1 scope
This technology is applicable for
industrial and civil construction of prefabricated reinforced concrete piles.
2 construction preparation
2.1 materials and equipment:
2.1.1 precast reinforced concrete piles:
quality specifications must meet the requirements of specification for design
and construction, and factory certificate.
2.1.2 electrode (piles): model, performance
must comply with the design requirements and the relevant provisions of the
standards, should be treated with E4303.
2.1.3 plate (piles): materials,
specifications comply with the design requirements, to use low-carbon steel.
2.1.4 main tools are: diesel hammer,
electric welding machines, pile caps, carry cars. Sling, wire rope, steel plate
or steel, as well as Pocket rule.
2.2 operating conditions:
2.2.1 pile axial and elevation have been
completed, and after checking the pre-screening procedure. Axis and elevation
control of pile-pile, should be set up in places not affected by pile driving
and should be properly protected.
2.2.2 processing of aerial and underground
obstacles. Affect the use or security of neighbouring buildings or structures,
effective measures should be taken in conjunction with the relevant
authorities, to deal with it.
2.2.3 released axis line, with chunks of
wood or steel head nails pile and lime as a marker, so that shot.
2.2.4 sites should be rolled flat, smooth
drainage to ensure vertical pile movement and stability.
2.2.5 test piles. Test pile construction
must play, the number of wood less than 2. Determine penetration and verify
piling equipment, construction technology and technical measures are
appropriate.
2.2.6 to select and rank pile driver access
routes and piling, and formulate programmes, make technology gives the
low-down.
3 operational processes
3.1 process:
Pile hoisting precast pile → → → → → piling pile
stabilization →
Intermediate inspection → pile to the
next pile position
3.2 in place pile: pile in place, should be
aligned to ensure vertical stabilizer, the construction does not tilt, move.
3.3 lifting prefabricated pile: first tied
good hanging pile with of wire rope and cable with, then application cable with
bundle live pile top rings near at, General should not be over 30cm, again up
moving machine lifting prefabricated pile, makes pile pointed vertical
alignment pile bit Center, slowly down plug buried in the, location to
accurate; again in pile top buckle good pile CAP or pile Hoop, can removed
cable with.
3.4 stability. After pile insert, use a
smaller drop-distance cold hammer 1~2, pile into a certain depth, then makes
the vertical stabilizer. 10m line for short pile can be Visual or
bi-directional correction; 10m or playing pile must be in line or theodolite
bidirectional calibration, not Visual. Insert vertical deviation must not
exceed 0.5%. Pile in front of the access should be set on the side of the pile
or pile the ruler, so that construction of observation, record.
3.5 driving: with a hammer or hammer
driving, hammers the maximum fall distance should be less than 1.0M. ; Driving
diesel hammer, hammer should be beating normally.
3.5.1 weight piling should be low, hammer
weight should be selected based on engineering geology condition of pile type,
structure, intensity and construction conditions to choose.
3.5.2 piling orders based on the underlying
design of the elevation, deep-shallow; according to pile size after the first
small, long before they are short. Due to the different intensity of the pile,
from the Center to two hearts to the symmetry or around; or by the side of a
single direction.
3.6
3.6.l in the case of long enough, by
welding by pile, embedded part of its precast pile on the surface should be
clean, gap between the upper and lower sections of iron Tablet pad solid solid;
welding, should take measures to reduce weld deformation of welds shall be
continuous welds.
3.6.2 pile, generally from when the ground
around the LM. Center line of the upper and lower sections of deviations not
greater than 10MM, joints flexed rise-high-‰ length shall not be greater than
l.
3.6.3 before the pile the soil, exposed
iron, make up brush paint again.
3.7 pile: when design requirements pile,
the centerline of the pile shall be consistent with the line of the pile, pile.
If uneven, sacks or thick paper pads that are available. The pile immediately
backfill compaction pile left.
3.8 checking: each piles to penetration
requirements, elevation of pile tip into bearing layer, when close to the
elevation, or while he was playing to the design level, intermediate inspection
should be carried out. In control, General requirements for the last sancishi
average penetration of the hammer does not exceed the values prescribed by, or
using a pile until elevation to control, comply with the design requirements
and fill construction record. Such as when he found the position and
requirements are different, and should be studied in conjunction with the
relevant authorities. Then moves to a new position.
3.9 during piling, meets the following
conditions should be suspended, and timely and relevant units dealing with:
3.9.1 penetration upheaval;
3.9.2 tilt and displacement or suddenly had
serious rebounding;
3.9.3 piles or pile when serious crack or
break.
3.10 all the piles after the excavation to
the design level, do a final check and acceptance. And submit the technical
data the total package.
3.11 pile in permafrost area in winter when
there are difficulties, it should first be removed or after thawing of frozen
soil.
4 quality criteria
4.1 project:
4.1.1 the precast reinforced concrete pile
quality must comply with the design requirements and specifications provided,
and has a factory certificate.
4.1.2 the piling of elevation or
penetration, piles of connector, you must meet the requirements of
specification for design and construction.
4.2 allowable deviation, as shown in table
2-5.
Precast reinforced concrete pile tolerance
table 2-5
Project tolerance (mm) test method
Vertical center line of Foundation beam 100
Along the center line of Foundation beam
150
Number of 2 piles for 1~3 or single-row
piles 100
3 number of piles for 4~16 root d/3
Edge d/3
Middle d/2
Note: d for the diameter of the pile length
or cross section.
5 finished product protection
5.1 shall meet the design strength of the
70% before he can lift, above 100% to transport.
5.2 lifting and handling, you must do the
lifting point meets the design requirements, should be smooth and not damaged.
5.3 pile piled up, the following
requirements:
5.3.1 venues should be smooth, firm, shall
not give rise to uneven sinking.
5.3.2 wood with hanging points should be
the same, and should be in the same plane.
5.3.3 pile, the pile should be put
together, and pointed to the end.
5.3. more than 4 storey wood should align
the bottom wood should be appropriately widened. Stacking layer is generally
not more than 4 floors.
5.4 properly protect the axis and elevation
control of pile-pile. No displacement due to collisions and vibrations.
5.5 data differ from the driving data
provided does not comply, it should stop the construction and joint research
with relevant units.
5.6 on the slopes close to buildings or to
shore, driving, effective measures should be taken in conjunction with the
relevant authorities. Should be observed at any time during construction to
ensure that avoids accidents because of piling vibration.
5.7 piling is completed during excavation,
should formulate a reasonable construction and technical measures in order to
prevent displacement and tilt.
6 quality problems to be noticed
6.1 advance order processing prefabricated
pile, driving strength must meet the design strength of precast concrete pile
of 100% and conservation period by one month behind the shot should be added.
6.2 pile break. Due to excessive bending,
strength of the pile and the underground obstructions caused, or fracture in
the stacking, lifting, transport, did not find consensus. Should be checked in
a timely manner.
6.3 fragmentation, due to pile on pile top
intensity and insufficient reinforcement mesh, reinforcement from the top of
the pile, or the pile caused by injustice, wrong choice of construction
machines and other reasons. Inspection at time of preparation should be
strengthened.
6.4 piles tilted. Due to the uneven, space
pile drivers chassis not level or steady not vertical, pile in underground
meeting caused by hard objects or other reasons. Should be strictly according
to the process regulations.
6.5 pulling crack. Connected surface is not
clean, connect welding quality uneven, iron does not meet the requirements,
then pile vertical centre line is not in the same line of fine resulting.
Should ensure the quality of piles.
7 quality records
This standard shall meet the following
quality records:
7.1 of prefabricated reinforced concrete
piles factory certificate.
7.2 test or test records.
7.3 filling pile floor map.