1 scope
This technology is applicable to general
industrial and civil building electrical installation engineering 10 (6) kV
outdoor terminations made of oil-paper insulated cable.
2 construction preparation
2.1 devices and materials requirements:
2.1.1 cable terminal type, specification
should conform to the voltage level, environment and design requirements.
2.1.2 cable terminal, should be supplied by
the cable accessories manufacturers supporting, and its main components,
accessories should be complete, insulating sleeve shall not be cracks and
damage, and the user manual and certificate.
2.1.3 type and the voltage level of the
cable insulation adhesive shall conform to the requirements and to have
chemical and electrical performance testing and certification.
2.1.4 metal fasteners are galvanized.
2.1.5 other accessories: black glass, seal,
stearic acid, copper wire, white and yellow lead powder, glycerin oil, gas,
cable, etc.
2.2 the main tools:
2.2.1 production machinery: wind fences,
plastic sheeting, oil pressure wiring pliers, blowtorches, iron pots, aluminum
pots, ceramic plates, aluminum pots, iron scoop, a slotted spoon, glove,
funnels, electric stove, hacksaw, wire brush, thermometer, scissors, etc.
2.2.2 Installing machines: pulley, rope,
wrenches, bench drill, welding and gas welding tools.
2.2.3 testing tool: shake table, a steel tape
measure, steel ruler, and test equipment and so on.
2.3 operating conditions
2.3.1 an outdoor cable terminal making
should choose sunny windless weather construction, ambient temperature above +
5 ℃, relative humidity below 70%.
2.3.2 construction site and its
surroundings should be clean and dry, and platforms should be strong, setting
April wind fences.
2.3.3 should be equipped with 220V power
supply at construction site and safe power supply.
2.3.4 construction site should comply with
the fire safety requirements, combustible for safekeeping.
2.3.5 cable terminal production staff
should receive specialized training and examinations, before construction
operations.
3 operational processes
3.1 process:
Equipment inspections and preparations → shake test
point cable and verify the tidal stripping the protective layer of the cable
and strip →
→
Stripping lead and gland → round
copper into copper bars and exhaust wrap insulation Assembly cable terminal box
→ →
Cable terminal insulation adhesive
installation → perfusion → commissioning and acceptance
3.2 cable terminal making made according to
the following procedure. Strip cut from the beginning to make filling must be
continuous, once completed, to avoid damp.
3.3 equipment inspection and preparation:
3.3.1 opening checking and construction
units and supply units, or units (engineer), checks, and completes the record.
3.3.1.1 cable terminal boxes shall be
conducted according to technical data or manuals, accessories complete and
without damage.
3.3.1.2 types must conform to the design
requirements of the cable end box and all accessories fit.
3.3.2 copper gland and wire copper bars
hanging Tin. Remove the copper gland, sealing parts Tin Copper bar wiring and
outlet hole in the wall.
3.3.3 cable inside the terminal box with a
wire brush to remove dirt and rust, and cloth with gasoline, along with
porcelain bushing shell wipe clean inside and outside.
3.3.4 all ready for cable terminal box seal
cover with rubber pad or feather pad, ceramic casing and additive, holes are
made of chicken feathers and paper pad.
3.3.53 tube fitting, should be closely and
correct.
3.3.6 ceramic casing and cover with seam
and yellow lead and Glycerin mixing glue in order to seal.
3.3.7 processed anti-torque clamp, cable
retention bracket.
3.4 roll cable insulation measurement and
calibration of moisture:
3.4.1 the cable head turn, 2500V side table
side insulation resistance measurement, after passing tide.
3.4.2 tide: since the end of the cable
100mm cable saw, inner and outer layer of paper torn off several turnkey and
wire insulation paper, cable oils into 140~150℃ (such as no cable
available transformer oil Rosin mixture and 25%), such as moisture, oil will be
suffused with bubbles and make a hissing sound (Figure 2-5).
Another boom is burning method: paper torn
off, fire, moisture, insulation paper surface will bubble up and making a
hissing sound.
3.4.3 cable insulating paper tidal
immersion, should be removed piece by piece, until the tide right so far. In
school will be processed before the tide of black paint with GE in 140~150℃ cable oil
and net moisture and set aside in a colander.
3.5 stripped cable layer (Figure 2-6).
3.5.1 peeling bark or plastic sheath, from
900mm at the end of the cable, held together by 2mm turns of bare copper wire
cable ties along the three lines, and then use the electric knife to skin
layer.
3.5.2 Peel strips:
3.5.2.1 clean with petrol cotton silk to
steel, from the end of the cable 830mm~880mm, same 2mm bare copper wire lashing
two, tied every three turns of wire, or strip width two-thirds clamp the cable
itself, using the method of the bite, clamp firm, fixed two clips to prevent
steel straps.
3.5.2.2 saw steel band must first clamp the
edge at the time saw a ring of dark marks and a depth not exceeding two-thirds
of steel belt thickness, not saws, steel tip with a screwdriver pry the tear up
and steel band clamp with pliers, steel band saw blank repairs steel burrs to
make it smooth.
3.6 welding ground:
3.6.1 cotton silk with gasoline the lead
Pack wipe clean, winter construction used a blowtorch to heat will lead to wipe
clean. The strips with a hacksaw or file file up.
3.6.2 multiple plastic copper wire (16 mm2,
120 mm2 cable for 120mm2 cable with 25 mm2 copper), Peel 10~15cm and copper
wire straightening, tiling on the steel belt and lead, φ 2 turns of copper wire
lashing 3~5 on the lead sheet, steel band clamp on the bite card in prison.
3.6.3 welding line for the steel belt and
lead sheet heated with a torch, stearic acid wash and coating on the steel
welded oil, ground wire welding with a seal, and require smooth surface, should
weld the steel belt, should not be cold solder joint.
3.7 stripping lead and expanded lead and
copper into the CAP:
3.7.1 stripping lead: the lead tip into the
copper gland. At the end of the cable at 530mm, in the lead pack with electric
knife carving a ring of dark marks, its depth shall not exceed the thickness of
the lead Pack one-second and chipping knife strip between the end of the cable
to the ring-shaped scar lead. How: use electrician's knife from the ends at the
ring marks two parallel gouges, the depth to the thickness of the lead Pack
one-second, two-line a distance of about 10 mm2, and then from the end broke
the lead, the lead Pack peeling (Figure 2-7).
3.7.2 expansion lead as shown in Figure
2-9, Shun turnkey paper winding direction 30 ° ~45 ° angle with the expanded
lead, the lead Pack expanded into a 45 ° flare, no burrs to smooth and
symmetrical. Expansion flare shown schematically in Figure 2-8.
3.7.3 release turnkey insulation paper,
from heaving out of the lead, in turnkey paper wrapped with 25mm temporary
oil-impregnated yarns with about 5 layers, from the Terminal to the edge of the
oil-impregnated gauze to turnkey insulation with shredded paper, followed by
electric knife to cut filler, pay attention to the knife blade should be remove
without damage wire insulation paper.
3.7.4 broke core line: see Figure 2-9, a
only hand forced hold core line roots, another a only hand gently to broke core
line, shall not forced had slammed, so as not to injury core line, core line
separate Hou, with clean of hand split cotton silk dipped alcohol wipe to cable
oil, Shun cable core insulation paper winding of direction, with oil dip yarn
with to half overlap method package wrapped around a layer temporary protection
package cloth, oil dip yarn with package to away from cable end of distance is
equal to outlet copper bar hole of depth added 10MM. In three separate core to
PCM and then wrap a layer of oil-impregnated gauze.
3.8.1 cut off each end of the wire
insulation paper, cut away plus 10MM is equal to the length of the copper bar
outlet hole depth (when not injured bad core), then use the gauze to remove
oxide layer on the wire, cotton dipped in gasoline to wipe dirt, then private
reduced oil pressure wiring clamp fasten.
3.8.2 demolition of temporary
oil-impregnated gauze and paper chromatography, dismantling the temporary oil
on wire gauze (Commission on packages of paper without dismantling) phase
chromatography paper tear each.
3.8.3 winding oil-filled black lacquer with
isolation: Shun cable insulation on each wire-wound direction, with the half
overlap wrap 4 layers. 200mm up at the three-core split half overlap for 4.
3.8.4 exclude moisture: turnkey temporary
oil-impregnated gauze paper removed, swap the black paint across, a total of
eight layers of smooth, and tied in the three core root, with heating oil from
the roots to the wire of the cable end of the cable to water for moisture.
3.9 assembled cable terminal box seal
(Figure 2-10, 2-11).
3.9.1 Assembly cable terminal box: terminal
box cover on upper-layer phenolic gluing paint surface of the rubber pad, the
half sleeve into the cable terminal box, according to phase into the casing lid
and porcelain, round copper bars respectively porcelain bushings and
Lower terminal box screw tight (it should
be noted that litter the correct location), copper bar outlet rubber washer,
copper and brass cap tightly.
3.9. the lead 2: lay the cable terminal box
and seal, to center the cable terminal box and cable line and smooth, open,
additive hole nut, seal. Seal using a blowtorch, baking, and fats essential
decontamination. Seal lead drops: using a blowtorch to seal of roasted, in lead
and copper plating on the gland evenly, then roast to seal paste, and cloth
lead forming smooth, fine and fat (also called stearic acid), cooling
decontamination. Sealing time too long, must be done in 15~20min. Ratio of
lead-free solder: lead 65%, SN 35%.
3.9.3 sealed cable terminal before lifting,
with yellow transfers and glycerol lead powder into a paste, Terminal cover
with paint to prevent moisture, final installation has been processed against
twisted hoop.
3.10 cable terminal box installation fixed:
will be processed well in advance of the Hoop and branch according to the
design and specifications for installation. The cable terminal box with a
pulley and rope lift and fixed firmly.
3.11 pouring insulation adhesive:
3.11.1 infusion line voltage levels must be
insulated and cable, and test data and factory certificate.
3.11.2 operation personnel must safeguard,
Spider-man to cooperate.
3.11.3 when pouring insulation adhesive,
place porcelain bushing shell nut and at the top of hat-take it down, moving
wire of copper bolts, all around there are gaps, so that when a bored to remove
air.
3.11.4 before filling plastic cable housing
should be heated to 60~70 °, and then heated to 180~190 ° plastic insulation
pumped into housing.
3.11.5 the rubber filling filling, filling
plastic hole put a long neck funnel, place a sieve funnel top to filter, glue
method is shown in Figure 2-12.
3.11.6 cable rubber normally watered three
times. First filling ceramic casing until the second filling when cooled to 60 ℃ to vases
and catchy, gum irrigation after all the cooling time. Then remove the funnel,
clean up the shell plastic, tighten the nut filling plastic hole.
3.11.7 to check every part of the cable
head housing screws are tight, but not too, and finally brush paint on the
shell.
3.12 commissioning acceptance;
3.12.1 the first cable production has been
completed, as required by the test Department pressure and test.
3.12 2 acceptance: the no load test run
24h, no abnormal phenomenon, for the acceptance procedures unit.
4 quality criteria
4.1 guarantee project;
4.1.1 cable terminal voltage test result,
leakage current and insulation resistance code requirements must be met.
4.1.2 cable terminals must be closed tight,
packing infusion full, no bubbles, no oil leakage, wire connections tight.
Inspection method: Visual check and
inspection and test records.
4.2 Basic project:
Cable head good looks, smooth, with no sand
hole, wire bends without creasing. Securely and phase sequence is correct.
Inspection method: Visual check.
5 finished product protection
5.1 the manufactured cable head, wearing
parts with care, actions, be careful to prevent chipped cable porcelain
bushings wearing parts of the head.
5.2 when the fastening screws of the cable
head, to prevent excessive force which part is damaged.
5.3 head lifting cables, install
torsion-proof Hoop, and equipped with loop, so as not to damage the cable and
break the magnetic sleeve, fix cables to pad a good rubber or lead sheet.
6 quality problems to be noticed
6.1 in the making in cable head, to keep
clean, oil-impregnated gauze and black insulation tape to stamp in the aluminum
pan, hand-to-mouth, and moisture on the hand to wipe. In the tool on a clean
dish.
6.2 cable wire paper insulation cannot be
damaged, particularly in three separate core broke off when not overexert, in
wrapping the insulation layer, no back and forth broke wire.
6.3 sealing faster, otherwise it will
affect the dielectric strength of the cable. Baking-lead package, flames should
be uniform to avoid damaging the lead.
6.4 filling cable gel, temperature control,
high temperatures can damage the insulation paper, temperature too low
perfusion is not true.
7 quality records
7.1 product certificate.
7.2 cable test report form.
7.3 inspection equipment and materials.
7.4 compound test report form.
7.5 mutual inspection records.
7.6 change record of negotiation.
No comments:
Post a Comment