1, appropriate USES waterproof construction waterproof coating
2, waterproof engineering should be done after take cover engineering construction completion and acceptance
3, waterproof construction to do 2 times after water storage test
4, bathroom waterproof layer should be not less than 1.8 meters
5, floor drain, Yin and Yang Angle, to do a more waterproof in areas such as the pipeline
6, floor drain to use against the stench, floor drain
7, hot and cold water pipes left hot cold right
8, the pipe as far as possible don't walk on the ground
9, cold water pipe in the wall to 1 CM with protection, hot water pipe is 1.5 CM, so deep groove
10, to the thickness of the PPR pipe is good to consider sticking ceramic tile, so the pipe will not come to light
11, cook only for a few minutes, it take long to wash the dishes, water must be going to buy a big one
12, bibcock and basin to form a complete set, lane is bad to can't put up
13, toilet installation cannot use cement, silica gel
After 14, toilet, faucet is installed to protect
15, want to consider when buying a toilet closestool hole spacing
Under 16, washing machine is to consider on drainage or drainage
17, the bathroom had better not telephone, easy to be affected with damp be affected with damp
18 a good size, the mirror in the bathroom, should consider first, otherwise lens headlight is easy to install
19, toilet pipes best manhole
20, consultative services can't wear in the same pipe
21, on the right or left zero phase grounding
22 300, power outlet, switch 1.4 meters
23, switch don't behind the door
24 and outlet should be good
25, high-power electrical appliances with 16 a socket, such as electric oven, etc
26, cassette with good
27, cassette must form a complete set, and the panel installed otherwise could not
28 wire, PVC wire and tube section area shall not exceed 40% of the wire and tube section area
29, air conditioning don't to the bed of the bedroom
30, air-conditioning hole to consider outward tilt, or the rain will come in
31, lamp consider double control as far as possible
32, toilet installation splash best outlet
33, balcony, want to consider a socket
34, wire slot to horizontal flat vertical, lined up, convenient to use in the future
35, common flue check valve is loaded
36, buy electrical appliances must have let workers see instructions
37, instruction manual and warranty card data must be good
Mud work
More than 38 and cement factory period will not be able to use for three months
39, variety, grade cement can not mix
Must be used with river sand, 40, yellow sand mouth to taste
41, floor tile of wall of flooding more than two hours, in order to post
Floor tile of wall of 42, would rather buy a few more, don't buy fewer, otherwise easy to appear off color
43, less than a full brick wall cannot have two rows
44, wipe immediately after the completion of the ceramic tile to clean up
45, ground marble (light color), stone on the back of the waterproof to do
46, Yang Angle to cut 45 degree Angle
47, floor tile should tilt to a floor drain, otherwise easy seeper
48, wall brick encounter apertures to adopt the form of sets of cutting, it looks or the whole piece of brick
49, dry ground marble should be spread
50, floor tile must be to bear or endure dirty, prevent slippery, don't just to look pretty
51, inferior smooth ceramic tile is hard to clean up
52, the balcony floor tile should pay attention to drainage direction
Wood working
53, keel best drying larch
54, large wooden plank is bought sawing dry
55, woodworking horizontal approach to play house
56, design and color panels came in and want to buy a paint brush again, to prevent being dirty
57, ceiling fans cannot be installed on the ceiling keel
In construction of 58, design and color panels to choose color in advance
59 steel hanger distance from the wall, condole supports shall not be greater than 300
60, plasterboard to use countersunk head tapping screws, into the panel 1 ~ 2 mm, antirust processing, and do not use nail gun
61, gypsum board, the distance between the nails shall not be greater than 200
62, plasterboard to 3 mm seam with the wall, for anti-cracking processing
63, plasterboard Yang Angle do best article Yang Angle of protection
64 to brush paint, the wooden door to stir up and down
In 65, the bottom of the toilet door cover to brush waterproof
The size of 66, the door should be consistent
67, try not to make wood furniture, also do not good
68, ambry buy as far as possible the overall, carpentry do bad, not design
In 69, the size must consider good, change is more troublesome
70, do move the door don't dark orbit, later can't repair
71, bathroom small do move the door as far as possible, don't open the door, take a place
72, not sure carpentry must communicate more with the boss, don't let them cool
73, money in the hand is the absolute principle
74, have children in the home, glass to use less
75 good drawings, be sure to let workers
76, kitchen drawer is very useful
77, floor wooden keel flatness is 5 mm
78, MAO paved floor to 30 or 45 degrees, between plate and plate for 2 ~ 3 mm, seam to stagger
79, should stay between floor and wall, 8 ~ 10 mm of seam
80, length of compound floor to consider more than 8 m expansion joints
81, using density board to do less as far as possible the door
82, hinge and hardware must use good
83, bath bully to put on the wooden keel, cannot be directly installed on the ceiling
painter
, dark emulsioni paint when construction in 84, try not to mix into water, otherwise it's easy to have a color difference
85, plasterboard juncture place to the bandage
86 there is crack, metope place want to go to the really cool cloth is better
87, the original wall putty to root out best, or brush glue sealing again
88, as far as possible to buy the famous brand of paint, decorate a company to recommend or recommended by the foreman obsure don't use as much as possible
89, the weather is too wet, don't brush paint
90, paint, paint grinding to wait after dry completely
Before 91, under a paint construction must be conducted after a paint dry
92 on the surface of the metal paint antirust processing to do
93, the weather is too cold, paint construction quality is poor
94, door paint, want to stick with crepe paper hinge and lock
95, it is too hot, pay attention to the ventilation
96, wallpaper, brush oil on the wall
97, wallpaper, to unload the panel of switch and outlet
98, light, the emulsioni paint of mercerized finished at one time, to fill the easy occurrence chromatism
After 99, play crural line installed with latex paint and putty to fill the seam
100, ground glass to protect with a newspaper