Wednesday, November 30, 2016

Installation technology of steel grid structure

1 scope
This technology is applicable to high steel grid structure in bulk, overall lifting of ground or aerial sliding method (upgrade) installation process.
2 construction preparation
2.1 materials
2.1.1 installation of steel grid structure of steel and materials, high strength bolts, welding electrodes, welding wire, flux, and so on, should comply with the design requirements and should have a factory certificate.
2.1.2 installation of steel grid structure with welding hollow ball, ribbed weld, bolt-ball. Semi-finished small spelling units, bars, as well as semi-finished products such as rubber, should comply with the design requirements and the corresponding provisions of the national standard.
2.2 the main tools:
Welding machines, oxyacetylene cutting equipment, wheel saws, bar cutting lathes, bar cutting head, steel tape measure, steel ruler, calipers, theodolite, level instrument, ultrasonic flaw detector, magnetic particle flaw detector, lifting equipment, lifting equipment, hammers, hydraulic jacks, chain, wire brush and other tools.
2.3 operating conditions:
2.3.1 install prior to inspection line check axis grid bearing and elevation. Grid axis, elevation location must comply with the design requirements and the relevant provisions of the standards.
2.3.2 Installing the front should check the column strength of concrete, roof concrete strength must comply with the design requirements and the State after the provisions of the relevant existing standards, in order to install.
2.3.3 use of aerial sliding method, should check the sliding rail pulley, levels of slip slope should comply with the design requirements.
Section 2.3.4, block installation, worktable when sliding, check table, sliding devices on the ground, and glide test.
2.3.5 using whole or partial lifting when Diego, should check the lifting equipment, lifting speed, lifting cranes, high closing and adjustment work well test, you must meet the requirements of construction organization design.
2.3.6 air when in bulk, should set up all-round scaffolding, and line the fulcrum position and elevation. Bolt the ball high when in bulk, should be designed to set up temporary stand, and provisional number of Fulcrum's position, after checking to make sure.
2.3.7 high bulk of temporary support magistrates or Jack is appropriate, such temporary Fulcrum can gradually adjust rack height. When the end of the installation when removing temporary supports, you can drop in synchronization between the fulcrum, subparagraph unloading.
3 operational processes
3.1 bolt ball corners square grid with high altitude in bulk:
3.1.1 technological process:
Line installation install bottom plane, inspection line network network install the bottom triangle filled inverted triangle network

Adjustment and fastening welding support installation roof CAP, acceptance

3.1.2 line, test line and basic checks:
Top 3.1.2.1 checking concrete strength. Check sample report, qualifying top in the sky line, test line.
3.1.2.2 packages provided top axis displacement, grid units installed on the grid provided support point location, dimensions, reinspect, upon re-inspection after check the axis position, elevation dimensions comply with the design requirements, to start the installation.
3.1.2.3 temporary location, quantity, fulcrum of the fulcrum height should be arranged, pivot the lower part should be properly reinforced, preventing grid point the local force is too large, rack sink.
3.1.3 install bottom flat grids:
3.1.3.1 a first cross between bearing installation, on the axis of the top good, center line, good elevation with a spirit level, errors should be corrected.
3.1.3.2 installed first across-down ball, Rod, forming vertical plane grid.
3.1.3.3 form a temporary stand, and ensure the bottom ball of parallelism, such as arching requirement should be found on the temporary stand base.
3.1.3.4 Setup first across the Web with the first ball, usually a ball Web of small units in place, with the bottom ball is screwed into the fixed.
3.1.3.5 installed first across the top chord, control grid size. Note that is screwed into the depth effects to entire truss deflections, should control the size.
3.1.3.6 check grids, grid size, check the grid vertical size and net loss of higher dimensions. If a discrepancy, you can adjust the temporary position to control the height of the fulcrum of grid size.
3.1.4 Installing filled inverted triangle meshes:
3.1.4.1 Web Unit assembled by continuous installation method.
3.1.4.2 from bearing started to install a bottom chord, check the thread quality, cleaning up the screw, screw, clean screwed into, also from the bottom chord of the first cross-also a bottom chord, composed the first grid penalty into the first section, closed the bottom chord of the first grid.
3.1.4.3 install inverted triangle cones, ball three small units (that is, a wound ball, a winding bar fight, two small abdominal helical rods unit) into the scene. The two diagonal supports on the bottom ball, tighten the top chord of the top, the top chord of gradually winding the ball close to the installed, is screwed into.
3.1.4.4 the tilt rod is screwed into the bottom ball holes, tighten, another slash can temporarily empty.
3.1.4.5 continue to install the bottom ball and rod (the second grid, down a ball is a ball). A rod is screwed into the bottom chord of the ball screw holes, one in the forefront installation, with a tilt rod connection is screwed into the horizontal bottom chord (second) installed into place, two each with screwed the ball into to form closed the bottom chord of the second grid.
3.1.4.6 process as described above to continue installing ball three triangular pyramid, installed vertically between the two inverted triangle cone winding rod and make it into one. Step by step, each installed a set of triangular pyramid, installing a vertical top chord, the top chord of two bolted into the truss chord grid closed also.
3.1.4.7 progressively installed to the support form a series of vertical triangular grid. Check the vertical size, check the truss deflections, check the pivot force.
3.1.5 installation factory chords are triangle meshes:
3.1.5.1 Web after installing the inverted triangular pyramid grid, the regular triangular pyramid grid installs.
3.1.5.2 installed down the ball and Rod ball rod form (that is, down ball and the bottom chord), the rod is screwed into the support holes.
3.1.5.3 install horizontal bottom chord, ball and bar closed square grid, check the dimensions. Can also take the form a ball (last quarter sphere and perpendicular two bottom chord grid closed the Quartet also installed).
3.1.5.4 install side diagonal Web members, single rod in place, screwed into the rise of the control grid.
3.1.5.5 continue to install the other side diagonal Web members, screwed into the bottom chord of the ball on both sides with the first ball to complete a set of regular triangular pyramid grid. Step by step installation to one side, until the supports so far.
3.1.5.6 each after the completion of a regular triangular pyramid, then install the check the winding square grid size error, gradually adjust and tighten bolts. Regular triangular pyramid grid installation, timely attention to temporary situations of fulcrum.
3.1.6 adjustment and fastening.
3.1.6.1 high bulk installation grid, should check the network quality measurements at any time. Check the bottom chord size and diagonal, check the wound size and diagonal, longitudinal length check grid, horizontal grid Vector length, high. The provisional support can also be adjusted without having to dismantle.
3.1.6.2 check grid overall deflection can bottom chord by chord size adjusted to control deflection.
3.1.6.3 network shall at all times during the installation process checks the sinking of the temporary stand, such as decline, should be strengthened to prevent sudden falling phenomenon.
3.1.6.4 Web inspection, adjustment, should back the grid of high-strength bolt fastening.
3.1.6.5 grid after high-strength bolt fastening, sleeve should be positioned on the small nut lock.
3.1.7 install roof Cap head:
3.1.7.1 weld Cap head screw into the wound ball.
3.1.7.2 in Hat head elements found on the slope for the installation of roofing sheets.
3.1.7.3 unused holes in the bolt and bolt sleeve, plugging the gaps between the bars should be to prevent rainwater seepage.
3.1.8 support welded and acceptance;
3.1.8.1 check grid size after passing checks whether the bearing positions on the axis, and the offset dimension. Grid size when installing cumulative error should be dispersed on both sides to prevent side bearing in place correctly, the other side bearing too large.
3.1.8.2 check rack elevation, rise, pivot grid elevation to four to each pivot should be standard size error.
3.1.8.3 check truss deflections.
3.1.8.4 dimensions are qualified, support weld.
3.1.8.5 support welded should have instructions. Grid bearings have a spring-type, slip, rubber mats. Support welded bearing performance should be protected. The intrusion of some protection against welding spatter, rubber pad when soldering, should prevent flame grilled wound pads, welding should be water cooled the supports at any time to prevent baking wound pads.
3.2 welding spherical surface installation closure method:
3.2.1 the process flow:
Line, test line install install install stereo nets grids chord grid grid integral lifting

Grid height folding network acceptance

3.2.2 line, test line:
3.2.2.1 the top line and the test line: axis and elevation marked, check the cylinder displacement; NET installation unit and the network support position, size, after reinspection is correct, the elevation, to be installed.
3.2.2.2 grid installation leveling the ground setting out, net frame spherical Fulcrum be placed line indicating the position and the ball.
3.2.2.3 of net frame spherical Fulcrum brick piers. DUN material can be steel supports, or brick piers plus a bit of pipe as net rack on bottom ball bearing.
3.2.2.4 each point marked elevation, such as truss arch request should be reflected at the bearing points, supported by different height of Arch of steel tube to complete the grid requirements.
A flat installation 3.2.3 steel grid:
3.2.3.1 ball has been and acceptance of welded ball, by specification, number in the install node, while ball better direction and location. Generally horizontal center line of circular welding seam the ball placed in the direction of the equator. Ribbed side in the last quarter of the top half of the ball.
3.2.3.2 places bar: good bar, arranged according to the specifications set forth in steel pipes. Placed before the Member, should check the specifications, size bars and Groove and weld seam gap, put the rod in between the two balls, adjust the clearance, solid.
3.2.3.3 plane assembled from the Centre lines of the grid, and gradually to show around, form a closed square grid, control size, together again around the grid, continued to expand. Note You should control the cumulative error, generally mesh with negative tolerance is advisable.
3.2.3.4 flat screen frame welding, welding to welding technology and frame welding should be well prepared in order to prevent deformation of plane truss.
3.2.3.5 flat screen frame welding according to the welding requirements, from center line of steel pipe under the left 20~30mm arc, welding to the right, leaning through welding, welding, uphill welding, brazing, welding position.
3.2.3.6 tube welded diagonal serrated weaving technique should be used for welding, preventing bites of meat.
3.2.3.7 welding after weaving to the survey center line on the tube, move on weld 20~30mm arc.
3.2.3.8 soldering is completed after the half, again from the right side of the center line of the underside of the pipe reverse arcs 20~30mm, welded to the left, the same as the above process, to continue after the top centerline forward, filling the crater, smooth weld lap in order to guarantee the welding quality.
3.2.4 rack main body Assembly:
Planar grid size, axis offset 3.2.4.1 check acceptance, check is correct, continue to assemble the main grid.
3.2.4.2 small spelling of a spherical four-bar units (one ball for the first ball and four-bar truss diagonal Web members) into the flat above the grid.
3.2.4.3 small spell units in place, should check the mesh size, rise, as well as small spell unit diagonal angle, position, angle was the first correction, correction must be qualified after the installation.
3.2.4.4 installation found is inconsistent spelling unit bar length, angle, cutting machine for too long poles should be cut and heavy Groove, re-seated checks.
3.2.4.5 need liner network, should be on the ball good spot welding liner. Small spelling units do not plane grid spot and temporarily also works with top chord before welding.
3.2.5 steel truss hip joint Assembly and welding:
3.2.5.1 in first plane the vertical bars of the network, check the wound ball vertical position and size are correct.
3.2.5.2 in first plane transverse bars of the grid, check the first lateral the ball position and size are correct.
3.2.5.3 by stereo small spelling unit diagonal Web members properly adjusted, so filled the vertical and horizontal bars and welded ball seats properly. Adjustment method of diagonal Web members is, to cut a long rod, chain opening angle of tilt rod can also be used, so rod is seated properly. Ensure correct chord grid size.
3.2.5.4 adjustment of the clearance and the clearance after passing the Basic, then spot weld the top chord.
3.2.5.5 solid after the winding bar and spot last quarter and slash the ball seam and connected firmly.
3.2.5.6 checked size, gradually moving forward. Truss webs and the installation of the truss top chord should be combined with each other.
3.2.5.7 grid floor after installation, should install a grid or block size acceptance.
3.2.5.8 grids must be welded to be hoisting operation is completed, weld appearance quality weld seam ultrasonic inspection report after passing to lift (lift).
3.2.6 web hoisting (lift):
3.2.6.1 overall hoisting steel grid before the inspection, weld inspection, acceptance of the upper bearing. After meeting the design requirements for the acceptance, before lifting.
3.2.6.2 overall hoisting steel grid should be selected before lifting point lifting rope should be tied to the bottom point, no hanging on the wound ball joints. If the grid stiffness in the lifting process is not also means strengthening suspended grid. Reinforcement was added several temporary reinforcement scaffold steel pipe, but should take into account this will increase lifting weights, increased load.
3.2.6.3 developed lifting (raise) program, debug installation (upgrading) devices. For lifting equipment such as hoists the rod, cable inspection, examination of the hydraulic circuit to ensure lifting (raise) a smooth, continuous, each hanging point synchronization.
3.2.6.4 load test (promoted): grid should be tried before the official lifting. Testing process is to hoist up, adjust the lifting point at the same time gradually from the ground. Try between the 200~300mm off the ground. The point after all, temporarily fixed, force the observation grid sections. If deformation can be reinforced in time, you should also carefully check whether the network frontiers of hoisting touching or hanging debris or temporary scaffolding, as there should be ruled out. Should also observe the bearing capacity of hoisting equipment, you should try to keep the lifting point synchronization to prevent tilting.
3.2.6.5 continuous lifting: when checking out, continuous lifting, on the premise of keeping citizens do not tilt should be continuously progressive lifting (raise). Fighting for the day in place, preventing winds.
3.2.6.6 gradually in place: truss lift is in place, should gradually reduce lift (lift) speed to prevent lifting.
3.2.7 high closure:
3.2.7.1 grid height in place, adjust the distance between grid and support, and to that end should be installed above the grid sets used for horizontal adjustment of the chain.
3.2.7.2 check overall elevation grid, preventing the level of unevenness, such as it is difficult to exclude, from the side elevation to be put in place, adjust the horizontal chain, high qualified end in place.
3.2.7.3 height and horizontal distance from the first qualified at one end, insert the connection, connecting rods can be amended at any time, heavy Groove, but fixed Rod length is not too big, you should try to keep the original size. Adjustment is made while tensioning chain, loosen chain on the other side, distances from the right step by step.
3.2.7.4 should be gradually adjusted side bar after all the solid, relaxed side chain, continue to fine tune elevation on the other side of the grid. Can a small amount of lift or down control elevation. Note at this time adjusting the lifting or descent should be a small amount of, step by step, not continuous. Adjustments should also be observed already in place fixed side of the grid to prevent welding.
3.2.7.5 Web side elevation adjustment, chain tensioning distance, initial checks in place, right after, insert the stopper, fixing.
3.2.7.6 solid grid bars around the insertion point. Attention welding rod at this time that there is a slope, the grid Center is slightly higher than support. Result grid when the effects of lifting from the Center, once the unloading will drop slightly, to prevent deformation and should enhance the margin of 3~5mm ahead.
3.2.7.7 solid after the bars closed around the grid point, check the grids ministries and in order, carried out according to welding process welding.
3.2.8 Web acceptance:
3.2.8.1 network acceptance is conducted in two steps, the first step is that grid lifting State of acceptance; the second is network independent loading, and handling during loading inspection.
3.2.8.2 check the weld appearance quality of space truss, shall meet the design requirements and standards requirements.
3.2.8.3 four frontier rod (the closing of welded pipe), in ultrasonic flaw detection of welding 24h reports and repair records.
3.2.8.4 check grid bearing weld quality.
Lifting equipment unloading 3.2.8.5 steel grid. Observation of deformation of the grid. Grid lifting parts of unloading should be slow, synchronized, to prevent local deformation grid.
3.2.8.6 chain to be closed separately removed and restoration of steel grid structure of natural state.
3.2.8.7 check the grid bearing force; check the arch truss or arch.
3.2.8.8 check the rack overall dimensions.
4 quality criteria
4.1 project shall comply with the following requirements:
4.1.1 high bulk installation of grid structure, accessories and elements of the node, should comply with the design requirements and the current national provisions relating to standards. Accessories and deformation of the rod must be corrected.
Inspection method: Visual check and inspection certificates of quality, factory certificate or test report.
4.1.2 top level Datum axis, columns and concrete strength, must comply with the design requirements and the current national provisions relating to standards.
Test method: check the survey records and reports.
4.2 Basic project shall comply with the following requirements:
4.2.1 appearance quality of truss nodes and elements:
Eligibility: clean the surface without welding scar, mud and sand, dirt.
Good: the surface is clean, no welding scar, sediment and dirt.
Check amount: according to the number of nodes check 5%, but should not be less than 5 nodes.
Inspection method: Visual check.
4.2.2 grid structure weight and roof deflection on completion:
Qualified: measuring deflection of 1.12~1.15 times the average design values.
Excellent: measuring deflection of an average of 1.12 times times the design value.
Check size: small-span truss structure measuring down the central spot; medium-span truss structure measuring the bottom chord of the central point and the bottom chord span four equal points.
Inspection method: with a ruler and level checks.
4.3 allowable deviation shall meet the following requirements:
4.3.1 high tolerances for bulk installation of grid structure project and the test method should meet the requirements of table 5-23.
Total grid structure assembling method for the determination of allowable deviation and table 5-23
Tolerance (mm) method
±L/2000
± 30.0
L/3000
30.0
The supporting grid
Adjacent pedestal height difference L/400
15.0
Supports maximum height difference 30.0 with ruler, level check
Multipoint support grid
Adjacent pedestal height difference L1/800
30.0

l2/1000
5.0
Note: 1. L is the vertical length.
2. L1 for the adjacent seat spacing.
3. L2 as the rod length.
4.3.2 approach installation of grid structure of the allowable deviation and the test method should meet the requirements of table 5-24.
Check amount: total inspection.
Apart from the high altitude in bulk, and other methods to install the allowable deviation of grid structure and test method for table 5-24
Tolerance (mm) test method

L/3000
30.0

L1/400
15.0
Pedestal height
L1/800
30.0 with ruler and level checking
Supports maximum height difference 30.0
Note: 1. L truss spans.
2. L1 for the adjacent seat spacing.

5 finished product protection
5.1 grid once installed, when removing the shelves should note the synchronization step by step disassembly to prevent stress concentration, making local distortion grid, or distort the local grid.
5.2 installation of steel grid structure after the end of time brushing paint. Bolt-net card after the installation, you should check that the bolt holes on the ball is closed, apply Putty to holes and paint tube after filling the gaps, and prevent the penetration of moisture, rust, Rod threaded the ball.
5.3 after the installation of steel grid, finished product rack protection, not above the grid focus stacking objects. Such as when there is a need to install roofing panels, purlins, and should also not overloading the separate pieces.
After installing 5.4 steel grid, such as with a crane when lifting or roof Purlin, should have happened, no impact grid grid deformation.
6 quality problems to be noticed
6.1 steel grid during installation, set to the temporary pivot should be taken seriously. Prior to installation, arranged for pivots and pivot level, temporary stand to keep the grid even by force, the rod force, should also pay attention to an interim point basis (scaffolding) stability, must be taken to prevent Fulcrum sinks.
6.2 temporary supports blocking best to Jack so that you can gradually adjusted during the installation process. Note the temporary adjustment of the pivot of a point should not be adjusted, also taking into account the force evenly around the grid, sometimes local adjustment will allow individual members, bending deformation.
6.3 temporary stand disassembly caution protection should be synchronized in group, in descent, decreasing range not too large, should be step by step section proportional decline in stages, or with less than 100mm per step step of demolishing the support-point drop.
6.4 welded spherical grid structure of the installation when welding, should take into account the deformation of welding contraction, especially lifting rack and bar space truss, installed on the ground, to control the welding before welding deformation and shrinkage. Steel mesh welding, welding points (heating surface) plane grid on the upper side, and very easy to make structural deformation due to unidirectional heat. General deformation law for grid structure after welding, will gradually free up around the bearings, if deformation when the springing of the original plan will be offset. As the original regardless of the arch, made the large deflection value produced, affects the quality of inspection requirements. Therefore should be considered in the construction welded spherical grid structure to a single heat distortion.
6.5 Web after installation should pay attention to support forces, some bearing allows welded shut, some bearing should be the free end, some bearing limit and more, so the grid supports the construction should be carried out in strict accordance with the design requirements. Bearing plate, limit boards should be required to order, method of installation.
7 quality records
This standard shall meet the following quality records:
7.1 bolts, welding-ball, high-strength bolts of material proof, factory certificate, a variety of carrying tensile test report.
7.2 the material certificate and retest report of steel.
7.3 material proof of welding and coating materials, factory certificate.
7.4 sleeve, Cone and plate sealing material reports and factory certification, such as steel, material weldability test report.
7.5 steel pipe with cover plate, cone composed of Rod bearing test report.
7.6 steel grid activity (or sliding) bearings should be factory-qualified certificates and test reports.
7.7 Welder certification, should have the appropriate welding station, the corresponding welding material and other projects.
7.8 Installing the grid after the overall size, springing and acceptance data.
7.9 weld inspection and acceptance record.
7.10 weld seam ultrasonic inspection reports and records.

7.11 coating (including corrosion protection and fire safety) construction inspection records.

No comments:

Post a Comment