On the installation process

1 scope
This technology is applicable to rated load 5000kg and below rated speed 3M/s and the following types of Chinese-made traction lifts for installation works.
2 construction preparation
2.1 devices, materials requirements:
2.1.1 specification shall conform to the design requirements, full, firm, and free from distortion and damage.
2.1.2 to guide and fixing screw for guide specifications, quality, quantity shall conform to the requirements.
2.1.3 adjusting shims should meet the requirements.
2.2 the main tools:
Chain, wire rope, wood side.
2.3 operating conditions:
2.3.1 for DIN rail mounting, adjustment, after acceptance, dismantled a local scaffolding stalls on the ground floor in order to be able to enter the shaft in place.
2.3.2 in hoistway tidy line, lighting and other welding, convenience of operation site.
3 operational processes
3.1 process:

Lifting preparation before hoisting the heavy framework work guide boot installation, adjustment of the weights is installed and fixed

3.2 lifting preparations:
3.2.1 in the corresponding position on the scaffold (to facilitate lifting the frame and mount Tuo block for example) installation platform (Figure 5-32).
3.2.2 in the proper height (for easy lifting on whichever) two heavy rail bracket attach the wire rope, wire rope Center hung a chain. Steel wire rope should be tied to the guide rail bracket, is not directly tied to the Rails to avoid rail force and displacement or deformation.
3.2.3 in the buffer on each side of a 100mmx100mm wood side. Wooden height C=A+B+ distance (Figure 5-33).
The distance shown in table 5-8.
5-8
Lift the rated speed (m/s) buffer-overrun distance (mm)
0.5~1.0
1.5~3.0 spring
Hydraulic 200~350
150~400

3.2.4 If the guide shoe for spring-mounted or stationary, to two of the same side of guide shoe removed. Guide roller, to four guide shoe removed.
3.3 the hoisting the framework:
3.3.1 the framework shipped to platforms, wire rope pull on rope hitch plate and chain hook together (Figure 5-34).
3.3.2 operation pour chain, slowly will on heavy framework hanging up to scheduled height, for side with spring type or fixed type guide boots of on heavy framework, mobile on heavy framework, makes its guide boots and the side guide anastomosis and keep contact, then gently relax pour chain, makes on heavy frame smooth firm to placed in prior support good of wood party Shang, not loaded guide boots of on heavy framework fixed in wood party Shang Shi, should makes framework two side and guide end surface distance equal.
3.4 installation, adjustment to the Guide:
3.4.1 stationary guide installation to ensure the lining and clearance of rail-side upper and lower line if it does not meet requirements to be used to adjust (Figure 5-35). 3.4.2 in prior to installing the spring-loaded guide roller, guide roller adjusting nut should be tightened to the maximum, no clearance between the Guide and guide shoe rack, which makes it easier to install (Figure 5-36).
3.4.3 If the guide roller slider-lined upper and lower inconsistent with track-side side gap, between Guide and counterweight frame shim adjustments, adjustments with stationary guide roller.
3.4.4 install roller guide shoes flat, roller guide after pressing rollers on either side should be equal to the amount of pressure spring, compressed size should be as stipulated in the factories. If no provisions are adjusted according to the usage pressure moderate front wheel and road surface compaction, wheel alignment guide from the Center Center (Figure 5-37).
3.5 installation and fixing of the weights:
3.5.1 into a corresponding number of the weights. Number of weights should be calculated according to the following formula:
Mounted on blocks =
3.5.2 design according to manufacturer requirements put on the block mounts. Figure 5-38 for the flapper mounts.
4 quality criteria
4.1 project:
The upper and lower guide roller should be in the same vertical line, skew, twist is not allowed.
4.2 Basic project:
Guide roller Assembly should comply with the following requirements:
4.2.1 using a rigid structure, able to guarantee the normal operation, and two rail ends with two guide surfaces and is not more than 2.5mm.
4.2.2 using the flexible structure, able to guarantee the normal operation and end face with guide roller slider surface without gaps, guide shoes spring telescopic range is less than 4mm.
4.2.3 use roller guide roller guide does not skew, even pressure, Center, and in contact with the Rails face even on the entire flange width (see 3.4).
Inspection method: observation and standard checks.
5 finished product protection
5.1 the guide shoe after installation, using things like old cloth for protection, so as to avoid dust residue into the boot lining, affect its service life.
5.2 construction should pay attention to avoid falling objects to prevent smashing guide shoes.
5.3 the framework of transport, lifting and loading Tuo block process, be careful, do not hit have been renovated floors, walls and Rails and other facilities, if necessary, to take the appropriate protection measures.
6 quality problems to be noticed
6.1 boot after installation and adjustment, each screw must bear in prison.
6.2 screw hole location if the individual does not meet the installation requirements, and can be resolved. Never allow empty without it.

6.3 in heavy lifting, don't touch the baseline, so as not to affect the installation accuracy.