1 scope
This technology is applicable to general
industry and civil architecture wall granitic plaster, water brushes bean stone
construction.
2 construction preparation
2.1 materials and equipment:
2.1.1 cement: No. 325, cement or Portland
cement and above, same color, should be used with the batch of products.
2.1.2 sand: sand. 5mm before using the
sieve of aperture.
2.1.3 gravel: solid particles shall not
contain harmful substances such as clay and other organic matter. Gravel
specification, the specification requirements, grading should comply with the
design requirements, eight per cent to 6mm, small eight per cent to 4mm. Wash
before use, according to specifications, colours and Marshall dry, stacked,
sheet cover for later use. Requirements consistent with gravel color, should be
delivered.
2.1.4 the small stone: size 5~8mm is
appropriate, clay is less than 1%, with the first two times we have sieve,
rinse with water and set aside.
2.1.5 lime cream: one month before using
lime 3mm sieve, pour into lime paste, available in gypsum mortar should not
contain particles and other impurities that are not cured.
2.1.6 lime: using water to stew through the
week before their full ripening, when used shall not contain curing particles
at the end.
2.1.7 other materials: 107 gum, YJ302
interface treatment agent and fly ash.
2.1.8 pigments: good alkali resistance and
light resistance of mineral pigments.
2.1.9 equipment should be equipped with
hand pump 2~3 (according to the amount of brushed stone and construction staff
size), wood float, large bar, mini bar, feet, feet, steel trowel, son of
pressure, paste pots, large (small) bucket, soft (or hard)-hair brush,
chopsticks, and so on. Plastering tools such as car, Gray Ash bucket, small
barrels, iron and so on.
2.2 operating conditions:
2.2.1 structure project has been accepted.
Construction requirements 2.2.2 ready to
double exclusive shelf or basket, bridge-type frame. The pole away from the
wall 20cm shelf to guarantee operation. Feet best not left hand-eye on the wall
to prevent secondary repair, resulting in wall of flowers.
2.2.3 reserved holes and disposed of
through embedded pipe wall. Waterproof finish a wall cavity and tricking water
test without leakage, check. Install Fixed door and window frames, and gap
plugging tight with the 1:3 cement mortar.
2.2.4 clean walls, walls of raised concrete
should tick. Recessed 1:3 cement mortar layer fill.
2.2.5 granitic plaster should be done
before construction of large area model to determine the mix proportion and
construction technology, obliges the person unified ingredients, and mix
control.
3 operational processes
3.1 process:
Caulking around doors and Windows (precast
concrete exterior wall cavity Board slot) → wall cleaning →
Watering moist walls (wall cavity slot
tricking water test) → hanging vertically, set the rules, plaster cakes, Chong tendons →
Tiered bottom mortar → elastic → line → cell
adhesion, drop gravel pulp
Repeated massage flushing shoot compaction → → iron trowel
calendering, washed with hand pump wash stone →
Size pot bottom riffle in rinse,
water-cement pastes caulking
3.2 base for concrete external wall:
3.2.1 primary processing: cutting hair on
the surface of the concrete plate surface net meringue tick, dust brush off
with a wire brush, rinse, water moist; 10% caustic soda water to the concrete
surface with oil and dirt brush, rinse and dry, spray or dump 1:1 fine 20% 107
glue a cement mortar mixed with water consumption. End gel Hou watering
conservation, until mortar and concrete Board stick prison (with hand broke
mortar not off), party can for playing end of; or used YJ302 concrete interface
processing agent on grass-roots for processing, its operation method has two
species: first species, in cleaning clean of concrete matrix Shang, brushing
"processing agent ° a, immediately follow with wipe cement mortar,
requirements wipe gray Shi processing agent cannot dry. Second, just after
finishing the treatment agent sprinkle a layer of sand particle size 2~3mm to
increase the roughness of the concrete surface, until dry and hard of a base.
3.2.2 hanging vertically. Sets of rules: If
the multi-storey buildings, using special cable hanging down from the top of
the vertical, and after the guy wire, wire vertical requirements at Tai Kok,
doors, plastering holes on both sides of layered cake. If the top should point,
jambs and theodolite used in vertical vertical line and line layered plaster
cake to find rules, horizontal direction to achieve the smooth consistency.
3.2.3 the underlying mortar: elevation of
above the ash cake gluten-filled, brush 10% 107 adhesive mud mixed with water,
immediately followed by layers and underlying mortar, mixing ratio can be
chosen at the end of 1:l:6 at room temperature (mixing mortar) or 1:0.5:0.5:6
(fly-ash mortar mix), hit bottom with tie bar anyway, scrape and rub wood
trowel. After the final setting of water conservation.
3.2.4-line grid, cell adhesion, water:
according to the drawing size line, sticky, cells in epithelia to be flat,
horizontal even vertical lines circles counterparts. And according to the
specifications of part set drop.
3.2.5 wipe cement gravel pulp surface
layer: scraping a within mixed 10% of 107 glue mud, follow with wipe 1:0.5:3
(cement: lime cream: small eight PCT) gravel pulp, bottom-up points two again
and points grid article wipe flat, and timely with small bar check its flat
degrees (wipe gravel layer to above points grid article LMM), then will gravel
laminated flat, and pressure real.
3.2.6 trimmed and painted: Pat down will
have good gravel surface compaction, will it cement slurry extrusion water
brush dipped in water to grout brush, compacted again clear, repeated 3~4 times
until the surface starts to gel, na no trace water brushes off the stone tablets
for the degree. A brush with brush dipped in water to the cement slurry, one
followed by the top down using hand pressure pump sprayer spray rinse, spray
distance wall 10~20cm, cement wash out after the gravel surface, and finally a
smaller water rinse the gravel surface. After wall moisture control, grid, and
timely with cement plaster caulking.
3.2.7 operation program: soft face doors
and Windows, Bay Windows, balconies, rain cover and other parts to brush the
stone should be small and big, to ensure that the surfaces are clean and
beautiful. Brushes Shi Yang corner, shower outside wash, and finally a smaller
water rinse. Soft face cornices, window sill, balcony, rain cover and other
surfaces should be done by the end of drip, width at top 7mm, width under 10MM,
dark 10MM, not less than 30mm from the skin. Large stone wall brush one day to
finish, before continued scouring a new live. Brushed stone to do the night
before should be soaked with water, and after for spraying brush when wet mud
is easy to clean, prevent pollution, wall. Wrong should be left on the grid
slot.
3.3 base for brick walls:
3.3.1 base treatment: the plaster dust and
dirt on the front grass-roots clean up, plug for hand-eye coordination, water
wetter.
3.3.2 hanging vertically, set the rules:
from the top layer with a special line, stretched wire hanging straight, then
layering plaster cakes, angle of yin and Yang, on either side of the window,
column, Duo, etc should be hanging straight, stretched wire, good ash cakes and
filled bars.
3.3.3 the underlying mortar: at room
temperature, mix it with 1:0.5:4 mortar or 1:0.3:0.2:4 mixed with fly ash
mortar base, plastering gluten-filled to control the thickness of the plaster
should be layered and loaded until the erase bar. Requested heading back again
when ash. Mortars into their bond in the mortar joints, leveling the surface
rubbing hair, water conservation after the final set.
3.3.4 playing line, divided into cells,
cell adhesion, water: according to the drawing size line grid, cell adhesion,
and cells to horizontal even vertical circle, drop of paste should be according
to the specifications and drawings parts, and should be straight.
3.3.5 gravel-cement paste: scraping
together of 10% 107 glue a cement slurry mixed with water consumption, and
gravel 1:0.5:3 cement slurry, should wipe from bottom to top to the thickness
of the grid, and feet with leveling, concave handle compacted after leveling,
pressed, shooting up to the gravel on the face.
3.3.6 dressing, and spray brush: will has
wipe good of gravel surface layer took flat pressure real, will its water mud
extrusion, water brush dipped water will water mud brush to, again pressure
real clear, repeatedly for 3~4 again, stay surface layer began early gel,
refers to NA no marks, with brush brush not off gravel for degrees, a people
with brush dipped water brush to cement pulp, a people follow with with hand
pressure pump nozzle by Shang down order spray water scrub, nozzle General from
wall 10~20cm, put surface water mud flush clean show gravel, last with small
Kettle watering will gravel rushed NET, After wall moisture control, grid, and
timely with cement plaster caulking.
3.3.7 operation program: soft face doors
and Windows, window sills, balconies, rain cover and other parts brushes Shi
Xian small and big, to ensure that the walls are clean and beautiful. Brushes
Shi Yang corner applicators should wash from the outside, and finally a smaller
water rinse. Cornice, window sill, soft face, balconies, rain hood bottom
should do throat, wide on 7mm, down width 10MM, dark 10MM, not less than 30mm
from the skin. Large stone wall brush finish a day, such as the need to
continue construction, washing should be done the day before before the new
live paint stone wet with water, for when spray is easy to clean after wet mud,
pollution prevention wall.
3.4 winter rain during construction:
3.4.1 construction in winter to prevent the
ash layer from the cold, should not be mixed with lime in the mortar paste, in
order to ensure the workability of the mortar, the same volume of fly ash can
be used instead. Such as playing ash mixing ratio 1:0.5:4 can be used (cement
fly ash: sand) 1:3 cement mortar or cement gravel mixture mixing ratio 1:0 can
be used ... 5:3 (cement fly ash: gravel) or to 1:2 gravel-cement slurry used.
3.4.2 plastering mortar using hot water
mixing and take measures, when applied mortar temperature should not be below +
5 c.
3.4.3 plastering layer's early hardening
without freezing.
3.4.4 to enter construction before winter,
should be mixed with mortar admixture reduces freezing, plus calcium chloride
or sodium chloride, the dosage should be adjusted according to the atmospheric
temperature to 7:30, mortar, additive dosage.
3.4.5 of freezing method masonry walls,
exterior plaster should be completely thawed before wiping, shall not be washed
with hot water freeze walls with hot water or elimination of wall of frost.
3.4.6 winter stage construction.
3.4.7 construction taking the rain rain
protection measures, has just completed a brushed stone walls such as the case
when heavy rains washed, should pay attention to block to prevent damage.
4 quality criteria
4.1 project:
4.1.1 the variety and quality of the
materials used must comply with the design requirements.
4.1.2 the plaster layer and must bond
between plaster layer and the substrate, no delamination, hollowing and cracks
and other defects.
4.2 Basic project:
4.2.1 surface: the stone tablets of clear,
uniform distribution, close formation, consistent color, no trace of grain and
Cha.
Section 4.2.2 (seam): uniform width and
depth, (seam) is flat and smooth, Leng corners neatly, horizontal even
vertical, smooth.
4.2.3 drop line (slot): flow direction is
correct, drip line straight, throat width and depth is not less than 10MM, neat
and consistent.
4.3 allowable deviation, as shown in table
9-5.
Granitic plaster wall surface tolerance
table 9-5
Project tolerance (mm) method
1 façade vertical 5 2m supporting plate
check
2 smooth 3 2m m on foot and wedged feeler
Gage check
Angular vertical 4 3 Yin and Yang with 2m
supporting plate check
4 corner square 3 Yin and Yang with 2cm
feet and wedged feeler Gage check
5 foot Dado head straight 3 5M line and
check
6 minutes straight 3 5M line and standard
inspections
7 full height vertical single-layer,
multi-layer h ≤ 20 ‰ and transit checks
Full height vertical top h ≤ 30 ‰ and transit
checks
5 finished product protection
5.1 stuck to the door and window frames and
brick mortar should be cleared in a timely manner. Aluminum alloy doors and
Windows should be promptly stick protective film to prevent contamination.
5.2 when spray plastic mulch well let's
give wall to prevent contamination. Especially windy day more carefully
protected and covered.
5.3 building after the import and export of
granitic plaster well let's give, should be nailed to wood protection angle,
preventing the broken edges.
5.4 remove shelves and Interior and
exterior cleanup, not to damage the glazing and contamination and water
brushing stone walls.
5.5 painters brush oil tank should be take
care not to over contaminated walls, brush for have stone sills and convex
lines, should be protected, do not pedal step on the damage.
6 quality problems to be noticed
6.1 gray layer bond not prison, and empty
drum: reasons is grass-roots not watering wet; grass-roots didn't cleanup or
cleanup not clean; each layer gray with have too tight or once wipe gray too
thick; playing end of Hou didn't watering conservation; prefabricated concrete
outside wall board too smooth, and grass-roots didn't "hair of"
processing; board surface crisp skin not tick chisel clean; points grid article
sides empty drum is because up article Shi will gray layer pulled crack. Should
pay attention to the grass-roots level of cleaning, watering each ash plastering
layer thickness is not too thick; the end of grey 24h attention to water
conservation. Precast concrete wall panels must be clear and crisp the skin,
and "texture".
6.2 the wall dirty, color inconsistencies:
brush to erase stone walls not compacted, pit water in mud not rinse rinse or
final use; a stock of raw materials is not enough; mixture ratio of cement or
gravel, different colors or no gradation is not consistent. Erase operation
should be repeated when kneading, where its uneven, and finally washed clean
with water. Request brush mix has special master of stone, cement, gravel
should be prepared.
6.3 crack, crack: due to uneven surface
depth, scouring thin junction because of different weight fall when cracked,
dry cracks enlarge live a few times is not enough, ash layer compacting is also
easy to form lines or cracks; gravel with unripened grain, volume expansion of
water surface burst. Required hits bottom ash flat, surface construction must
be in accordance with standard side brush the water pressure, until the surface
compaction and light so far.
6.4 rot: brushing stone and apron and waist
line and other contact surface is not clean, there is debris on the surface, to
be formed after debris clean roots due to bottom construction, live a few times
is not enough, ash layers do not compact, formed after the flush dregs or local
gravel is not dense. Brushing stone and apron and waist contacts clean; brushed
stone root construction should be carefully and seriously.
6.5 negative pollution angle brush, stone,
stone wall brush, opacity, not clear: internal corner do both sides brushed
stone in two, then brush side brush earlier side of pollution. Entire wall
pieces, done after a, scrub pollution have been doing a piece of both sides of
the internal corner to find rules, once made and painted. On the large stone
wall brush, to prevent pollution, in front of the stone after scouring brush,
brush stone will be ready first flush clean with water and moist, then scour
new brushes Shi, new living is completed, then rinse with clean water ready to
brush the stone, prevent pollution caused by washing dirty, muddy.
6.6 brushes Shi Cha confusion, the overall
effect is poor: brushes Shi cha in the child should remain in the compartment,
or behind the waterspout, or decorations at the edge of independence, must not
remain in the block.
7 quality records
This standard shall meet the following
quality records:
7.1 cement factory prove and test reports.
7.2 certificates of quality of sand and mud
content report.
7.3 quality certificates such as gravel,
little pea stone.
7.4 certificate of lime, fly-ash factory.
7.5 other materials: 107 gum, factory
certificate of treatment and how to use the YJ302 interface.
7.6 quality inspection and assessment of
records.