Tuesday, April 11, 2017

Plastic floor paving process

Plastic floor paving process

1. Laying the main construction process of plastic flooring.



(1) semi-rigid plastic flooring:

Grass-roots treatment → elastic line → plastic floor degreasing dewaxing → pre-shop → scraping gum → towel → rolling → conservation.

(2) soft plastic floor:

Grass-roots treatment → elastic line → plastic floor degreasing dewaxing → pre-laying → groove cutting → scraping glue → paste → welding → rolling → conservation.

(3) Coil Plastic Flooring:

Cutting → grass processing → elastic → scraping glue → paste → rolling → conservation.

2. Construction points.

Grass should reach the surface can not afford the sand, can not afford to skin, can not afford to gray, no hollow, no grease. No touch of rough feeling. Do not meet the requirements, should first deal with the ground.
Pop up each other perpendicular to the positioning line, and according to the pattern of pre-shop embroidery pattern.

Grass and plastic floor block at the same time the same side of the plastic, plastic surface sticky hands can be paving.

Each piece of the block after the pieces will be squeezed out of the plastic in time to clean up with cotton wire.

Pavement is completed, to clean up the floor surface in time, the use of water-based adhesive can be wiped with a damp cloth, the use of solvent-based adhesives, the application of turpentine or gasoline to remove rubber marks

Floor blocks should be defatted and dewaxed before paving.

3. Precautions

(1) for the adjacent two rooms lay different colors, pattern plastic floor, the separation line should be in the door frame outside the door line, so that the door floor symmetry.
(2) paving, the use of rubber hammer from the middle to the percussion, the bubble catch the net.
(3) 3 days after the shop can not be superior.
(4) PVC floor roll should be 3 to 6 days before paving cutting, and leave a margin of 0.5%, because the plastic after cutting a certain degree of contraction.