill or scrape with a small cold chisel lightly glazed, tick to brick layers of ash at the end of the prescription can be hard, but not too hard, to avoid rejection of ground-surface phenomena or shock to the empty drum.
5.3 sanitary ware after steady load, in order to prevent parts are missing or damaged, such as zippers, blocking links and other materials, components should be installed before the completion of a unified.
5.4 Installing the fittings shall be protected to prevent surface damage and corruption throughout the ware ware porcelain.
5.5 test determines the flow should be checked before a floor drain water, the valve is closed, and then according to the layers through each room test, so as not to leak the renovation works that will suffer.
5.6 in the indoor access to the warm winter, various sanitary ware water must be clean. Traps should be no water, so as to avoid Frost crack ware and traps.
6 quality problems to be noticed
6.1 squatting rough, left and right tilt. Reason: stable when loaded, front and side trig in prison, coke residue after fill, no checking, plastering a bad repair, resulting in high water tank and it does not.
6.2 high, low, pull, pull the water tank is not flexible. Reason: high and low water tank interior accessories installation, three main components in the tank position is unreasonable. High water tank, pull the water tank should be placed on the side. When used so as not to interfere with each other.
6.3 parts chrome-plated surface is damaged. Reason: installation using a pipe wrench. Flat spanner or self-wrench should be used.
6.4 not on the toilet tank and back Center, elbow grimace. Reason: dash does not, it is not positive or stable steady load box back and safe.
6.5 off the floor around the toilet. Cause: the pipe reserved high stability not repaired before loading.
6.6 standing urinal from the wall gap is too large. Reason: dump size is not accurate.
6.7 ware overflow failure. Reason: no overflow drain nozzle.
6.8 water before clean up the dirt, and shall not take water to the dirt into the sewer pipe, so that the pipe plug.
6.9 do not use unfiltered, lime instead of lime cream stable install plumbing fixtures to avoid plumbing fixtures from splitting.
Quality of 7 records
7.1 product certificate (certificate of sanitary ware factory).
7.2 due sanitary appliances and fittings products from entering the site inspection records.
7.3 pipe dump location before installation inspection records.
7.4 open house inspection and appraisal records;
7.5 sanitary equipment installation engineering quality inspection and evaluation;

7.6 health apparatus water test records;