Friday, September 23, 2016

Template for shear wall structure wall reinforcement technology

1 scope
The technology is applicable to outer mold, outside the brick mold, complete casting formwork structures such as wall reinforcement project.
2 construction preparation
2.1 materials and equipment:
2.1.1 forming steel or mesh: according to design drawings and specifications, forming steel or spot welding mesh in advance.
2.1.2 reinforcement and support bars: double steel mesh while bound between two pieces of steel reinforcement and support bars, above and below to fix the distance between the bars. See Figure 4-8 (a), (b). Tie bar as shown in Figure 4-8 (a) as shown, and l is the distance between the two networks, lashing vertical and horizontal spacing shall not exceed 700mm. But this form of tie bar to pull not only play a supporting role. In order to ensure correct location wall double-layer tablet, preferably using ladder support bar, as shown in Figure 4-8 (b). Ladder support bar is made of two vertical bars (vertical bars with diameter and height of the wall) and horizontal ribs welded ladder, tied to the wall between the two rows of steel plays a supporting role, spacing about 1200mm. H is the vertical height of the wall in the picture, h for the transverse reinforcement of wall space, and c equal to the wall thickness minus the protective layer of concrete.
2.1.3 wire: use of 20~22 wire (wire) or galvanized iron wire (wire).
2.1.4 control mortar for concrete pads, plastic card.
2.1.5 tools: steel lashing hooks, crowbars, steel panels, racks, trolleys, wire brushes, chalks, rulers, etc.
Figure 4-8
(A) tie bar; (b) the ladder support bar
2.2 operating conditions
2.2.1 checking steel factory certification, the required mechanical properties of the second interview, special circumstances such as when the brittle fracture occurred during processing, the need for chemical testing; mesh processing factory certificate, bars should be no old rust and oil.
2.2.2 reinforcement or spot welding mesh should be stacked at the specified position in the construction plans, network chip while standing with stand, flat pad should be flat, wood, hoisting should use netting installed.
2.2.3 when steel surfaces such as rust, clean prior to binding, rust severely eroded sections of steel shall not be used.
2.2.4 checking the geometry of the mesh sizes, specifications, quantity and spot welding quality, qualified before the use.
2.2.5 brick mold projects must be built up within exterior walls.
2.2.6 binding reinforcement location should be cleaned up.
2.2.7 elastic walls and entrance location line, the loose concrete and reserved bar tick cut clean.
3 operational processes
3.l shear wall with steel binding:
3.1.1 technological process:
Modifications reserved lap bars tied tied transverse reinforcement tied Stud reinforcement or support bars

3.1.2 the wall leave steel bar straightening and straightening out, and clean up the surface of mortar and other debris. First State 2~4 vertical bar and mark the cross bars logo, and on the lower and chest tied to two cross bars at a fixed location, and mark logo on the cross bars and tied the remaining vertical bar, and tied the remaining cross bars.
3.1.3 between double rows of steel tie bar, tie bar diameter not less than 6, spaced not more than 600mm, shear walls strengthened parts of lacing at the bottom should be properly encrypted. Keep the distance of two rows of bars, should adopt binding positioning the ladder support bar, space 1000~1200mm.
3.2 lashing precast shear wall meshes
3.2.1 process
Repair reserve lap bars fixed binding root reinforcement mesh temporary reinforced tied to Windows and doors tie lacing or support bars

3.2.2 wall reserved for steel bar straightening and straightening out, and clean up the debris on the surface. Press print screen in place, mesh set up temporary fixed support using wood after prison. And lap steel lashing by roots, were tied at the ends overlapped parts of the Centre and 3 buckle. Both jambs reinforcing bar binding requirements location accurately. Such as doors and Windows entrance reserved for reinforcement displacement, should be made into a lamp bracket bending (1:6) so that the reinforced door hole location meets the requirements of drawings.
3.3 reinforcement of shear wall lap lap of horizontal reinforcement detailing in the wall as shown in Figure 4-9. Vertical distribution in the wall bar, when the level of seismic shear walls and all parts I and II strengthening parts of the seismic shear walls, reinforced joints should be staggered, every time you connect to does not exceed the number of steel 50%. Other steel shear walls can be lapping at the same site. Lap length comply with design requirements, such as when there is no requirement, shall satisfy the provisions of table 4-8. Method of vertical reinforcement in the wall as shown in Figure 4-10.

Figure 4-9

Figure 4-10
Tensile steel banding lap length table 4-8
Concrete strength
C20 C25 C30
Grade reinforcement 1 35d (30D) 35d (30D) 35d (30D)
2 grade steel (Crescent-shaped) 45d 40D 35d
3 grade steel bar (Crescent-shaped) 55d 50d 45d
Note: l. When level and steel bar d>25mm, whose lap length can be increased according to the number in the table 5d.
2. when the rebar diameter 25mm, the tensile reinforcement, lap length reduced by values in the table 5d.
3. figures in parentheses lap length of welded mesh.

3.4 scissors the anchoring wall bar
3.4.1 shear walls with anchorage according to the design requirements of the horizontal steel bars in construction. Dark posts or add bars, as described in Figure 4-11 (a), (b).
Figure 4-11
BW-cutting width; la-anchorage length
3.4.2 horizontal reinforcement of shear walls in "small" Byte and lashing of anchorage of corner node, as described in Figure 4-12, 4-13.
4-12 4-13
3.4.3 the coupling beam of shear wall length of horizontal steel bar into the wall e ' must not be smaller than the design requirements, as described in Figure 4-14 (a), (b).
3.4.4 shear-wall connecting beam along the beam length of hoop structures to meet the design requirements, on the top floor of a building even within the length of the steel beams into the wall, spacing should be no less than 150mrn construction of stirrup, as described in Figure 4-15.
3.4.5 wall opening reinforcing steel banding around, the anchorage length shall conform to the design requirements.
3.5 reinforcement of shear wall with precast wall panel connections: install wall panel in place, this layer shear wall column insert external wall of prefabricated vertical reinforcement plate steel rings, shaft reinforcement insert rings shall not be less than 3 wall panel and tie firmly. Refer to figure 4-16.
3.6 out of shear walls with brick wall connection: when tied up within the walls, first reserved for exterior wall φ 6 tie bar straightening out, and then within the walls overlap tied, as described in Figure 4-17 (a), (b).
3.7 all casting wall reinforcement connection binding construct, refer to figure 4-18.

3.8 fixed: template after the closing, to trim the wall bars protruding, and tied up a temporary horizontal bars fixed the spacing out of the bar (left rib spacing). Wall concrete special care when rebar, pouring out, immediately out of the bar (left bar) for finishing.
4 quality criteria
4.1 project:
4.1.1 varieties and properties of steel, electrode grades, performance and joint use of steel sheet and steel must comply with the design requirements and the provisions of the relevant standard.
4.1.2 reinforced with granule and Flake old rust, rust steel pits after, according to the original specifications is strictly prohibited. Steel surfaces should be kept clean.
4.l.3 bar sizes, shapes, sizes, quantity, the anchorage length, connector set, you must meet the requirements of specification for design and construction.
4.1.4 results of mechanical properties test of welded joints, welding code requirements must be met.
4.2 Basic project:
4.2.1 steel mesh frame and tie missing clasp, tie loose quantity does not exceed 10% of buckle, and should not be set.
4.2.2 reinforcement mesh leakage welding, welding does not exceed 2% of the welding points, and should not be set.
4.2.3 hook toward the right. Lashing fittings shall conform to the provisions of the code, where each joint of the lap length is not less than the specified value.
4.2.4 number of Stirrups, hook angle and straight length should comply with the design requirements and the provisions of the code.
4.2.5 steel spot welding molten metal at the point where even, no defects such as cracks, holes and burned. Solder indentation depth in accordance with provisions of the reinforcing bar welding procedures.
Welding: no transverse cracks and burns, uniform welding package joint bending, not more than 4 ° axis displacement is not greater than 0.1d and less than 2mm.
Arc-welded weld surface, no dents, welding tumor, crack, blowhole, slag and undercuts, bent connector is not more than 4 ° axis displacement is not greater than 0.1d and less than 3mm, width not less than 0.1d, the length is not less than 0.5d.
Allowable deviation, see table 4-9
Reinforcement and embedded parts tolerance table 4-9
Project tolerance (mm) test method
1 Web length, width of ± 10 ' check

Welding ± 10
Lashing ± 20

Distance ± 10
Distance ± 5

Welding ± 10
Lashing ± 20

Center line 5
High levels of differential +3-0
Mechanical reinforcement protection layer 6-foot check

5 finished product protection
5.1 collision embedded parts is strictly prohibited when binding reinforcement, such as touch design location should be fixed firmly.
5.2 assurance embedded conduit location accurately, such as when a conflict occurs, vertical bars along a plane can be bent around, transverse reinforcement bending, bypass the buried piping. But make sure that the thickness of the protective layer is strictly prohibited any cut steel.
5.3 template Panel brush isolated agent, non-polluting steel.
5.4 the types of operators are not allowed to any pedal step on the steel, snapping and cutting steel.
6 quality problems to be noticed
6.1 horizontal position, spacing does not meet the requirements: wall binding reinforcement should take Gordon or a simple scaffold to prevent horizontal displacement.
6.2 wall protruding lower vertical reinforcement with steel and does not meet the requirements: binding should first lower wall out of steel bar straightening and straightening out, then tying or welding. Reinforcement displacement of the lower reach out when the consent of the design process.
6.3 jambs rib dimensions do not meet the requirements: prior to binding adjustment based on where the hole edge stiffener, lashing the stiffener should wait for alignment.
6.4 level anchorage of shear wall length does not meet the requirements: studying the drawings. Right around the corner, cross point, wall end, steel anchor beams parts should comply with the design requirements.
7 quality records
This standard shall meet the following quality records:
Steel quality certificate or test report 7.1.
7.2 mechanical properties of steel test reports.
7.3 import steel chemical composition and solderability test report the test report. Domestic steel processing, poor performance or occurrence of brittle fracture, welding and mechanical properties significantly abnormal, chemical composition inspection report.
7.4 welded test report.
7.5 welding electrode and flux certificate.
7.6 forming mesh factory certificate.
7.7 bars covert acceptance record.

7.8 steel bar sub-item project quality inspection and evaluation of information.
Because of the war, many people become homeless. I can't do it well. Please help me.my PayPal is xhhnet@163.com.

No comments:

Post a Comment