1 scope
This technology is applicable to
horizontal, vertical, column of the fan coil and induce standard products for
installation works.
2 construction preparation
Requirements 2.1 materials and equipment:
2.1.1 the use of fan-coil units, induction
unit, equipment should have a factory certificate or qualification documents.
2.1.2 structure of the fan-coil, induction
unit equipment type type, installation, export orientation, intake location,
the design and installation requirements.
2.1.3 equipment installation by the use of
ingredients and auxiliary materials, model should comply with the design
requirements and have a factory certificate.
2.1.4 rotary hammer, hand drills, wrenches,
socket wrench, hacksaw, box spanner and hammer, bench vise, taps, threading
plates, level, wire pendant, hand pump, steam pressure case, welding tools.
2.2 operating conditions:
2.2.1 fan coil units, induction unit and
main and auxiliary materials have arrived at the scene, install the required
tools have been prepared, and installed former test sites, water and power
supplies.
2.2.2 structural engineering construction
is completed, finish the roof waterproof layer, indoor walls, floors finished.
2.2.3 installation dimensions comply with
the design requirements, pipe of the air conditioning system is installed,
connected to the fan-coil tube reserve pipe location elevation meets the
requirements.
3 operational processes
3.1 process:
Preflight preparation → → motor check the
condenser pressure test the trial go → → suspension →
Installation of fan coil induction piping
installation → connection → test
3.2 fan coil in installing the front should
check each pedestal electrical engineering hull and surface exchangers has no
harm, rust Eclipse etc. blemish.
3.3 fan coil and induce to power should be
used for each test, mechanical part of friction, electrical parts must not leak
away.
3.4 fan-coil and induction unit-by-water
test, test strength should be 1.5 times working pressure, pressure was observed
after 2~3min no seepage and leakage.
3.5 horizontal fan-coil and hoisting
induction unit, hanger installation neat and firm, and correctly positioned.
Hangers should not be free swinging, suspenders attached to the tray
application double nut fastening citizen.
3.6 induce quality checks must be
considered before installation, check the following:
3.6.1 connection does not loosening,
deformation and fracture condition; nozzles cannot fall off, blocked.
3.6.2 plenum head gap sealing material,
without cracks and falls off; the primary air regulator must be flexible,
reliable, and transferred to the full open position.
3.7-induced work inspected according to the
design requirements for models in place of installation, and check the nozzle
type is correct.
3.7.1 concealed horizontal induction unit,
hangers should be fixed, and ease of disassembly and repair.
3.7.2 induction unit and an air hose
connections should be tight to prevent leakage.
3.7.3 induction hose joint direction and
return air headed, the design requirements. Vertical double-sided air induction
unit to facilitate the return, should stay above 50mm against the wall space.
Horizontal double air induction unit make sure floor side to leave enough
space.
3.8 medium hot and cold water pipes and the
fan coil, induction of straight pipe or copper tube is connected, take over
should be straight. Tightening wrench jammed when the six-party joint to
prevent damage to copper pipe. Condensate pipe should be flexible connections,
hose length is not more than 300mm materials should be treated with clear
plastic tubes and hose clamps tighten leakage is strictly prohibited, the slope
should be correct, condensed water should flow to the specified location, water
should be free of stagnant water.
3.9 fan coil units, induction unit with hot
and cold media connection, should flush the pipe system of sewage and then
connect to prevent blocked heat exchanger.
3.10 concealed horizontal fan-coil, ceiling
should be left active inspection door, easy unit disassembly and maintenance as
a whole.
4 quality criteria
4.1 project:
4.1.1 fan coil units, induction unit
installation must be stable and strong.
Inspection method: with a spirit level and
cable fall measurement.
4.1.2 fan coil units, induction unit
connection to the water pipe leakage is strictly prohibited, condensate pipe
slope drainage requirements must be met, with air and return air connections
must be tight.
Inspection method: standard, observe
inspection and test records.
4.2 Basic project:
Fan coil units, induction unit air outlet
connection tight no leakage.
Inspection method: Visual check.
5 finished product protection
5.1 fan coil and induction unit sent to the
scene to take measures to keep it neatly. Rain and snow prevention measures.
5.2 when winter construction, fan-coil
water discharge immediately after the pressure test must be clean to prevent
freezing equipment.
5.3 installation of fan-coil induction must
be shipped with, and note to intersect with other types of work product
protection to prevent chipped.
5.4 concealed vertical fan coil, installed
after installation should cooperate with civil protection cover. Roofing should
take protective measures prior to spraying, protect installed equipment, keep
them clean.
6 quality problems to be noticed
Quality problems should be paid attention
is shown in table 4-31.
Common quality problems and control
measures in table 4-31
Ordinals often quality control measures
1 Winter freezing water exchanger test
pressure must be placed on the surface clean to prevent freezing
2 fan coil transport easy to hit when
handling single code light light discharge
3 fan-coil unit air coolers clogging the
fan coil and pipe connections without flushing sewage shall not be put into
operation in case of jams
4 fan-coil water clogging the fan-coil knot
should clean up before running with debris in the pan to ensure the condensate
flow
7 quality records
7.1 air quality inspection and assessment
of manufacturing and installation project tables.
7.2 out of checking and cross-checking
records.
7.3 inspection projects and inspection
record form.
7.4 entry equipment inspection records.
No comments:
Post a Comment