1 scope
This standard applies to buildings and
structures set automatic sprinkler system installation.
2 construction preparation
2.1 after receiving the construction task,
earnestly familiarity with drawing paper and construction site, found that
construction of design issues, timely and relevant research, and go through the
negotiation procedures. Determined according to the characteristics of the
construction method, is equipped with the corresponding labor, equipment,
materials, machinery and so on. Equipped with a complete set of life, temporary
facilities.
2.2 equipment and materials:
2.2.1 automatic sprinkler system main
equipment selection of materials should conform to the 6-l "General
requirements for the installation of fire engineering" of the relevant
content.
2.2.2 major equipment: spray pumps, fire
department pumper connection, alarm valves and components, signal control
valves, flow indicator, spray heads, pressure water supply device, power pumps.
Spray heads, alarm valves, pressure switches, flow indicator and other major
system component fire protection products should have a national quality
supervision and inspection Center report.
2.2.3 General material: pipes and fittings,
steel, welding electrodes, oxygen, acetylene, thick paint, hemp, Teflon tape,
expansion bolts, gaskets, bolts, nuts, motor oil, paint, thinner, smaller
lines, wire, batteries, and so on.
2.3 main machines, threading machines,
wheel saws, bench drill, hammer, drill, hand wheel, electric drill, electric
welding machines, electric pressure pumps and other machinery. Silk panels,
pipe wrenches, pressure clamps, chain pliers, hammer, hacksaw, wrenches, nail guns,
chains, electric welding and other tools. Steel tape measure, leveling ruler,
machine n oil standard calipers, lines, spirit level gauge.
2.4 operating conditions:
2.4.1 should be complete construction
drawings and related technical documents: electrical shall meet the
construction requirements of water, the system should guarantee normal
construction equipment and materials.
2.4.2 subject of embedded structure
complete piping installation needed for baseline determination should be
marked: Add ceiling height, ground elevation, location of partition lines.
Before installation, Foundation should be inspected. Pipes and sprinkler head
installation should meet the ceiling decoration.
3 operational processes
3.1 process
Installation preparation → network → → device → installed
sprinkler branch pipe installed sprinkler system installation →
Water adjustment
3.2 installation preparation:
3.2.1 familiar with the drawings and
control on-site review pipelines, equipment, location, elevation is a crossover
into improperly arranged, with designers to study and solve in time, go through
the negotiation procedures. Check for the right embedded-reserved tone,
temporary pick your cut should be good consultation and design of civil
engineering.
3.2.2 installation forward field equipment
material test: entry equipment material specifications, and model should meet
design requirements: appearance clean, no defect, and deformation and the rust;
plating zinc or coated paint uniform no off: flange sealed surface should full
smooth, no Burr and the radial Groove; silk buckle intact injury; pump disc car
should flexible no block and the exception sound; equipment accessories should
complete; alarm valve individually leakage test, valve, and nozzle sampling
strength, and tightness test results should meet construction acceptance
specification provides.
3.3 network installation:
3.3.1 automatic sprinkler system pipes
should be selected according to the design requirements, generally use
galvanized steel pipe and fittings, while nominal diameter less than or equal
to 100mm, the thread should be used when the nominal diameter is greater than
100mm, flanges and welding, welding inside and outside surface for good
corrosion protection.
3.3.2 installation before straightening the
pipes and clear debris, stop is installed when you install pipeline exposure
should be sealed well. Required when welding galvanized pipe openings should be
preformed in advance, both ends of the pipe, if necessary by law lanhuo, finish
cleaning corrosion after welding installation. Banning has been installed in
hole welding on galvanized pipe.
3.3.3 the piping through the expansion
joints should be set when Flex pipe, pipe installation should be installed
horizontally 0.002~0.005 slope, slope discharge device.
3.3.4 automatic sprinkler system piping
support and hanger selection and Atlas of practice should meet the construction
requirements, maximum of support and hanger spacing in accordance with the
following provisions:
Nominal diameter (mm): 25 32 40 50 70 80
100 125 150 200 250 300
Maximum spacing (m):3.544.55666.5789.51112
3.3.5 pipe installation:
3.3.5.1 spray pipe flange connections, each
piping length should not exceed 6m, straight pipe can be connected together
using several chain installed, but should not be too long. Also be numbered
according to the order after straightening, lifting should first lift one end
of the pipe, to be stable after lifting the other end.
3.3.5.2 piping fastening flanges, check
that the flange end face is clean. 3~5mm the rubber gasket. Specifications
should be in line with provisions of the flange bolts. Fastening bolts should
be tightened the most unfavourable point, then the symmetric fastening. Flange
connector should be installed on the easy Assembly and disassembly of the
locations.
3.3.5.3 horizontal pipe generally consists
mainly of hanger card, each pipe should be located 1 baffle support. Pipeline
changes direction, slosh bracket should be added.
3.3.5.4 concealed in the shaft when the
standpipe, embedded iron parts installed on the card in the tube well fixed,
installation location from the ground or floor surface should be as 1.5~1.5M,
higher than 5M support should be added.
3.3.6 duct installation:
3.3.6.1 piping branch provision before the
lifting should be good. Silk tee location of provision. Weld on the pipe
openings welded wrought iron pipe couplings. All provision and temporary
plates.
3.3.6.2 pipeline diameter, use reducers.
The pipe elbow bushing can not be used. When heart is required, 1 available on
the three-way, four-way should not be more than 2.
3.3.6.3 every pipe in the water
distribution tube, pipe between the two adjacent sprinklers set of hangers
should not be less than 1, when the nozzle is smaller than the distance between
three 1.8M can be set at regular intervals, but the hanger spacing should not
be greater than 3.6m. Each water distribution pipes should be installed a anti
shaking brackets. Pipe supports and hangers of the installation location should
not interfere with the spray nozzle water effects.
3.3.7 the hydraulic test:
3.3.7.1 spray pipe hydrostatic test can be
staged, while the highest point to exhaust, low install a pressure gauge on the
water and check the piping for leaks, if there is leakage of flanges, valves
and other parts should be fastened in front of pressure, boost leaks occur
after mark when, after unloading. Leaking water when necessary.
3.3.7.2 hydrostatic test pressure should be
determined according to the working pressure. When the system pressure is equal
to or less than 1MPa, the test pressure with 1.4MPa when the system pressure is
greater than 1MPa, the test pressure working pressure plus 0.4MPa. When pressure
testing voltage 30min, Visual networks without leakage and deformation, and the
pressure drop is less than 0.05MPa. After passing the test in time for the
acceptance procedures.
3.3.7.3 winter test water pressure, ambient
temperature should not be below + 5 c, if less than + 5 ° c anti-freeze
measures should be taken.
3.3.8 rinse:
3.3.8.1 spray finish continuous flushing of
pipes pressure test. Should ensure that the tube has enough amount of water
when you flush. Drainage pipes should be connected to the drainage system, the
emissions should be smooth and safe. Pipe cleaning should be carried out
continuously, when the color of the water at the outlet, transparency and color
of the inlet when the basic one to end. The flow direction of the pipeline
flush and fire network flow in the same direction. After passing the rinse
water tube should be completely removed and handled in a timely manner and
acceptance procedures.
3.3.8.2 when unable to meet water flow and
drainage conditions, shall be settled according to site conditions and design.
3.4 equipment installed:
3.4.1 water pump installation:
3.4.1.1 specification shall conform to the
design requirements of the pump, water pumps, irrigation water should be used,
pump base according to the design drawings, there should be no air bag and leak
on the suction pipes in horizontal pipelines, and fire water tank connections
should be interpreted with shock absorbers. Pump does not have a damper, but
constant pressure pump damping device, water inlet and outlet with noise
protection facilities, slow close check valve water pump outlet should be
added.
3.4.1.2 pump piping installation pump
location looking for smooth, firm followed. Pumping equipment shall not bear
the weight of the pipe. Installation order for the check valve. Valves and
pumps in turn bear jail, connected with the water pump pipe flanges and the
valve flange tight prison, straight lines attempt to find, pipe sizes, on pipe
welding flange, then remove welded flange release, cooled and then connected
with the valve, then another flange connected to the welding and piping.
3.4.1.3 piping flanges should be compatible
with pumps, valves, flanges, valve install the handwheel should be easy,
elevation, piping aligned.
3.4.2 tank installation: tank should be in
place before Cap structure and full water test should be done. Fire and other
shared water tank with water, we should ensure that water is not being used,
with 10 minutes of fire water. When combined with water, water should be in a
constant flow, to prevent a deterioration in water quality. Fire outlet check
valve should be added. All tank nozzles should perform if openings welded on
site should be welded on the tank plate.
3.4.3 alarm valve installation: when
installing the alarm valve water control valve, alarm valve should be installed
first, then the auxiliary pipes and accessories according to the manual
installation. Water control valve, alarm valve connection to the water pipe,
the flow in the same direction. Installation location should comply with the
design requirements of the alarm valve group. When the design is not required,
alarm valves should be installed in a clear location easy from the interior
floor height should be 1.2m: distance on either side and the wall should not be
less than 0.5M positive and wall distance should not be less than 1.2m. Alarm
valve group installed an indoor ground drainage.
3.4.4 Fire Department pumper connection
installation: pump design specifications should be based on a combination of
the selected, there are three types: wall, floor, underground type. The
installation location should be clearly marked, valve location should be easy
to operate, combined with nearby there should be no obstacle. Working pressure
safety valve on the system pressure, combined with the drain valve shall be
installed.
3.5 spray head pipe installation;
3.5.1 spray head pipe installation
ceiling-type head end of a pipe, it tube cannot be completed simultaneously
with the branch pipe, and you want to synchronize with the ceiling decoration.
Ceiling joist loaded, set according to the thickness of ceiling material
provision of the sprinkler head elevation, ceiling decoration to determine the
coordinates of the sprinkler head, tube reserve location accurate. Branch pipe
size is 25mm, end 25mmx15mm different diameter pipe straps, cable installation.
Pipe elbow 100mm cards should be added at the end of fixed to prevent the spray
head contact with the ceiling is not strong, and dislocation. Branch pipe
ready, reservation of mouth plugs tightened.
3.5.2 conditions of a sprinkler head upward
and branch pipe installed at the same time good. Difficult operations of other
pipe after installation location should also be installed upward spray head.
3.5.3 sprinkler system pressure test:
ceiling prior to pressure testing of the system, in order not to affect the
progress of ceiling decoration can be staged. After passing the test to reduce
the pressure working pressure tightness test, voltage 24-hour seepage and
leakage is qualified.
3.6 system components and sprinkler head
installation:
3.6.1 installation the flow indicator: is
usually installed on each floor or a regional branch on the trunk. Flow
indicator should be kept 5 times before and after the installation length of
straight pipe pipe diameter, should be installed horizontal vertical loading,
pay attention to the flow direction and the line indicates the direction of the
arrow, after the installation of a flow indicator lodicules, diaphragms should
be flexible and should not be rubbed with the wall.
3.6.2 alarm valve accessories installation:
alarm valve parts typically include pressure gauges, pressure switches, delay,
filter, water alarms, drain, etc. Should strictly follow the instructions to
install or install Atlas. Water alarms should be installed in the public
channel or on the wall near the Office, and maintenance test valve should be
installed. Water alarms and alarm valve connection should use galvanized steel
pipe, when the nominal diameter is 15mm, the length should not exceed 6m when
20mm is the nominal diameter, the length should not exceed 20m. Hydraulic Bell
starting pressure of installation shall not be less than 0.5MPa.
3.6.3 sprinkler head installation: spray
head generally hanging mounted after the installation of the roof, installed in
special wrench should be used. Installation of sprinklers at the vulnerable to
mechanical damage, should be added shields. Sprinkler head screw packing PTFE
tape should be used.
3.6.4 throttling devices installed:
throttling in nominal diameters of not less than 50mm should be installed on a
horizontal pipe; orifice flow in a pipe bend should be installed on the
downstream side of the straight tube, and distance should not be less than the
nominal diameter of the corner twice times.
3.7 water connection debug:
3.7.1 overall water sprinkler system
installation and make preparing to debug a system reaches normal operating
pressure.
3.7.2 release through the end device, when
pipe network pressure from dropping below a set value, the regulator pump
should start, stop water pipe network pressure returned to normal, and
regulator pump should stop running. When a terminal device to 0.94~1.5L/s when
the flow of water, regulated pumps should be locked. Flow indicator, pressure
switch, water alarms and fire pumps and timely actions and issued the
corresponding signal.
4 quality criteria
4.1 project:
4.1.1 pipe hydrostatic test results and use
of fire control system must conform to the design, specifications, dimensions
and construction specifications.
4.1.2 specifications must conform to the
design requirements of the pump, pump bearing temperature rise test run must be
in order.
4.1.3 automatic sprinkler and drencher fire
fighting installations in the nozzle position, spacing and direction must
comply with the design requirements and construction specifications.
4.2 Basic project:
4.2.1 galvanized pipe threaded connections
should be solid, seams no leakage of Yau Ma Tei and in good preservation.
4.2.2 flanges should be butted closely
parallel and perpendicular to the pipe centerline, screw out the nut length is
greater than the diameter of the screw 1/2.
4.2.3 galvanized steel pipe welding,
welding flatness, and strengthening compliance with the construction
requirements of weld surface without burn-through defects such as cracks,
inclusions, porosity, welded joints for good corrosion protection both inside
and outside.
4.3 allowable deviation:
4.3.1 horizontal piping installation slope
should be between 0.002~0.005.
4.3.2 hangers with the distance of the
nozzle should not be less than 300mm, the distance from the nozzle at the end
is less than 750mm.
4.3.3 hangers should be located in the
adjacent sprinklers on the pipe segment, when adjacent nozzle spacing less than
3.6m, and can be set to 1. Less than 1.8M, allows the isolation period
settings.
5 finished product protection
5.1 after the construction of fire control
system and components of various parts of the equipment to be protected to
prevent the touch running water, damaged decoration products.
5.2 alarm valve fittings and parts of the
instrument shall strengthen management to prevent loss and damage.
5.3 fire protection piping installation and
civil engineering and other pipe contradictions, not allowed to demolition, is
designed to handle the negotiations proper solution.
5.4 installation without damage and
contamination of the spraying ceiling decoration.
6 quality problems to be noticed
6.1 due to the poor coordination of
installation processes, no overall arrangement makes the spray pipe demolition
is serious.
6.2 due to not pressure test caps, after
causing water leakage.
6.3 due to branch pipe elbow without fixed
cards at the end, branch size allowed, the spray head contact with the ceiling
is not strong, and not being.
6.4 because no cable installation,
sprinkler head is not a row, take place.
6.5 as the flow indicator installed in
opposite directions; electric contact poor contact caused by oxides or flow
indicator lodicule doesn't match the diameter and its insensitive.
6.6 Fire Department pumper connection
cannot be pressurized. Because the valve does not open, check valve installed
backwards, or caused by a blind flange was not removed.
7 quality records
7.1 material certification, product
certification, inspection report of major system components.
7.2 entering material inspection records.
7.3 construction records
7.3.1 valve records.
7.3.2 leak test record heating and plumbing
engineering strength.
7.3.3 heating and plumbing engineer Chong
(blow) wash test record.
7.3.4 irrigation experiment of heating and
plumbing engineering records.
7.3.5 heating and plumbing engineering
water test records.
7.3.6 single water pump commissioning
record.
7.3.7 debug reports.
7.4 the construction records
7.4.1 construction logs.
7.4.2 self and cross-checking records.
7.5 pre inspection records
7.6 conceal engineering acceptance record
7.7 the construction programme
7.8 technical programme
7.9 quality inspection and assessment of
7.9.1 installation of indoor water supply
pipeline assessment.
7.9.2 indoor water supply pipeline
assessment-installation of the annex.
7.9.3 subsidiary equipment evaluation of
indoor water supply pipeline.
7.9.4 quality assessment for heating and
plumbing Engineering Division.
7.9.5 impression quality heating and
plumbing engineering assessment.
7.10 construction inspection information
7.10.1 intermediate inspection records.
7.10.2 unit engineering acceptance record.
7.10.3 fire supervision Agency verification
certificate.
7.10.4 quality oversight body checks.
7.11 design changes, record of negotiation
7.12 the construction plans
8 resources
8.1 the standards for building equipment
installation project construction technology.
8.2 the General water supply engineering
Atlas 918B3.
8.3 the code for construction and
acceptance of automatic sprinkling fire-extinguishing system GB50261-96.