Semi-rigid laying technology for fire retardant plastic dark

1 scope
This technology is applicable to General electrical conduit wiring of lighting engineering in the civil, not at high temperature places, places vulnerable to mechanical damage and laying of the roof.
2 construction preparation
2.1 materials requirements:
2.1.1 semi-rigid plastic pipe and fittings must be made of fire-retardant treated materials. Plastic wall should be spaced not more than 1M the continuous flame marks and factory standards and product certification. Pipe wall thickness uniformity, no cracks, holes, bubbles and deformation of tube and so on. Semi-rigid plastic pipe shall not be stored at high temperatures and open spaces stacker.
2.1.2 distribution box: for the two certified manufacturers, product certification of products.
2.1.3 switch box, outlet boxes, lamp boxes, junction boxes, plastic boxes should look neat, complete knockouts, no cleavage, and so on.
2.1.4 galvanized material: flat steel, round steel, wood screws, machine screws, wire, etc.
2.1.5 supplementary materials: paints, adhesives, cement, sand, and so on.
2.2 the main tools:
2.2.1 line pencil, tape measure, level, barrels, buckets, ash, ash shovel.
2.2.2 hammer, cut son, hacksaw, saw blades, knives, rasps, etc.
2.2.3 bench drill, drill, drill bits, wood drill tool bag, tool box, high stools.
2.3 operating conditions:
2.3.1 closely integrated civil construction, according to the wall of the building structure (such as a brick wall, brick wall of aerated) better horizontal and wall thickness of lines, installing boxes, cartons and pipe.
When construction of civil structures 2.3.2, templates, sliding formwork of concrete wall, be embedded in the process of reinforcement set and pipe card at the hidden after inspection, and concrete construction.
2.3.3 aerated concrete floor slab, plate with a circular hole, good lifting floor boards shall be adjusted in time to meet the construction joints for piping.
3 operational processes
3.1 process:
Line box fixed positioning sweep for pipe laying pipe Threading line

3.2 line positioning: according to determine the horizontal and the thickness of the wall line map, determine the location boxes, cartons and embedded parts; rows into columns of boxes, cartons should be telephoned or cross lines to determine exactly where the boxes, cartons.
3.3 box, fine is fixed:
3.3.1 block wall stable box, box. According to tick the box, bin location line hole, hole size slightly larger than box, box is appropriate. Clean up the hole, water will wet hole, and then use the strength grade of cement mortar not less than M10 stable box, box.
After picking holes in hollow block wall and broken blocks of cement mortar hole plugging, unstable box, box.
Fixed in 3.3.2 reinforced walls, floor boxes, cartons:
3.3.2.1 wear reinforced box fixed directly on the bars.
3.3.2.2 with machine screws on the box, the box is fixed on flat steel, flat steel will be fixed on the steel.
3.3.2.3 precast floor slab stability buried conduit Circular box: prefabricated plates with a circular hole, aerated concrete floor lamp box hole, picking holes in the floor below the bottom up, above the hole in the floor above the hole. Installed the card in the box rail or car, pallet installed in the floor below, water will wet hole, and then use the strength grade of cement mortar not less than M10 steady buried the box.
3.3.2.4 stability of the sliding formwork for concrete wall box, box: reserved box, box sets, and then remove the box, box sets, stability at the reserve holes buried boxes, cartons.
3.4 tube:
3.4.1 tube requirements:
3.4.1.1 semi-rigid plastic pipe casing bonding connection can be used, sleeve length shall be not less than three times the tube diameter; the interface should be located in the center of the casing pipe, connection joints applying adhesives firm bonding.
3.4.1.2 when laying pipes, should try to reduce bending when lines line segments longer than 15m or right-angled bend when more than three should be added indirect box.
3.4.1.3 pipeline after deformation joints, due compensation devices can move freely.
3.4.1.4 tick Groove with tube, not allowed to mark cross-slot and tick off steel; aerated concrete panel only allowed rejection of Groove-along the seams.
3.4.1.5 sliding vertical pipe sections should not have joints within the template.
3.4.1.6 tube boxes, box, tube should flush pipe Show box, boxes should be less than 5mm, and a tube of a hole, hole size should coincide with the outer diameter of the tube.
3.4.2 block wall tube:
3.4.2.1 walls should be combined with civil engineering, semi-rigid plastic pipe laid on the wall upward tube nozzle should be well plugging and temporary support rod (steel or wood) along the direction of laying the tubes started. For making boxes, cartons smooth, accurate elevation, to laying pipe to dump box, 100mm box location, wall built after the then pipe steady box, box.
3.4.2.2 tick Groove with tube should be on each side of tank line, cold chisel tick. Wall of aerated concrete used saws saw blades on both sides and then, Groove width and groove depth is larger than the outer diameter of the pipe 5mm is appropriate. Apply pipe every 0.5M with an iron nail, fine wire pipes fixed well. Then use strength grade of cement mortar not less than M10 protection thickness should not be less than 15mm.
3.4.3 prefabricated pipeline laying on the floor:
3.4.3.1 prefabricated laying pipe on a plate with a circular hole, every 0.5M, away from the lamp holder cartridge 0.15m fine wire and plate hole fastening firmly fixed, and conduit Circular box buried solid stabilization with cement mortar.
3.4.3.2 to partition reserved tubes should not be too long, should block well pipe.
3.4.3.3 the pipe cement mortar to protect against mechanical damage.
3.4.4 pipeline laying in concrete walls or floor:
3.4.4.1 pipelines should be laid in the midst of two layers of steel, it tube into the box should be blocking good pipe, blocking good boxes. Line about every 0.5M from within 0.15m of the box with a fine wire and rebar tie firmly.
3.4.4.2 pipe not too long into the wall with reserved and well pipe plugging up tube steel stir up down tube can be reserved and excluded hole in the wall is vertical (approximately 100mmx50mm), or embedded casing after removal, under the tube.
3.4.4.3 when sliding the template construction, by the switch box or junction box to the light pipe can be placed within the bracket wall section, after sliding mode, remove the pipe, and when the roof to light.
3.5 and tube lines:
3.5.1 after the tube, after the construction of walls, floor (concrete works after the removed template), should be carried out promptly and so Kwun Wat. Gordon in the process pipeline and construction plans must be checked, handle the fault in the pipeline.
3.5.2 so Kwun Wat method should be used, namely cloth fixed to the one end of the line, from pulling on the other end of the pipeline, and clear the debris, water pipe. Gordon after the nozzle should be blocking well closed boxes.
4 quality criteria
4.1 project:
Semi-rigid plastic pipe must be made of fire-retardant treated materials, oxygen indices should be above 27%, the material and the applicable provisions must comply with the design requirements and specifications.
Test method: observation of concealed works of checks or check the record.
4.2 Basic project:
4.2.1 connection close tube smooth, cover more than 15mm.
Inspection method: Visual check, check concealed work records.
4.2.2 box, box is set up correctly, reliable and pipes into the box, the box straight, box, box showing length should be less than 5mm.
Inspection method: observation, standard checks.
4.2.3 piping a building deformation joints should set compensation, compensation device of movement.
Inspection method: observation on concealed works of checking and inspection records.
4.3 allowable deviation:
Pipeline laying and installation of boxes, cartons tolerances shown in table 3-4.
5 finished product protection
5.1 when you pick your slot holes, do not push too hard, so as to avoid breaking around the walls. Portal is not easy to tick too large, too broad and do not cause structural defects.
5.2 protect tube ends immediately after, when other types of operations, care should be taken not to pipe smashed and trampled.
5.3 in the concrete, aerated when picking holes in the plate, be careful not to tick off bar, picking holes should be drilled first hole, then spread
Hole, hit with a sledgehammer by the above hole is strictly prohibited.
When civil engineering concrete 5.4 should be sent for care, to prevent the pipe displacement or against mechanical damage.
6 quality problems to be noticed
6.1 piping exposed phenomenon, or a lack of protective 15mm, pick your slot to ensure depth and pipes will be fixed in a timely manner, and then protected with cement mortar.
6.2 hold and the embedded box, box has skewed, coordinates are not allowed, the mortar is not full, and so on. Find location when holding boxes, cartons, to inject the right amount of cement mortar, then the fall line alignment, then around the box, box with cement mortar filling the gap.
6.3 concave flat tube simmering bending over and bend RADIUS must be greater than or equal to 6D. Simmering bending operations and fixed and protected in a timely manner as required.
6.4 line doesn't make sense. The tube is easy to fall into junk on and, therefore, shall promptly nozzle blocked well. Other types of work, should be careful not to touch the loss finished laying the pipeline to avoid pipe blocked.
7 quality records
7.1 semi-hard flame retardant plastic pipes and accessories, quality certificates and oxygen index test report form.
7.2 distribution box factory quality certification, other provinces and cities to Beijing should be "two-part" approved production of acceptable proof.
7.3 technology to give the low-down, hidden inspection, inspection, checking and cross-checking records.
7.4 semi-hard flame retardant plastic fill pipe and pipe thread engineering quality inspection and assessment of tables concerning the distribution of relevant content.

7.5 design changes, record of negotiation and completion chart.