1 scope
This technology is applicable to industrial
and civil construction of aluminum alloy door and window installation.
2 construction preparation
2.1 materials and equipment:
2.1.1 aluminum Windows and doors:
specification, model, the design requirements, and should have a factory
certificate.
2.1.2 aluminum alloy door and window
hardware should match the Windows model. The accessories and best fitting made
of stainless steel, with other materials, it must be treated.
2.1.3 anti-corrosion materials and
insulation materials shall conform to the drawings, and the ex-certification.
Its more than cement 2.1.4 No. 325; sand
prepared according to the requirements.
2.1.5 and iron foot fixed connection
structure, connection plates, should according to drawings and specifications
prepared. And well treated.
2.1.6 electrode specifications, models
should be consistent with the quenching by welding, and should have a factory
certificate.
2.1.7 caulking materials, sealant, model
should comply with the design requirements.
2.1.8 paint, wire fabric (or aluminum
yarns), shall comply with the design requirements such as gauze, and the
ex-certification.
2.1.9 specifications, models, the design
requirements of the seal, adhesive and sealing material should be matched and
factory certification of products.
2.1.10 main equipment: aluminum cutting
machines, hand drills, Rotary Rasp, semicircular Rasp, Phillips screwdriver,
needle, iron feet, compasses, ruler, steel ruler, steel ruler, drills, hammers,
shovel, trowel, a bucket, water brush, welding, welding masks, welding lines,
and so on.
2.2 operating conditions:
2.2.1 structure after acceptance, the
quality meet the eligibility standard, between jobs for the handover
procedures.
2.2.2 dimensions as shown playing the
middle line of the window and play +50cm horizontal calibration door hole
position size and elevation for conformance to design drawings, rejection of
chisel handle-if you have any questions in advance.
2.2.3 checked iron foot aluminum alloy door
and window on both sides of the connection locations agree well with the wall
holes location is reserved, if problems should be dealt with in advance and
reserved clean hole of debris.
2.2.4 unpacking check of aluminum alloy
doors and Windows, window frame around the bandage removed, according to the
drawing requirements check types, check the quality and the smoothness of the
surface, such as chopping, channeling corners angled and warping inequalities,
serious incidents, serious injuries, skin color, such as a defect, shall be
settled through consultation with the persons concerned, the finished qualified
before they can be installed.
2.2.5 check the integrity of aluminum alloy
door and window protection film, if there is any breakage, should fill the
stick and install again.
3 operational processes
3.1 process
Line the rules → → jambs jambs laid
connecting iron aluminum alloy doors and Windows unpacking check → →
Transported to the installation site by
drawing number → check the protection coating on aluminum alloys → aluminum
alloy door and window installation →
Caulking around doors and Windows, fill
insulation mounting Wang →
→ → clean
installing doors and Windows sealed →
→ Yarn quality check fan installation
3.2 line rules: find out the window at the
very top edge, under the edge of the door with large window and line at the
doors and Windows on each floor, not directly to individual's mouth should pick
your cut. Theodolites of high-rise building vertical lines.
The horizontal position of the window floor
+50cm horizontal line shall prevail, up against, measure the window height,
find direct line, each window (the same elevation) it shall, on the same level.
3.3-thick wall installation location:
according to the width of the detail of the walls and sill plates, determine
the installation location of aluminum alloy doors and Windows in the
wall-thickness direction; such as wall thickness deviation should, in
principle, to the same room window sill outside the same size as the standard,
should extend into the aluminum window sill plate 5mm under Windows.
3.4 installation aluminum window pishui:
according to design requirements will shed fixed on the aluminum window, you
should ensure the installation position is correct and secure.
3.5 anti-corrosion treatment:
3.5.1 treated both sides of the door and
window frames should be carried out according to the design requirements.
Design requirements, brushing anti-corrosion material, such as rubber or
polypropylene anticorrosion coating resin protective decorative film, may be
pasted with plastic film for protection, avoid filling cement mortar is direct
contact with the surface of the aluminum alloy doors and Windows,
electrochemical, corrosion of aluminum alloy doors and Windows.
3.5.2 aluminum alloy doors and Windows
installed that fixed by binding of metal, iron should be embalmed,
connection-the best selection of stainless steel parts.
3.6 in place and temporary fixation:
according to the installation location you have put lines installed, and
hanging it looking straight, problem-free rear wooden wedge a temporary fix
available.
3.7 with wall fixing: aluminum alloy door
and window and wall fixed have three methods:
3.7.1 φ 6 hole hammering along the window
wall power (deep 60mm), and "PHI bar (40mmx60mm) 107 glue viscosity mud
into the hole in the cement after the final set, then iron feet and embedded
steel bars welding in prison.
3.7.2 connecting iron with embedded steel
plates or ruled out structural reinforcement welding in prison.
3.7.3 concrete wall available nail gun iron
foot and wall fixing.
Regardless of which method to use a fixed,
iron should be greater than the distance from the feet to the window corner of
180mm, iron-foot spacing should be less than 600mm.
Aluminum alloy door and window installation
node as shown in Figure 8-l.
3.8 processing of door and window frames
and wall cracks: aluminum alloy doors and Windows after the fixed, timely
processing of door and window frames and wall cracks. Design at the packing
materials provided, mineral wool or glass wool mat should be used layered
Garret, outer surface 5~8mm deep filled caulk, filling cement mortar is
strictly prohibited. Treated in both sides of the door and window frames,
complete block design specifies the insulation and sealing materials. Aluminum
window and sill plate installed, gaps around the window frame and filled and
filled hard and should not be too large, prevent the window from deformation.
3.9 aluminium alloy door installation:
3.9.1 reserved openings in aluminum door
frame sizes repaired well in advance.
3.9.2 in the side of the door frame fixed
the binding of metal (or wood block).
3.9.3 frames made by location, and find the
vertical size and geometry, with a nail or self-tapping screws the frame fixed
with the embedded parts of the wall.
3.9.4 filled frame and masonry walls with
insulation material (or concrete) gap.
3.9.5 the use of sealant filled the slot
beside the wall and door and window frames.
3.10 spring installation: install location
base spring, picking holes in advance, place the spring in picking good hole,
fixed with cement mortar.
Spring quality must be guaranteed: to
spring e must be consistent with the interior; floor spring hinge axis must be
consistent with the frame transverse axis PIN.
3.11 aluminum alloy door installation: door
frame fan connections are aluminium corner connector fixation, practices the
same as door frame installation.
3.12 installation hardware accessories:
finished Grouting repair, let's give finish painting before the installation of
door and window hardware fittings, installation process as described in the
product description, require the installation of a solid, flexible use.
3.13 installation aluminum screen doors and
Windows:
3.13.1 tension and the iron (or steel,
aluminum yarn), cut yarn, layering is fixed, the screen doors and Windows with
steel frame construction method of sand.
3.13.2 hanging yarn sector.
3.13.3 installed hardware.
4 quality criteria
4.1 project:
4.1.1 quality of aluminum alloy doors and
Windows and their accessories must comply with the design requirements and the
provisions of the relevant standard.
4.1.2 installation position and opening
direction of aluminum alloy doors and Windows must comply with the design
requirements.
4.1.3 aluminum alloy doors and Windows must
be installed firmly planted embedded parts of the number, location, connection
methods, you must comply with the design requirements.
4.1.4 aluminum alloy doors and Windows
between the box and non-stainless steel fasteners must be treated; non-cement
mortar is used as packing material between the wall and door and window frames.
4.2 Basic project:
4.2.1 aluminum fan installation should
comply with the following requirements
4.2.1.1 casement sash shut tightly, even,
flexible.
4.2.1.2 sliding sash shut tightly, even,
fan and box bonding should comply with the design requirements.
4.2.1.3 spring doors automatic positioning
accuracy, ± 1.5 ° opening angle of 90 °, the closing time in the 6~10s range.
4.2.2 aluminum alloy doors and Windows
accessories is complete, installation is correctly positioned, solid, flexible
application, achieve their function, upright appearance.
4.2.3 aluminium alloy door and window frame
gap between wall and filled full of dense, flat, smooth surface, free of
cracks, filling materials and methods meet the design requirements.
4.2.4 aluminum alloy door and window
surfaces clean, no scratches, bumps, no corrosion; coating surface is smooth,
smooth and of uniform thickness, no pores.
4.3 allowable deviation: window box two
diagonal length, doors, box, side of vertical, horizontal, horizontal box
marked higher, shall exceed the values in table 8-3.
Aluminum alloy door and window installation
tolerances in table 8-3
Project tolerance (mm) test method
Door and window frames of two diagonal
length ≤ 2000mm
>2000mm 2
3 steel tape measure checking angles
2 sash and casement window box poor lap
width 1 depth gauge or a steel ruler to check
3 Tang doors adjacent cross-side corner of
the fan width and 2 in cable and steel ruler check
4 door sash opening force limit size ≤ ≤ 40N 1.5m2 100N
spring scale hook hand
Sliding doors and door opening force limit
fan area >1.5m2 at 60N, door 5 average
5 door sash and frame or adjacent State
edge parallel 2 1M steel ruler check
6 doors in line vertical, transverse joint
between the slats or fan and box joints limit 2~4 wedge feeler Gage check
7 spring door door leaf and ground
clearance joints limit 2~7
8 door lip sewing is closed flat 2 depth
gauges checked
9 door and window frames (spell-containing
Tang) is 2 1M support vertical, side Board check
10 door and window frames (spell-containing
Tang) level 1.5 1M the level of scale and wedge feeler Gage check
11 horizontal box at 5 with a steel ruler
to check doors and Windows, compared with baseline
12 double doors and Windows inside and
outside the frame, jamb (spell-containing Tang) Center from the 4 with a steel
ruler to check
5 finished product protection
5.1 aluminum alloy doors and Windows should
be kept storage, bottom mat, mat, neatly stacked. On Windows that has been
installed with water, pay attention to storage pads good, prevent damage to the
shed.
5.2 door and window protection film should
check the integrity of the installation, after installation time on both sides
of the door frame using wood, tied good and banned from transporting any of the
window material, to prevent collision damage.
5.3 If the low alkaline cement concrete or
beans when caulking, blocking time after the cement laitance brush to prevent
cement curing bad cleaning, and damage to the surface of the oxide film.
Aluminum alloy doors and Windows before the
caulking, to contact with cement mortar should be brushing preservatives
preservative treatments.
5.4 before plastering the aluminum alloy
doors and Windows should be protected with plastic film in the Interior wet
prior to the completion of any type shall not damage the protective film to
prevent erosion of the surface layer of mortar.
5.5 aluminum alloy doors and Windows should
be in place before removing the protective film, lighter to tear, and
unavailable operating shovel, to prevent scratching the surface is affected.
5.6 surfaces such as aluminum alloy doors
and Windows when there is a jelly, wipe clean cotton yarn stained with special
solvents should be used, such as local scratches, use small brush paint the
contaminated liquid.
5.7 take down the shelf, Interior and exterior
plaster, steel joist installation, pipeline installation and construction
materials transportation process, no rubbing, smashing, Tang touched and
damaged aluminum alloy doors and Windows.
5.8 establish strict protection system of
the finished product.
6 quality problems to be noticed
6.1 when using combination of aluminum
alloy doors and Windows, should pay attention to assembling quality seams
should be formed, spelled Tang box fan do not split hesitated, angle not
channeling.
6.2 spring and handles don't behave size
allowed: reserve hole size should be checked before installation is correct.
6.3 pollution bite: the finished product
protection in construction without note failing to clean up.
6.4 surface scratches: keep clean aluminum
surface dirt with a hard object.
6.5 missing pishui: Windows not loading
shed according to design requirements, use.
7 quality records
This standard shall meet the following
quality records:
7.1 aluminum alloy door and window factory
certificate.
7.2 aluminium alloy door and window parts
and accessories installed, fixed pieces of material evidence and illustration.
7.3 sealed certificate of materials
materials, insulation materials and product certification.
7.4 cement factory certification and test
reports sand in products quality certificate.
7.5 welding rod brand, model number and
certificate.
7.6 quality inspection and assessment of
records.