1 scope
This technology is applicable to general
industry and civil construction brick, outside the brick mold brick masonry
engineering and anti-earthquake construction post.
2 construction preparation
2.1 materials and equipment:
2.1.1 brick: variety, strength class must
conform to the design requirements, and factory certification, test. Dry wall
brick color uniform, neat corners.
2.1.2 cement: varieties and markings should
be based on location and environmental conditions in which the masonry, use No.
325 of ordinary Portland cement and slag Portland cement.
2.1.3 sand: sand, preparation of M5 mortar
with sand clay content of not more than 10%,M5 mortar sand clay and above does
not exceed 5%, 5mm aperture of sieve sieve before use.
2.1.4 admixtures: lime maturing period of
not less than 7d, or fly ash;
2.1.5 other materials: wall tie bar and
embedded parts should be brushing preservatives, wood bricks, and so on.
2.1.6 major machines; should be equipped
with shovels, digging adzes, trowels, a fan and supporting plate, wire pendant,
a small white line iron level, tape measure, ruler, counting rods, small
bucket, ash grooves, grapple bucket, broom, etc.
2.2 operating conditions:
2.2.1 completion of backfill in outdoor and
room, trench cover is installed.
2.2.2 finished ground and foundation
engineering hidden procedures.
2.2.3 according to elevations well cement
mortar damp proof course.
2.2.4 axis wall elasticity and good lines,
according to approach the actual size of the brick, pop-up Windows and doors
opening line, line meets the design requirements of experience, through
pre-screening procedures.
Design elevation 2.2.5 request I be number,
counting Rod spacing to 15~20m is appropriate.
2.2.6 mortar by laboratory test, testing of
ready mortar (6 as a set).
3 operational processes
3.1 process:
Mortar mixing
↓
Ready → water → → brick masonry brick
wall test assessment
3.2 brick water: clay bricks in masonry
must water the day before humid, General water into the brick-sided 1.5M is
appropriate, water 10%~15%, construction must not be used at room temperature
on the brick wall; the rainy season reached saturation point of water shall not
be used with brick walls; winter watering with difficulty, must be
appropriately increased mortar consistency.
3.3 mixing of mortar: mortar mix should be
used to weight ratio, measuring accuracy ± 2% cement, sand, gypsum mortar
control within ± 5%. Suitable for mechanical mixing and stirring time no less
than 1.5min.
3.4 build brick walls:
3.4.1 unit masonry method: masonry
generally Shun Ding (Man Ding, full article), diced plum or a three-building
method. Brick column should not be used to build four weeks after filling the
heart of building method.
3.4.2 late laying brick pile (dry-laid
brick): General first-story brick pile at the end of the wall, rows of small
brick two Gables, eaves before and after vertical wall tiles. Line the jambs
according to play position, carefully check the wall between Liao, stack size,
their length in line with rows of brick module, if it does not meet when the
module, move around the position of the door. If there are broken live, seven
separate or small brick should be ranked in the middle of the window, with a
pilaster or other inconspicuous parts. When you move the window position,
should pay attention to heating and plumbing pipe installation and when doors
and Windows are not affected. In addition, should also be considered when
laying brick on brick wall on the top of the window when closing the door does
not appear broken. So when laying brick must do all things considered, when the
brick wall the first row before and after skin, consider dumped Windows and
masonry brick, window corners must be seven is to live separately.
3.4.3 optional brick masonry drywall edges
should be selected in order, any bent, cracked, uniform color, basically the
same specifications of the brick. When hit with loud, roasted over the fire color
variants available in base and does not affect the appearance of the brick
wall.
3.4.4 wheel angle: bricklaying should be
preceded by angle, wheel angle not more than five at a time, new Horn, crane,
in a timely manner. If there is deviation in time dressing. To carefully
control point counting the brick layer and elevation of the pole, control the
mortar joint sizes, uniform horizontal mortar joints. Good horns and reviewed
again, flat and vertical in full compliance with the requirements, and then hang
drywall.
3.4.5 hanging line: masonry a brick half
wall must double hanging line, if long wall several per capita using a root
pass line, Middle should set several extension points, small line to pulled
tight, each layer brick are to thread see flat, makes level sewing uniform
consistent, flat through Shun; masonry a brick thick mixed water wall times
used offside hanging line, can care brick walls on both sides flat, for Xia
road process control wipe gray thickness lay based.
3.4.6 brick: bricks should be used a shovel
ashes, a brick, a squeezing rubbing "31" masonry method, that is full
of shops, extrusion method. Masonry bricks should be placed flat. Were holding
hands high, the wall; lower were holding hands, the wall is back. Masonry must
be used with the line, "with the line, with ribs under left and right
adjacent to the flat". Thickness of horizontal mortar joint width and
vertical mortar joints is generally 10MM, but should not be less than 8mm, and
should not be greater than 12mm. In order to ensure dry wall seam vertical, and
did not tour the small joints, when you are finished building one step higher,
suitable for every 2m space in small brick vertical cord to position playing
the two vertical vertical line can control You Ding seam. In the course of
operation, has to carry out a self-test, if biased, should be corrected at any
time. Hit the wall is strictly prohibited. Dry wall is not allowed to have
three separate, any of the wood in the upper comes alive, out of joint. Masonry
mortar mixed with used mortar must be used up within 3h, cement mortar must be
used up within 4H, you may not use the night mortars. Dry wall should be built
with masonry, and
With seam, seam depth of 8~10MM and depth,
the walls clean. Ash mixed with water wall with masonry with the tongue
scraper.
3.4.7 Cha: exterior wall corners should be
built. Inner and outer wall junction must remain oblique Cha, Cha 2/3 of length
should not be less than the wall height, Cha must be flat and smooth. Segment
location should be in slot or window a quarrel, partition walls or columns are
not built at the same time, may keep the Cha and Yang embedded tie bar. High
along the wall according to the design requirements of each embedded φ 6 50cm
steel 2 ribs, cut into the length starting from the wall at Cha, generally not
less than 50cm on each side, plus 90 ° hooked at the end. Construction hole
should also be required to remain above horizontal tie bar. Wall vertical brick
skew tunnel jam.
3.4.8 reserved holes and wooden bricks wall
tie bar: wooden bricks embedded should head out, big, according to opening
height. Cave high in the 1.2m, put 2 pieces on each side, high l.2~2m, 3 pieces
on each side, high 2~3M, 4 on each side, embedded parts of the wooden block in
the hole above or below four bricks, evenly distributed. Wooden block to get
embalmed. Steel doors and Windows installed reserved hole. Hard frame formwork,
heating and plumbing pipes, according to design requirements should be set
aside, not pick your cut. Wall tie bar position, specifications, quantity,
spacing shall be retained according to design requirements should not be
misplaced, left.
3.4.9 pad installed beams, beam: when the
beam, beam pad is installed, its elevation, location, and type must be
accurate, gray full. Ash thickness exceeding 2cm, concrete paving with bean,
beam installation, is supported at both ends should be consistent in length.
3.4.10 structural column procedure: where
there is no structural columns works in front of the brick, line according to
the design drawings of constructional column and reinforcing structural column
straightening out straight. When the brick masonry, connected with the
structural columns at the Cha built horse teeth. Each size should not exceed
the height of Ma ya Cha 30cm (that is, five tiles). Ma ya Cha should back off.
Tie bar placed according to design requirements, design requirements, the
General 50cm set 2 pieces along walls of φ 6 horizontal tie bar on each side
wall should not be less than 1M.
Winter construction of 3.5: in anticipation
of continuous 10d by average temperatures below + 5 c or when the minimum
temperature lower than-3 ° c on the day that is entering the winter
construction. Winter use of brick, requires that clears Frost before laying.
Cement should be treated with ordinary Portland cement, gypsum mortar
antifreeze, has been behind the Frost to melt can be used. Shall not contain
more than 1cm block of frost in the sand, material when heated sand heating not
heating water not more than 80 ℃ 40 ℃. Brick is due water, temperature, negative temperature that should
be stopped. May be appropriate to increase consistency of mortar. Should not be
used without Portland cement mortar in winter. When mixed with salt in a
mortar, Baume hydrometers check the concentration of salt solution. But for
insulation, thermal insulation or decorating projects with special requirements
shall not be mixed with salt, mortar, using temperature should not fall below +
5 ° c, mixed content should be consistent with provisions of the winter
programme. When mixed with salt, mortar and masonry reinforcement should be
done in advance in anti-corrosion treatment, coating paint two.
4 quality criteria
4.1 project:
4.1.1 brick variety, strength class must
meet the design requirements.
4.1.2 variety and strength of the mortar
should comply with the design requirements. The same group, same strength grade
mortar sample average compressive strength of not less than the design
strength, the strength of any group block value is greater than the design
strength of the bottom 75%.
4.1.3 masonry mortar must be compacted
full, solid brick masonry mortar for horizontal mortar joints full of not less
than 80%.
4.1.4 wall corner straight Cha is
prohibited, other temporary break Cha practices must comply with the
regulations.
4.2 Basic project:
4.2.1 masonry joints, brick, Duo Pack heart
building law: no seams between walls and dry wall surface of the window; mixed
with water wall of every room (Office) 4 bricks-free joints (seams brick refers
to the upper and lower skin lap length is less than 25mm).
4.2.2 brick masonry mortars at the Cha
should be dense, straight joints, bricks, each Cha site thickness of horizontal
mortar joint is less than 5mm or clear defects does not exceed 5.
4.2.3 embedded reinforcement of quantity,
length comply with design requirements and specifications provided, retaining
pitch deviation of not more than one brick;
4.2.4 column retained the right, MA ya Cha
to step back into the straight up and down, and residue clean mortar.
4.2.5 drywall Group built properly, sew
smooth, scraping seam depth appropriate, consistent, Leng corners neatly, the
walls are clean and beautiful.
4.3 allowable deviation, as shown in table
6-2.
Table 6-2
Tolerance (mm) method
1 axis offset 10 using a theodolite or
cable and check
2 base and the wall and top level ± 15
level foot check
Check every 5 2m supporting plate
3
Vertical ≤ 10m 10
>10m 20 with Theodolites or hanging and
foot check
Dry wall, column 5
Surface flatness water wall and column 8 2m
m on foot and wedged feeler Gage check
Dry wall 7
Horizontal mortar joints straight mixed
with water wall 10
6 cement, mortar joint thickness (10
cumulative number of bricks) ± 8 and counting Rod size check
7 20 hanging drywall You Ding joints and
standard checks, subject to the first brick at the bottom
Door hole width ¡à 5
(Rear) door height +15 (-5) foot check
9 reserved column (width and depth) ± 10 '
check
10 outer walls and lower window offset 20
using a theodolite or wait for check, subject to the window at the bottom
5 finished product protection
5.1 wall tie bar, anti-earthquake
construction post reinforcement and formwork concrete wall with steel bars and
a variety of embedded parts, heating and plumbing, electrical, pipeline and so
on, should be protected, not arbitrarily demolition or damage.
5.2 mortar consistency should be
appropriate, walls should be protected from splashed mortar wall surface.
5.3 at hanging scaffold platform or install
large template, command staff and the crane driver to command and operation
carefully to prevent collision has built a brick wall.
5.4 high frame around the inlet,
applications, such as plastic or wood cover, keep the walls clean.
5.5 wall of floor or roof panel and the
column is not already installed, when you may encounter when Gale, temporary
support measures should be taken in order to guarantee the stability of walls
in the construction.
6 quality problems to be noticed
6.1 the foundation wall and upper wall
dislocation: the foundation brick pile bottom to the right, closed back angle
to be equal on both sides, back to the wall to check for the right axis and the
line before, such as smaller deviations can be corrected at the base site, not
in moisture-proof layer above or back out.
6.2 water wall You Ding go sewing: row
brick Shi must put State sewing row uniform, masonry finished a step frame
height, each across 2m spacing in d brick State stared blankly at with
supporting Board hanging straight play line, two step frame to Shang continues
to hanging straight play pink, by end of column Shang all seven separately of
length should keep consistent, upper points window location Shi will with Xia
window keep vertical.
6.3 mortar joint sizes are not uniform:
State level to ensure consistent, mortar joints to master even when the wheel
angle, brick little line taut, prevent a layer of loose, a layer of wire
tightly.
6.4 window upper vertical seam: drywall
when laying brick and Duo line, to make the walls between Windows, live, live
in the Middle, or not be visible, when in the first row on the brick masonry
beam, are not free to live.
6.5 wall bulge: the brick mold at the wall,
in-wall, earthquake-resistant columns on either side of the window upper,
middle and lower left 6cmx12cm through hole, wood on the wall outside the
earthquake-resistant columns template, with a TURNBUCKLE with a large template
securely attached. Stratified placement of concrete, vibrator must not directly
touch the outside wall. Three 12cm brick wall outside floor beams should also
be seriously strengthened. As vibration found brick wall is bulging, was built
should be promptly removed.
6.6 mixed with water wall roughness: Ash
does not scrape the tongue, used two quarters collection, resulting in seams; a
thick brick wall back larger deviations; brick split-level caused wall screws.
Two quarters should be spread on the walls of the larger surface. Ground floor
or first floor check counting poles of brick elevations and floor to prevent
top wall masonry screws. One brick thick walls should be the right-hand side
thread.
6.7 structure column at masonry not meet
requirements: structure column brick walls should masonry into big horse teeth
Cha, set good pulled knot reinforced, from column feet began sides are should
first back into, dang chisel deep 12cm Shi, should be catchy a skin into 6cm,
again Shang a skin into 12cm, to guarantee concrete pouring Shi Shang angle
dense structure column within of landing gray, and brick slag debris must
cleanup clean, prevent concrete within Clip slag.
7 quality records
This standard shall meet the following
quality records:
7.1 material (brick, cement, sand, steel,
etc) certificate and retest report of the factory.
7.2 mortar summary test report.
7.3 quality inspection and assessment of
the project.
7.4 hidden inspection, inspection records.
7.5 winter construction records.
7.6 design change and record of
negotiation.
7.7 other technical documents.